MONTHYEARML20248B2371998-03-31031 March 1998 Revised Monthly Operating Rept for March 1998 for Indian Point Station Unit 2 ML20029C7801994-03-31031 March 1994 Monthly Operating Rept for Mar 1994 for Indian Point Unit 1. W/940415 Ltr ML20247G5171989-04-30030 April 1989 Monthly Maint Category I Rept Pages from Monthly Operating Rept for Apr 1989 for Indian Point ML20154M5661988-08-31031 August 1988 Monthly Operating Rept for Aug 1988 for Indian Point Station Unit 2 ML20154M5691988-07-31031 July 1988 Revised Page to Monthly Operating Rept for Jul 1988 for Indian Point Station Unit 2 ML20236P9861987-10-31031 October 1987 Monthly Operating Rept for Oct 1987 ML20235Y9681987-09-30030 September 1987 Monthly Operating Rept for Sept 1987 ML20236A5811987-09-30030 September 1987 Monthly Operating Rept for Sept 1987 ML20234D7771987-08-31031 August 1987 Monthly Operating Rept for Aug 1987 ML20237J6511987-07-31031 July 1987 Monthly Operating Rept for Jul 1987 ML20235U7571987-06-30030 June 1987 Monthly Operating Rept for June 1987 ML20215F3711987-05-31031 May 1987 Monthly Operating Rept for May 1987 ML20214H5111987-04-30030 April 1987 Monthly Operating Rept for Apr 1987 ML20214E9541987-04-30030 April 1987 Monthly Operating Rept for Apr 1987 ML20206Q6951987-03-31031 March 1987 Monthly Operating Rept for Mar 1987 ML20206R6201987-03-31031 March 1987 Monthly Operating Rept for Mar 1987 ML20207T1321987-02-28028 February 1987 Monthly Operating Rept for Feb 1987 ML20207R6861987-02-28028 February 1987 Monthly Operating Rept for Feb 1987 ML20206R6451987-02-28028 February 1987 Revised Monthly Operating Rept for Feb 1987 ML20211E1381987-01-31031 January 1987 Monthly Operating Rept for Jan 1987 ML20211J1481987-01-31031 January 1987 Monthly Operating Rept for Jan 1987 ML20212P8891986-12-31031 December 1986 Monthly Operating Rept for Dec 1986 ML20207P9801986-12-31031 December 1986 Monthly Operating Rept for Dec 1986 ML20215E8501986-11-30030 November 1986 Monthly Operating Rept for Nov 1986 ML20211Q0501986-11-30030 November 1986 Monthly Operating Rept for Nov 1986 ML20212L9131986-10-31031 October 1986 Monthly Operating Rept for Oct 1986 ML20214D0211986-10-31031 October 1986 Monthly Operating Rept for Oct 1986 ML20203P1081986-09-30030 September 1986 Monthly Operating Rept for Sept 1986 ML20209J0801986-08-31031 August 1986 Monthly Operating Rept for Aug 1986 ML20214K4281986-07-31031 July 1986 Monthly Operating Rept for Jul 1986 ML20207C3021986-06-30030 June 1986 Monthly Operating Rept for June 1986 ML20207C3171986-06-30030 June 1986 Monthly Operating Rept for June 1986 ML20211F7351986-05-31031 May 1986 Monthly Operating Rept for May 1986 ML20198A2731986-04-30030 April 1986 Monthly Operating Rept for Apr 1986 ML20205P6911986-04-30030 April 1986 Monthly Operating Rept for Apr 1986 ML20141E6071986-03-31031 March 1986 Monthly Operating Rept for Mar 1986 ML20141E6121986-03-31031 March 1986 Monthly Operating Rept for Mar 1986 ML20140B8481986-02-28028 February 1986 Monthly Operating Rept for Feb 1986 ML20154P0171986-02-28028 February 1986 Monthly Operating Rept for Feb 1986 ML20141D2331986-01-31031 January 1986 Monthly Operating Rept for Jan 1986 ML20153E3491986-01-31031 January 1986 Monthly Operating Rept for Jan 1986 ML20140B8541986-01-31031 January 1986 Rev I to Monthly Operating Rept for Jan 1986 ML20140A8211985-12-31031 December 1985 Monthly Operating Rept for Dec 1985 ML20141J1861985-12-31031 December 1985 Monthly Operating Rept for Dec 1985 ML20138P4981985-11-30030 November 1985 Monthly Operating Rept for Nov 1985 ML20138M5941985-11-30030 November 1985 Monthly Operating Rept for Nov 1985 ML20136E8811985-10-31031 October 1985 Monthly Operating Rept for Oct 1985 ML20138J7921985-09-30030 September 1985 Monthly Operating Rept for Sept 1985 ML20205C7241985-08-31031 August 1985 Monthly Operating Rept for Aug 1985 ML20134F6881985-07-31031 July 1985 Monthly Operating Rept for Jul 1985 1998-03-31
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARML20217H8501999-10-14014 October 1999 Safety Evaluation Supporting Amend 197 to License DPR-64 ML20206U2551999-02-0909 February 1999 Safety Evaluation Supporting Amend 187 to License DPR-64 ML20236Y1571998-08-0303 August 1998 Part 21 Rept Re ASTM A351,GR. CF8 Matl at Indian Point Being Out of Specifications in Molybdenum & Chromium.Cause & Corrective Actions Are Not Stated ML20236V4281998-07-13013 July 1998 Safety Evaluation of TRs WCAP-14333P & WCAP-14334NP, PRA of RPS & ESFAS Test Times & Completion Times. Repts Acceptable ML20236T5511998-06-24024 June 1998 Consolidated Edison Co of Ny,Indian Point Unit 2,Drill Scenario Number 1998C ML20248B2371998-03-31031 March 1998 Revised Monthly Operating Rept for March 1998 for Indian Point Station Unit 2 ML17264A9381997-07-10010 July 1997 Deficiency Rept Re Potential Safety Hazard Associated w/FM-Alco 251 Engin,High Pressure Fuel tube-catalog: 4401031-2 in Which Dual Failure Mode Exists.Caused by Incorrect Forming Process ML18153A1431997-06-10010 June 1997 Part 21 Rept Re Possible Machining Defect in Certain Stainless Steel Swagelok Tube Fitting Bodies.Facilities Have Been Notified About Possible Problem ML20210E3591997-03-27027 March 1997 Part 21 Rept Re Sorrento Electronics Inc Has Determined Operation & Maint Manual May Not Adequately Define Requirements for Performing Periodic Surveillance of SR Applications.Caused by Hardware Failures.Revised RM-23A ML1005008001997-02-28028 February 1997 Conditional Extension of Rod Misalignment TS for Indian Point 3. ML20115J3981996-07-22022 July 1996 Interim Part 21 Rept Re 3/4 Schedule 80 Pipe Furnished to Consolidated Power Supply.Investigation Revealed Only One Nuclear Customer Involved in Sale of Matl ML20096E5101995-12-31031 December 1995 Resubmitted Rev 13 to QA Program ML17059A3611994-07-0606 July 1994 Emergency Action Level Verification & Validation Rept. ML17311A0181994-05-13013 May 1994 New York State EAL Upgrade Project Verification & Validation Rept. ML20029C7801994-03-31031 March 1994 Monthly Operating Rept for Mar 1994 for Indian Point Unit 1. W/940415 Ltr ML20056E5171993-08-31031 August 1993 Technical Review Rept, Tardy Licensee Actions ML20062J2281993-07-23023 July 1993 Consolidated Edison Co of Ny Indian Point Unit 2,Drill Scenario 1993 ML20118A2681992-12-31031 December 1992 Consolidated Edison Co of Ny Indian Point,Unit 2 Exercise Scenario,1992 ML20125C7161992-12-0707 December 1992 Part 21 Rept Re Possibility for Malfunction of Declutching Mechanisms in SMB/SB-000 & SMB/SB/SBD-00 Actuators. Malfunction Only Occurs During Seismic Event.Balanced Levers May Be Purchased from Vendor.List of Affected Utils Encl ML20127P5861992-11-23023 November 1992 Followup to 921005 Part 21 Rept Re Potential Defect in SB/SBD-1 Housing Cover Screws.Procedure Re Replacement of SBD-1 Spring Cover Bolts Encl.All Fasteners Should Be Loosened & Removed.List of Affected Utils Encl ML20096H2301992-05-21021 May 1992 Special Rept:On 920504,south Side Lower Electrical Tunnel Detection Sys 8 Taken Out of Svc for Mod to Reposition Detection Sys Run of Conduit.Detection Sys Declared Operable on 920520 After Mod Completed & Sys Retested ML20079F9181991-05-31031 May 1991 Structural Evaluation of Indian Point,Units 2 & 3 Pressurizer Surge Lines,Considering Effects of Thermal Stratification ML20059E9461990-08-31031 August 1990 Nonproprietary Rev 2 to Indian Point 2 Tube Fatigue Reevaluation ML20059G2011990-07-31031 July 1990 Final Rept on Steam Generator Insp, Repair & Restoration Efforts During 1990 Midcycle Insp ML20058K4151990-06-30030 June 1990 Steam Generator Insp,Repair & Restoration Program Presentation to Nrc ML20058K4121990-06-30030 June 1990 Status Rept,Indian Point Unit 2 Mid-Cycle Steam Generator Insp Presentation to Nrc ML20043A4891990-05-30030 May 1990 Nonproprietary Indian Point Unit 2 Steam Generator Insp, Repair & Restoration Program. ML20042F1441989-12-31031 December 1989 New York Power Authority Annual Rept for 1989. W/900430 Ltr ML19332B9371989-11-30030 November 1989 Nonproprietary Info Presented to NRC Re Indian Point Unit 2 Steam Generator Secondary Side Loose Objects. ML19332D6661989-10-31031 October 1989 Nonproprietary Rev 2 to Indian Point Unit 2 Steam Generator Girth Weld/Feedwater Nozzles Rept Spring,1989 Outage. ML20247J8161989-07-31031 July 1989 Safety Evaluation for UHS Temp Increase to 95 F at Indian Point Unit 3 ML20248B3171989-06-30030 June 1989 Rev 1 to Nonproprietary WCAP-12294, Indian Point Unit 2 Steam Generator Girth Weld/Feedwater Nozzles Rept,Spring 1989 Outage ML20248D3631989-06-30030 June 1989 Rev 1,to Indian Point Unit 3 Reactor Vessel Fluence & Ref Temp PTS Evaluations ML20247N5331989-05-31031 May 1989 Nonproprietary Indian Point Unit 2 Steam Generator Girth Weld/Feedwater Nozzles Rept Spring,1989 Outage ML20247J8071989-05-31031 May 1989 Containment Margin Improvement Analysis for Indian Point Unit 3 ML20247G5171989-04-30030 April 1989 Monthly Maint Category I Rept Pages from Monthly Operating Rept for Apr 1989 for Indian Point ML20244C3311989-04-10010 April 1989 Safety Evaluation Supporting Amend 137 to License DPR-26 ML20248F4211989-03-31031 March 1989 NSSS Stretch Rating-3,083.4 Mwt Licensing Rept ML20235V5931989-03-0202 March 1989 Special Rept:During Cycle 6/7 Refueling Outage Scheduled from Feb-May 1989,openings Will Be Made in Plant Penetration Fire Barriers in Order to Install Various Mods. Fire Watches Posted & Fire Detection Tests Completed ML20248F3001988-12-31031 December 1988 10CFR50.59(b) Rept of Changes,Tests & Experiments Completed in 1988 ML20246E2711988-12-31031 December 1988 Con Edison 1988 Annual Rept ML20196D3011988-10-31031 October 1988 Reactor Vessel Matl Surveillance Program for Indian Point Unit 2 Analysis of Capsule V ML20155H2541988-09-30030 September 1988 Rev 2 to Indian Point Unit 2 (NRC Bulletin 88-008 Thermal Stresses in Piping Connected to RCS) Indentification of Unisolable Piping & Determination of Insp Locations ML20154M5661988-08-31031 August 1988 Monthly Operating Rept for Aug 1988 for Indian Point Station Unit 2 ML20154M5691988-07-31031 July 1988 Revised Page to Monthly Operating Rept for Jul 1988 for Indian Point Station Unit 2 ML20151N7881988-07-31031 July 1988 Rev 1 to Charpy Toughness & Brittle Transition Temp Characterization of HAZ High Hardness Zone of Indian Point Unit 2 Steam Generator Girth Weld by Gleeble Weld Thermal Cycle Simulation ML20006B4741988-05-31031 May 1988 Nonproprietary Indian Point Unit 2 Evaluation for Tube Vibration Induced Fatigue. ML20151N7821988-05-31031 May 1988 Fracture Sensitivity Study of Girth Weld 6 Repaired Configuration,Indian Point Unit 2 ML20153F9161988-04-28028 April 1988 Changes,Tests & Experiments - 1986 ML20151T4681988-01-31031 January 1988 Experimental & Finite Element Evaluation of Spent Fuel Rack Damping & Stiffness 1999-02-09
[Table view] |
Text
_ . _ _ . _ _ _ _ _ . __ __
OPERATING DATA REPORT DOCKET NO. 50-286 DATE guly 1, 1983 COMPLETED BY T>. Kellv TELEPHONE (914) 739-8200 )
OPERATING STATUS Notes
- 1. Unit Name: Indian Point No. 3 Nuclear Power Plant
- 2. Reporting Period: June 1983
- 3. Licensed Thermal Power (MWt): 3025
- 4. Nameplate Rating (Gross MWe): 1013
- 5. Design Electrical Rating (Net MWe): 965
- 6. Maximum Dependable Capacity (Gross MWe): 1000
- 7. Maximum Dependable Capacity (Net MWe): 965
- 8. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report. Give Reasons:
Main Turbine Modified. replaced blades nreviousiv removed. l
- 9. Power Level To Which Restricted,If Any (Net MWe):
- 10. Reasons For Restrictions.If Any:
This Month Yr..to.Date Cumulative
- 11. Hours la Reporting Period 720 4343.0 59,904.0
- 12. Number Of Hours Reactor Was Critical 333.7 333.7 34,424.5
- 13. Reac:or Reserve Shutdown Hours 0 0 0
- 14. Hours Generetor On Line 229.1 229.1 33,142.2
- 15. Unit Reserve Shutdown Hours 0 0 0
- 16. Gross Thermal Energy Generated (MWH) 282,244 282,244 86,425,645
- 17. Cross Ele:trical Energy Generated (MWH) 68,310 68,310 26,366,610
- 18. Net Electrical Energy Generated (MWHg 60,735 60,735 25,244,178 l). Unit Service Factor 31.8 5.3 55.3
- 20. Unit Availability Factor 31.8 5.3 55.3
- 21. Unit Capacity Factor (Using MDC Net! 8.7 1.5 43.7
- 22. Unit Capacity Factor (Using DER Net) 8.7 1.5 43.7
- 23. Unit Forced Outage Rate 56.6 56.6 14.5
- 24. Shutdowns Scheduled Over Next 6 Months (Tyx. Date.and Duration of Each):
25 If Shut Down At End Of Report Period. Estimated Date of Startup: (Est. January 1984) 26 Units in Test Status iPrior to Commercial Operation): Forecast Achieved INITIAL CRITICALITY INITIAL ELECTRICITY ,,-[
r COMMERCIAL OPERATION u308110210 830701
-gDRADOCK 05000286 2DR . - _
i AVERAGE DAILY UNIT POWER LEVEL DOCKET NO. 50-286 Indian Point UNIT No. 3 DATE Juiv 1, 1983 COMPLETED BY L. Kelly TELEPHONE _ (914) 739-8200 MONE June 1983 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe-Net) , (ywe. Net) 1 0 '
415 g7 2 0 527 18 3 0 g9 0 4 0 0 20 5 6 0 21 6 0 0 -
p)
.: 22 7 0 0 y
8 47 0 24 9 182 0 25 10 . 54 0' 26 1l 144 ' 0 27
! 12 191 0 28 13 185 0 29 14 189 0 30 15 259 - -
3g 16 346 l
l INSTRUCTIONS On this format, list the average daily unit power level in MWe Net for each day in the repor...q i+.ntn. Compute to the nearest whole megawatt.
1 (9/77)
, - ., . , . . ... , . . , n . , \
MONTilLY MAINTENANCE REPORT June 1983 MONTil S KI DATE EQUIPMENT MALFUNCTION CORRECTIVE ACTION 3678 6/02/83 31 Steam Generator Blowdown Diaphram leak Replaced air diaphram -
Isolation Valvo 1214 '
3650 6/07/83 Reactor Coolant System RTD Packing leak Inject scalant in packing gland t4anifold Valves 561D, 562D, 570D, 569D, 565D 3660 6/13/83 34 Accumulator Fill Valve Valve malfunction C1 caned solenoid valve 090-D 3671 6/13/83 Pressurizer PORV Block Valve Improper indication ~ Replaced limitorque operator r10V-536. '
0 l
O t
/
e
-a
. _ _ _ _ =
MONTilLY I & C CATEGORY I REPORT June 1983 MONTil W.R. # DATE EQUIPHENT HALFUNCTION CORRECTIVE ACTION 2077 6/09/83 PCV-455C Acous'tical Monitor Faulty circuit card Repaired circuit card ,
2/53 6/09/83 Recirculation Sump Level LT-939 elevation 47'.11" Replaced Float Switch indication inoperable 2157 6/09/83 Condensate Storage Tank Erratic indication Replaced transmitter Level transmitter LT-ll28 2163 6/09/83 #31 Source Range Detector Sensitive to noise Replaced detector 2164 6/15/83 Vent Ileader Pressure Bellows-coil linkage disconnected Reconnected linkage Transmitter PT-1025 '
2187 6/06/83 Loop 31 Cold Leg Wide Range Erratic indication when cable Replaced RTD RTD TE-4138 flexed
/
o O
D
. :P. '
-_r-_-___ _ _ _ _ ---:_-----------
r O. <.
DOCKET NO. 50-286 UNIT SilOTDOWNS AND POWER REDUCTIONS ,
UNIT NAME NO. 3
- DATE July 1, 1983 COMPLETED BY L- Kelly REPORTMON111_ June 1983 TELEPHONE 914-739-8200 w.
E E No.
,$ 7 }g j$5 Licensee E,
, gg Cause & Currective DJte k 3g 2s5 Event gy pU Action to H
f5 5 jiji g Repori# mO g , Prevent Recurrence 6
04 820325 -S 173.2 B&C N/A N/A N/A Unit completed a scheduled cycle sti III-IV refueling and maintenance
/ outage on 21 May 1983 and unit ret,urned to service on 8 June 1983.
i 01 830608 P 7. *G
, 3 N/A II . II . IIT EXCIIP #31 Steam Genc.'ator Iligh Level during synchronization to bus while feedwater f ,
in manual control.
1 02 830610 S 1.9. 2 B I 1 N/A N/A N/A Unit removed from service for Turbine overspeed Trip Test 03 830618 F 291.2 A 3 N/A ED GENERA D Electrical malfunction in the main generator i 2 3 4 F: Forced Reason: Method: Exhibit F-Instructions S: Scheduled A Equipment Failure (Explain) 1-Manual for Preparation of Data B-Maintenance o( Test 2 Manual Scram. Entry Sheets for Licemce C Refueling 3-Automatic Scram. Event Repor (1.ER) File (NUREG-D-Regulatosy Restriction 4-Other (Explain) 0161) li-Operator Training & License Examination F Administrative 5 G-Operational Enror (Explain) Exhibit 11- Same Sonrce (9/77) Il-Other (Explain)
l l
SUMMARY
OF OPERATING EXPERIENCE JUNE 1983 Indian Point Unit 3 was returned to service after a 440 day refueling and maintenance outage. The , generator was synchronized to the bus on June 8 at 0512 hours0.00593 days <br />0.142 hours <br />8.465608e-4 weeks <br />1.94816e-4 months <br />. On June 8 the Unit tripped at 0517 hourt because of high level in No. 31 steam generator while feedwater control was in manual control during synchronization to bus.
The reactor was eturned Jo criticality on June 8 at 0907 hours0.0105 days <br />0.252 hours <br />0.0015 weeks <br />3.451135e-4 months <br /> and the _
9) generator was synchronized to the bus on June 8 at 1236 hours0.0143 days <br />0.343 hours <br />0.00204 weeks <br />4.70298e-4 months <br />.
On June 18 at 2050 a fault in the electrical generator caused a unit trip.
The problem is under investigation and it is estimated that the unit will be retur[adtoserviceinJanuary1984.
s s
t a
t i
e' i
- -.y-e
~
Indian Point 3 .
P.O. Box 215 1 Buchanan, New York 10511
)
914 739.8200
- > NewYorkPbwer 4# Authority July 18, 1983 IP-IK-2052 Docket No. 50-286 License No. DPR-64 Director, Nuclear Reactor Regulation Office of Management Information and Program Control U. S. Nuclear Regulatory Commission Washington, D. C. 20555
Dear Sir:
Enclosed you will find two copies of the revised monthly operating report relating to Indian Point 3 Nuclear Power Plant for the month of June, 1983. The Authority's report dated July 11, 1983 provided inaccurate numbers for the Gross and Net Electrical Energy Generated (lines 17 and 18 of the operating data report).
Very truly yours, t
lohn C. Brons Resident Manager LK/bau Enclosure cc: Director, Office of Inspection & Enforcement (40 Copies) c/o Distribution Services Branch, DDC, ADM U. S. Nuclear Regulatory Commission Washington, D. C. 20555 Dr. Thomas E. Murley, Regional Administrator Region 1 U. S. Nuclear Regulatory Commission i 631 Park Avenue King of Prussia, Pennsylvania 19406 Mr. Leroy W. Sinclair New York Power Authority l 123 Main Street White Plains, New York 10601
- IP3 Resident Inspectors' Office 4 George Wilverding (SRC), WPO '
J. P. Bayne, WP0
((Q INPO Records Center Suite 1500 1100 Circle 75 Parkway I/
j Atlanta, Georgia 30339