ML20073H193
ML20073H193 | |
Person / Time | |
---|---|
Site: | Pilgrim |
Issue date: | 04/08/1983 |
From: | BOSTON EDISON CO. |
To: | |
Shared Package | |
ML20073H165 | List: |
References | |
PROC-830408, NUDOCS 8304180517 | |
Download: ML20073H193 (90) | |
Text
_ _
l
, PILGRIM NUCLEAR POWER STATION'S 3 APRIL 8,1983 l
I I
i e, m- 3 n ,~
ll A a l u ....... .. =
h n ~/ 7 c ,s c g aswe w;;=w 7
%x+ isw pe,e w =2 nqw w r h..w, ,lL n # N .m w = pw r.
y-...
r Y i,.r.;
\ ~
'l,; #
lgh 1. -
kI b) ,' h I S, a{llllljav . y ,
,1, ,1 LONG TERM PROGRAM c.,
BOSTON
(
Edison COMPANY 8304180517 830414 PDR ADOCK 05000293 P PDR
I O ,
[ BOSTON E isonj COMPANY l
l l PILGRIM NUCLEAR POWER O
STATION'S 4
LONG TERM PROGRAM O
l
e 4
(
x TABLE OF CONTENTS
- 1.
SUMMARY
l-1
- 2. EXECUTIVE STATEMENT 2-1
- 3. PROGRAM INITIATION 3-1
- 4. PLAN AND' SCHEDULE ANALYSIS 4-1 NO. 1 NO. 2
- 5. FINAL PLAN AND SCHEDULE DEVELOPMENT 5-1
- 6. CLOSING 6-1 TABLES 1 LIST OF MAJ,OR PROJECTS FOR 83-85 1-4
. FIGURES 1 LONG-TERM PROGRAM SCHEDULE 1-3 2 PROGRAM DEVELOPMENT PLAN 3-2
'3 INITIAL IMPLEMENTATION SCHEDULE 3-4 4 (100) RESOURCE CONSTRAINED PRE-OUTAGE SCHEDULE 4-3 5 (50) RESOURCE CONSTRAINED PRE-OUTAGE SCHEDULE 4-4 6 UNCONSTRAINED 3 YEAR SCHEDULE 4-6 7 WORKING CONTRACTOR USAGE FOR PROPOSED PLAN 5-2 8 CONTRACTOR USAGE ON ELEVATION 23 ANALYSIS 5-3 ATTACHMENTS A PROGRAM. PLANNING AND SCHEDULING STANDARD B WORK ELEMENTS BY SYSTEM AND ISSUE REQUIRED BY THE REGULATOR (Q_) ii i
_ _ . . . , . . _ . .. . , . _ ,. _ _ _, _ -.._ ,. ~ , . . . , _ . ,.~.... . _ _ - - - . . _ ,
O 1.
SUMMARY
The enclosed program and resultant implementation schedule is a logical extension of Boston Edison Company's commitment to the safe reliable and economic operation of Pilgrim Nuclear Power Station.
It is this commitment that provides the primary objective for the Long-Term Program:
Provide an approved plan and schedule for work at the station that e Meets Regulatory Requirements e Meets plant improvement needs e Controls the impact of modifications on operations personnel e Effectively manages resources O
The secondary objective is also an extension of this same commitment:
Maintain the approved plan and schedule as a working tool against which to judge performance and measure future commitments.
Realizing that this program could become cumbersome if not focused properly, it was decided to direct the emphasis on those issues impacting the next full cycle of operation while planning for those issues extending beyond that point with decreasing detail. Satisfy-ing the secondary objective will provide the forward looking focus needed to detail and update the schedule as work is accomplished.
~.)
1-1
There are three major components of the overall program.
1 Management Improvement Program 2 Maintenance of the Baseload Activities 3 Control of the Physical Modification Process at the Station.
The emphasis of this report is primarily on the third component because of its inmediate impact on the plant. It is the program's intention to integrate the remaining two, which are in varying degrees of development and implementation, upon acceptance of the submitted plan and schedule, and the subsequent allocation of the dedicated resources to accomplish the. scheduled work.
The final schedule (Figure 1) and the scope of work to be accom-plished through Refuel 7 (Table 1) meets the primary objectives of this program. It enhances the safe operation of the plant by
(
balancing the improvements required by both the Regulators and the Management while allowing the appropriate level of controls to be exercised regarding the physical condition of, affect on safe operations at, and rate of modification to, the plant. The key strategy decisions to allow the above to occur are as follows:
- 1. Committing to a mid-cycle modification outage (between Refuel 6 and Refuel 7).
- 2. Maintaining area densities (particularly elevation 23 in the Reactor Building) at a controllable level.
- 3. Focusing and directing the organization's efforts at a <
specific set of goals and schedules.
1-2
q % s (d ) sj s s v
)
r i 1983 1984 1985 I
JIFlMl AlMlJlJI AlSIOl NlD JlFlMl AlMlJlJl AlSl0lNlD JlFlMl AlMlJlJl AlSl0lNlD RFFUEL-6 30DEC831 119APR84 I ,- I g .
MOD OUTAGE I 1J L 85 23FEB85 1 f REFUELS 7 l 1NOV85 d 15DEC85 l
l l N1TROGEN MAKEUP (LONG TERM) 1[3 4FEB84 i l
! m HALON SYSTEM C: 120DEC83l l I O l w l FEEDWATER HEATER C !!- _2:
i i 19M AR84 g l
z BASEPLATES C 312JUL83
) l l l
I O 23JUN83 I l ye PIPE SUPPORTS l l
oz TM1 i i Q 1JUN84 !
1y e
a ps RECIRC PIPE 4
=
i l 18J AN84 l l g j BLOCKWALL F4.4 @ 13FEB84 l 1 ll g QO TORUS EXTERNALS a i i 24JAN84 g l ll 1 $w PURGE AND VENT VALVE i i19M AR84 LJ 8 w
o $ TORUS TEMP MONITORING C3 3MAY83 l l l l
- l l 4
0 E RPS POWER SUPPLY z o [3 6FEB84 l ll 4 m VBP RCIC/HPCl/RWCU<MS/AtR i i 11M AR84 !
l H O
, 2 z RAD WASTE BETTERMENT i I i 14JUL84 l Il g
$ CRD BETTERMENT i i s 19APR84 Il '
E N1 A BLOCK OUT d 12JAN84 !
, w i
1l
] y NITROGEN MAKEUP (SHORT TERM) i i 29AUG83 l l l
SECY 82-111 EMER OPER PROC C ! ! ! !11 ! Z l - - - - - -- -- - - ' 28NOV84 i
I SECY 82-111 CONTROL ROOM DESIGN C 1. _ . ! 2 } --- -- --- ' ~ ~ ~ Z Z.] 23DEC84 I l SECY 82-111 REG. GUIDE 1-97 C 211 1 J.~r} e L "19APR85 i gl SECY 82-111 SPDS C . 1 -T - -- J . !
- - - - 2 23 20DEC84
- <- - - - - ly--
SCRAM DISCHARGE VOLUME i i e i 123FE885 mw ! TORUSINTERNALS l ( ! ! ,,_ _ J J ; p 21FEB85 !
$ ,o @ APPENDIX R l
- l l 14DEC85 i O6y HYDROS '
- Q 29NOV85 mmw " i
- i I I i i!
Figure 1. Long-Term Program Schedule
P f D d '
V TAB LE 1 List of Major Projects for 83-85 PRE RFO #6 WORKING SCHEDULE TARGET PROJECT SCOPE TIME AVAILABLE COMPLETION COMMENTS Torus Temp. Complete installation April-December Prior to Monitoring of 24 instruments, and RFO # 6 System readouts lia lon Replace failed CO2 April-December Prior to System System in Cable RFO # 6 Spreading Room Pipe Per 79-14 complete four April.-December Prior to Supports modifications RFO # 6 Base Per 79-02 complete four April-December Prior to Plates t..odifications RFO # 6 y Torus External Attached piping, column tie-down and saddle April-December Prior to RFO # 6 A
painting Complete modifications April-De cember Prior to U2 Short RFO # 6 Term to allow N2 supply to
-drywell Appendix R Start cable bank April-December Prior to Project work will stop during inetallation outside proc- RFO # 6 Refuel Outage No. 6 ess buildings to meet NRC separation criteria.
TMI Continue installation of April-December Prior to Project work will stop during (PASS !!220 ) PASS H 02 2 system per NRC RFO # 6 Refuel Outage No. 6, with the exceptions of provisions made for on-line tie-ins.
Scram Install two separate April-December Prior to Project work will stop during Discharge instrument volumes per RFO # 6 Refuel Outage No. 6 Volume NRC (SDV)
O O o 4
M TABLE 1 List of Major Projects for 83-85 (Continued)
- RFO #6 WORKING SCHEDULE TARGET PROJECT SCOPE TIME AVAILABLE COMPLETION COMMENTS Feedwater Replace feedwater heater RFO # 6 End of Heater E-102B RFO # 6 Valve Upgrade, replace valves RFO # 6 End of Betterment that are high maintenance RFO # 6 and/or not reliable HPCI/
RCIC, stop check, con-tainment purge and vent valves, miscellaneous steam valves, compressed
- air system isolation valves and condensate demin vent valves
- integrated with valve
- betterment program and local leak rate testing l
l Recirc Rebuild blockout in RFO # 6 End of
- Nozzle biological shield wall RFO # 6 i
Blockout (NIA)
Blockwall Install three blowout RFO # 6 End of Modifica- panels in bloc'kwall 64.4 RFO # 6 tion (64.4) per IE Bulletin 80-11 Recire Inspect recirc system RFO # 6 End of System in compliance with IE RFO # 6 Inspection Bulletin 83-01
~
t
. u") (J . (mJ TABLE 1 List of Major Projects for 83-85 (Continued)
RFO #6 WORKING SCIIEDULE TARGET PRCLTECT SCOPE TIME AVAILABLE COMPLETION COMMSNTS Insulation Replace / upgrade insulation RFO # 6 End of Replacement in drywell for drywell RFO # 6
/ Upgrade high temp issue and to facilitate easier removal and installation.
Reactor Upgrade the electrical RFO # 6 End of This modification will be Protection RPS system by installation RFO # 6 performed during any outage of System of 2 electrical protection sufficient duration.
assemblies.
Standard Refuel, turbine overhaul, RFO # 6 End of Refuel CRD's replacement, MSIV RFO # 6 Outage refurbishment e Scope
- N2 Long Reduction of combusible 'RFO # 6 End of Term gases in the containment RFO # 6 as a result of NRC Rule 10CFR50.54 i
O O O
, TAB LE 1 List of Major Projects for 83-85 (Continued)
PRE MOD OUT #1
, WORKING SCilEDULE TARGET PROJECT SCOPE TIME AVAILABLE COMPLETION COMMENTS
, Appendix R Install conduit and sup- April-December Prior to Project work will stop during ports in turbine building 84 Mod Outage Mod Outage # 1 to meet NRC separation # 1 criteria.
Scram Install two separate April-December Prior to Completion (tie-ins) of scram Discharge instrument volumes per 84 Mod Outage volume discharge system will occur
, Volume NRC #1 during Mod Outage # 1 (SDV)
TMI Continue installation April-June 84 Prior to Completion (tie-ins) of MI PASS (PASS !!220 ) of PASS 11 02 2 system per Mod Outage H02 2 system.
NRC #1 w
I 4
i l
4 l
.]
O O O TABLE 1 List of Major Projects for 83-85 (Continued)
MOD OUT #1 WORKING SCHEDULE TARGET SCOPE TIME AVAILABLE COMPLETION COMMENTS PROJECT Scram Complete tie-ins of Mod Outage # 1 End of Mod Discharge- instrument volumes to Outage #1 Volume scram discharge header (SDV) per NRC.
Hydro's 1/3 of Class II and III Mod Outage # 1 End of Mod piping system hydros Outage #1 Torus Modify torus as a result Mod Outage # 1 End of Mod of NUREG-0661 and 0 783. Outage #1 IH SI Heating process to mini- Mod Outage # 1 End o"f Mod Potential plan activity mize cracking in recire Outage #1 P i ping g
i CD i
O r u
c c
o l
l i
w s
S n T i N -
E e M i' M t O 7 C f o#
nO oF iR t
eg l n
) pi d mr e ou u Cd n
( RL r#
AP o 5 TM iO O rF 8 C PR 3
8 E r r LE e UL b O 1 o E
Ls f
e t
p e
Bt V S Ac GA -
Tej N h IE c o KM r r RI a OT M P W r
j o t r
a o M pl pl f uu a s pC i o / Rr tdNe t in t s uati i d er L nnec E
P oom ci n O too C eati S ul t nlsa iaer ttl a nsbp onae Cics 7 R x
O T i F C d R E n J e E O p R p O R P P A wI@
O O O TABIJ: 1 List of Major Projects for 83-85 (Continued)
RFO #7 WORKIbG SCliEDULE TARGET SCOPE TIME AVAILABLE COMPLETION COMMENTS PROJECT Standard Refuel, turbine overhaul, RFO # 7 End of Refuel CRD's replacement, MSIV RFO # 7 Outage refurbishment Ilydro's 1/3 of Class II and III RFO # 7 End of piping systems integrated RFO # 7 with local leak rate testing ,
Appendix R Complete project tie-in of RFO # 7 End of all cables to meet NRC RFO # 7 separation criteria 7c-Ola Verify compliance with April 83-RFO End of H environmental qualifica- #7 RFO # 7 h tions of electrical equipment o
/%
\
(J
~
To accomplish the above will require rescheduling the completion dates of the following major projects:
e Scram Discharge Volume e Long-Term Program Torus Internal Mods from the end of cycle 6 to the middle of cycle 7, and accepting the I
proposed completion dates of TMI (PASS H 02 2) and Appendix R.
The specifics and evaluation of the scope of relief requested for the Tbrus Internal Modifications and the Scram Discharge Volume are as follows:
Evaluation of Catwalk Extension Support Legs and Ring Girder /Shell Weld
() An evaluation of the safety margin of the above item was done prior
- to the start of Fuel Cycle No. 6. Both the catwalk extension support legs and the ring girder to torus shell welds were shown to meet the acceptance criteria of the MKI containment Short Term Program, i.e.,
meet a safety factor of 2 based on ultimate strength. The grating on the catwalk extension platforms was removed to reduce pool fallback loads.
The bounding load case for both the support legs and ring girder to shell weld is a LOCA plus SRV actuation. Analysis has shown that the catwalk extension support legs would bend due to submerged loads
, which would result in strain in excess of yield. Howeve r, the legs would not break and would remain in the deformed position. The catwalk extension platform would also bend when the legs bent. There would be no subsequent loads that would cause further damage or distortion of the support legs and the suppression chamber pressure boundary would remain intact.
1-11
jn k The_ ring girder to torus shell weld at the T-quencher supports has calculated stresses about 30 percent over MKI Containment Long-Term Program acceptance criteria. Although the stresses are over code allowables, they are below yield and the suppression chamber pressure boundary would remain intact and functional.
Evaluation of Scram Discharge Volume Modification Extension The present configuration of Scram Discharge Volume does not meet the regulatory requirements of IEB 80-17 The existing commitment date for compliance is the end of cycle 6.
The ability to SCRAM has historically been highly reliable and oper-ational problems identified in IEB 80-17 have not occured at PNPS as evidenced by the following:
() a) High reliability of the Water Sleuth System (CMS) b) At no time has water build-up been detected in the headers c) Independent drain systems precluding hydraulic inter-action within the system following a scram d) ' Installation of the air dump system to ensure a full scram upon detection of decreasing air header pressure.
Boston Edison Company believes that the reduced risk to the health and safety of the public afforded by the modification is outweighed by the increased risk associated with attempting to accomplish the modification in the presently planned manner to meet the existing commitment. The present plan calls for high craft density (approxi-mately 50 men at peak) on elevation 23 in an area that can cause inadvertant scrams during plant operations. When added to the normal refuel densities on the same level, manpower density will place operations in a posture where desired control of activities will be
) threatened.
1-12
[h
.v In addition, it presently appears that the 79-01B project would be
' implemented by the end of cycle 7 due to the integration of all projects in progress.'
The major milestones involved as a result of SECY 82-111 have been represented and as scope and implementation schedules evolve, the details will be integrated as part of the updated progress.
Boston Edison Company will be progressing and updating this program quarterly and reporting on an exception basis while adding detail as further scope becomes available.
O r
O l-13
4 s 2. EXECUTIVE STATEMENT I have had my present assignment for just over one year and I can assure you that Boston Edison's method of doing business in the Nuclear Organization is changing. At present we are endeavoring to meet our commitments and our mission today is another example of our continuing effcrts. I would be less than honest if I did not share with you my concern over the rate at which we have been doing our work -- and that rate must slow down.
Our program today will illustrate for you the many improvements we plan to make at Pilgrim Station which are not Regulator man-dated, but which will make the plant safer. We have completed a u) major reorganization, created entirely new sections, one of which is outage management, and have established entirely new policies.
Those are the software. The hardware are the physical changes we will make and will discuss later in the program.
As responsible utility executives, our goals continue to be the safe, reliable, and economic operation of Pilgrim Station consistent with cost effective implementation and modifications be they self-imposed or Regulator mandated.
The past few years of experience with refueling outages have been grueling ones from the regulatory sense, in that, within these time frames we have not been able to effectively manage our own
~ resources nor set priorities to achieve our goals as previously stated.
2-1 l
I observed us working inefficiently and at an accelerated pace C We had been doing that in an attempt to
\ which was unacceptable.
meet commitments which were made with inadequate investigation and planning. We had dedicated resources but we continued to place ever greater demands upon those same resources. The result was the hectic outage we experienced from September 1981 to April 1982, eight months' duration. Gentlemen, we must reduce our outage time in the future.
How had we arrived at this situation?
Let me briefly discuss that question.
In the mid 70's commitments were first made and scheduled afterwards.
Although this cannot be viewed as a sound practice by today's O(_s standards, it was acceptable when modifications were not numerous.
Shortcomings were easily addressed because nuclear organizational staffs were small and relatively stable, which allowed individuals to close out commitments and exchange information on a personal level by utilizing simple systems.
In addition, modifications were made with the utility's own staff, which enhanced operational knowledge of the change and maintained the ability to control them.
The transition from the 70's to the 80's saw a steep increase in regulatory actions in the form of bulletins, orders, NUREGs and changes in the " law". We accept and understand the reasons for this increase.
s, 2-2
-. . .. . .~
~- .
Also, the intensity (establishment of the on-site inspector pro-() gram) and complexity of inspections changed drastically. Performance appraisal teams, radiological assessment teams, emergency response teams and the yearly systematic assessment of licensee performance program are all examples of this change and all in a relatively short time period.
The utility industry responded in kind by stepping up their quality assurance programs with the same intensity and complexity, and established the Institute of Nuclear Power Operations (INPO) to address and make recommendations on the same issues.
Unfortunately, Boston Edison company responded to the output of these various programs in'the same conditioned manner of the mid 70's. This caused us to begin to have difficulty meeting other
^
commitments so we elected to supplement the permanent work force with an increasing number of contractors in an attempt to respond to the new requirements and meet the increasing number of commit-ments.
The results experienced during this period were as follows:
Increased number of missed commitments Physical and administrative changes to the Plant at a rate that could have caused confusion to the operator Site manpower densities to implement change straining the control of management and support services Outage durations often approaching 6 months
() --
Knowledge transfer to permanent employees minimized 2-3
,g
-- Inability to maintain documentation consistent with
(-) physical plant
-- Plant improvement needs sacrificed in an attempt to meet regulatory needs
-- Reduced plant maintenance
-- Reduced training
-- Boston Edison did not know the number and scope of post-TMI modifications Correctly, this period saw a greatly increased regulatory involve-ment which was not quickly matched by an increased commitment of Boston Edison resources. The result was our inability to do more than short problem solving and place large demands on the avail-able personnel.
This taught us that our situation required an integration of work, based on resource manageability, with schedules reflecting well thought out strategies so as not to create a negative impact. It was during this period that I joined the Boston Edison Nuclear Organization.
As I observed our performance I began to formulate some policies which would address the issues. Paramount was Boston Edison's continuing policy to keep the plant safe. We had to readjust how we did our work and -- in some cases -- when. I never again will permit the status to be that which we had during the 1981-1982 refueling and modification outage. As a result, we approached these problems by developing a long term program which was formu-() lated using the following elements:
2-4
-- Keep the plant safe by performing our improvements at a rate our operating force can understand.
-- Perform base load work without major amounts of over-time, to keep our resources alert and involved.
-- Control the work force to reduce the possibilities for error and operational transients by limiting site and area density.
-- Minimize outage times but increase the frequency.
-- Allow plant improvements to be prioritized according to their significance relative to all other tasks.
-- Provide operations with greater time for personnel to become familiar with changes, and allow time for up-dating procedures and prints and training.
Because of the continually increasing level of sophistication associated with nuclear design, operation and modification, we believe our goal of supplying safe, reliable and affordable energy can be successfully fulfilled only by 1) a coherent long-range program which prioritizes without undue rigidity; 2) which allows the scheduling of future requirements in a realistic manner relative to the existing baseload; and 3) which allows a deployment of resources -- particularly human resources -- in a manageable way.
Only by developing a program that addresses these criteria --
which we believe this program does -- can we hope to achieve ex-cellence in the future, and escape the errors of the past.
This attitude was expressed in the actions we tock during the end of our last outage. Those actions included the immediate cessation O
2-5
, . - _ . ~. - .- . - . -.
of all work, removal of all contractor personnel from the site,
(%
\_) removal of all staging, cleaning and decontaminating the entire plant, identification of all remaining work that had to be done, and a rescheduling of this work accordingly. This was done with advance notice to all interested personnel and discussed in meetings at regional headquarters.
As a result, a Confirmatory Action letter was issued by Region I which confirmed all the agreements we had reached in those meetings and allowed us to reschedule our resources accordingly.
This program allowed us to regain control of the station and was applauded by both BECo. and NRC management. These actions became the initial building blocks for our Long Term Program and developed into the philosophy for operating Pilgrim Station in the future so that we would never again find ourselves in the situation we had during that outage.
This philosophy is expressed in the policies I have issued, as follows:
- 1. Pilgrim Station shall be operated and maintained in a safe condition at all times. This extends to opera-tional and outage periods alike.
- 2. Established site densities will be upheld. The station manager must always be able to maintain his systems' operability and tech. spec. compliance.
- 3. Adequate time will be scheduled around each modification such that all affected procedures and drawings are up-
- dated and operator training is completed.
2-6
- 4. Work packages will not be allowed to commence until
() individuals involved are trained for the job at hand and sufficient materials and space for storage of those materials are available.
- 5. The amount of modifications being implemented at any
,one time will not exceed the operator's ability to fully understand "the big picture" including the " hows" and
" whys" for each modification.
- 6. In the future we will have independent refueling and modification outages.
- 7. Personnel will not forego vacations or be required to work excessive amounts of overtime, nor will the number of modifications create reduced time allocated for operator training.
- 8. Implementation schedules for BECo. desired modifications
/~' shall not be sacrificed if other scheduled tasks cannot V) be accomplished as originally planned.
I realized that these policies wouldn't work unless they were applied to a program so we implemented them into the Boston Edison Long Term Program, and I believe our presentation will assist each of you in understanding that its acceptance is critical to our future.
f
(
2-7
- 3. PROGRAM INITIATION This program is not another attempt to predict the future, but rather an attempt to create the future and adjust dynamically to changing situations. The enclosed plan and schedules are the result of five distinct phases.
- 1. Assemble the Data Base "What do we think we are presently trying to accomplish?"
- 2. Situation Analysis "Where are we and why are we attempting to accomplish these activities?"
- 3. Direction "What do we want to accomplish and what constraints exist?"
- 4. Plan "How do we want to accomplish these activities, are they interrelated, in what sequence and who will perform them?"
- 5. Schedule "When will the work be accomplished?"
The last phase which will be initiated after approval is the Update and Recycle for Each New Commitment Phase which will cause the pro-gram to be dynamic.
Figure 2 depicts the plan utilized to produce the implementation schedules. It took four months to complete the first two phases of the program and produce the initial implementation schedule, with the full data base upon which to develop strategies and make decisions.
O 3-1
f N U '
O[*
l I STANDARD IN y m
EXIS.T.S .G _ ,A,OR,,, _ OR TE _
SCHEDULES 8 SE TTIDeG A
DEVELOP h ESTABLISM N
, DEVELOP GATHE R SORTSV PROSLEM & PRIORITT & Y'I INITIAL 3 gga
( STARY j
SOURCE DOCOS e Sv5 TEM &
ISSut S N
+
SCOiPE STAfsSTICS ygg g
NO PLANT CONDITIONS LOAD e
~
EWNT SCHEDULE F F ES 3 #
STANDARD STANDARD STANDARD FOR - FOR CONST FOR CODE DAT& ASST SCHEDULES FIELD USE A A 1f I' ip PROVIDE 8' ItsPLEesENT _ LOAD INDIV A SCHEDULE SCHEDULES OR ACCESSEXIST =
i f STANDARD FOR RESOURCE -
f d
ALLOCATION J e O Oe s ,
S,_ ARO.OR r .T. _ R.
CNANGE -o- c0*' -
SPECireCAYtDN **"O
' L
]
j u o 7 ST ANDARD FOR --
DEVELOP' ACCESS T ASK RE ADV L ENG PLANS PMG A
n INTE3 HATE PLANS & END I STANoARDrOR SCwfDuLES - (
if PKG M + DEVELOP < ACCESS 4
START-UP &
- TURNOVER 1
STANoARD rOR TURN-OVER -en-PE G A
Figure 2. Program Development Plan
O At this point in the process, there existed approximately 500 pieces of work, and 280 individual construction / maintenance schedules. The initial integrated schedule (Figure 3) reflected 13 of these activ-ities and only those required by the Regulator. The ability to con-fidently analyze and manipulate the data and schedules was enhanced by the standards that were developed during the process. Attachment A provides a summary of these standards.
The total listing of the network is available; however, inclusion in this report would only serve to increase its weight and not its value.
To provide a sense of the detail and effort involved in assembling the data base, the following attachment has been included:
Attachment B - WORK ELEMENTS BY SYSTEM AND ISSUE REQUIRED BY THE REGULATORS.
With the data base fully assembled, the analysis and manipulation began with the initial schedule and logic, i
O 3-3
l S
C I t M
PPT
- A 4E SCESM J#
O 2T
/R A 4 fCM i 8
EC N J E OAC A U
RA J PS' lIl1l 4 J 4 I I
I 8 M R I
4 A 8 M 4 A Y I 9 8 A 4 9 M I 4 8 I 1 M 5 8 N l 2 4 R A 8 P J I F R A 8 I I A I 0 1 4 4 J M 9
1 4
f 1
3' 8 B
E 8
8 E
@E I
1 0 3 8 A N [ F I
F 6 IF 3 8
P J
[3[
1 C
I N E S
6 2
1 3
8
[6 E 0
9 V e
0 2 3 1
01
[ 0 3
1 l I T
t M
f S 3 3 C 0
[ 9 2 [
n I 8 8 o
M A 3 8 [ N U
N U
1 3 [ 3 8
[ e l
V J J Y l e
a 3J 8 N A [ 3 2
3 2 [ '1A 3 [ u FL 9 I I I
[
9
[8 RP [ d M [
/ 4 J
0v EE p
1 l - - [ A
- e 0f 0u M [ I I 3 [ 9 [ h Ml I I 8 1 c
IlI E
A 3 i
l
[3 8 r
A 3
8 f
A
'E i
5 B
[
3 1
[ S t
D u N R P
3
[8 M 2
M 2
3 8
N 2 [8 N
]8 N
n A N o
I E I C
S H
F 8 2
A J
3 1 A J
A J_ [ 3J i 8 8
[@
I 6
e J 2 1
2 1 @ t a
t 3 t 8
N N A
n N
A J e O
T 8
2 m P
L S
E e
0 0
l t c p O
n C a
i r
M m
v S
I 0
5 Ilr l
a i
?
g t
Nn I i f0e l0 n l
AC I El4 Le0 Un5 D$t ER0 MOE .
c SRw l 3 A0 EE7 CL5 _
AC0 TUN U3 e O
O r LC EE D E u F
E uS N L O A g
R
/
N T C i S I 5
f E T F F
M E L I
I R
f I
M C m G o
C sa E I un Au E
JJ M G 0 U E N L _
24 L V I _
R O L 4 V A O 0 V T Y l R f E E I L YE T G 4 t N P _
RP L
A S R h O P I A M M E T A 4 E M U O H E W S TSC E P R 6 P
T R S O C P S R E P S I L D M R Y X E T P I P L N E E 6 H S I T A U D A A T W - C 0O 0O D A L S C W O L S MP N N W P M R K E S S P E
/ /
O E D E E A I C C U U U G FF N EE e n L P E S P 1 R C O R R R S F RR e A P E A I M C E L U O O P E I w
e M A F B P T S R B P T T R R K TC R E n O JT OO ne 5 6 7 8 9 1 2 3 4 6 7 8 9 0 W WL m 2 2 2 2 2 3 J 3 3 3 J J 3 4
- P e gIA
( 4. PLAN AND SCHEDULE ANALYSIS ANALYSIS NO. 1 The initial schedule based primarily on Regulatory Requirements, Figure 3, produced the following results:
A. An unacceptably high number of contractors which
- will cause the following management control j problems:
l e Housekeeping e Fire Protection e Exposure e Waste Generation e Quality
() e Impact on Operations B. The work being accomplished with the exception of the feedwater heater and purge and vent valves was because of Regulatory Requirements without consid-eration for plant improvement needs.
9 C. Area loadings, because of the scope-of-work planned in excess of 150 contractors on Elevation 23 during i outage conditions, in the Reactor Building alone.
D. A water management problem if the Torus Internal Modifications and Feedwater Heater replacement were to be accomplished together that would require the temporary storage or discharge of approximately 200,000 gallons of water from the Torus.
O 4-1
4
) () E. The requirement to provide an extensive tempor ary contaminated exhaust system to allow the containment purge and vent valves to be upgraded simultaneously with the Torus Internal Modifications.
A sensitivity study utilizing manpower loading as the variable to minimize A and C for pre-outage work to support the schedule produced the following:
- e 100 working contractors would complete the work by March of 1984, e 50 working contractors would complete the work by October ' of 1984.
e The term working contractor does not include the increased burden of Administrative, Health Physics, Quality Control, Waste Management, etc., personnel that are required to support each contractor in the field.
The existing reload requirements and present plant performance indi-cate the end of cycle will occur late in December - early in January; therefore, neither of the above results are satisfactory. Figures 4 and 5 depict the analysis. Recognizing that a broader base would be required if a viable strategy was going to be developed, the follow-ing programs were added to the plan:
i e Valve Betterment e Radwaste Betterment e Cooling Water Betterment e GEMAC Replacement e Condensate Pump Upgrade e Facilities Upgrade O
V 4-2
\
{
1 I
I 1983 1984 FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEg MAR MANHOURS
! l ll eaaa eaae aei iII eaie iI I I eI i l tt iel l l t l IIi l l l ll l l 1
1 :
1
, ______-- - T-5 JAN 84 l ".
il 25 HALON SYSTEM 2_0A_PR_8_3 _ _ _ _ -
- e400 I
! 28 BASEPLATES 12 MAY 83 l 11 AUG S3 :
i
- -- 5800 5 29 PtPE SUPPORTS 12 MAY 83 l 21 JUL 83 g
4 _
- *eoo 3 1
b 31 TMs 28 JAN 83 29 DEC 33 l , y
l L _FE_B S_3
- 3M. p j /
38 TORUS TEMP MONITORING 28JAN83 j l19 AT1183 : N 3
i .f _ .co
- n 1
]
41 MANPOWER LOADING 28JAN83f MC Si] :
- - 1eco 4
L soo
" o ii I
i i
1 1
l Figure 4. (100) Resource Constrained Pre-Outage Schedule
\
1983 1984 DEC JAN FEB MAR APP MAY JUN JUL AUG SEP OCT FEB MAR APR MAY JUN JUL AUG SEP OCT NOV MANNOURS iIt Itai att tit till ett felt sit ilI itse sta eet titt telt sti ttt atti eat tis lasi tet
~
23 0CT M 25 HALON SYSTEM [20 AP.R. 33._ _ _ _ _ _ _ _ _ _ _ .,. _-
_ 7200 23 SASEPLATES 12 MAY 83 { ~ ~_ ~ ~ ~ ~ ] 29 AUG 83
- - 6400 2
2 MAY 83 ( ~ ~, ~, l18AUG83 ,
O 29 P1PE SUPPORTS ,
- 2. JAN s3
, OCT ul -__ ,,,, 3 A 3, y,, .
i o A 23 AUG 84l
- - 4000 b 32 SCRAM DISCHARGE VOLUME (2,3, FEB 83 =
2 38 TORUS TEMP MONITORING *J__ _ -_ __
I h 3200 [
20 JAN 83 30 DEC 83l Z- 2400 41 MANPOWER LOADING W \ le0e
- - eso
=
- 0 l
l I
l Figure 5. (50) Resource Constrained Pre-Outage Schedule
O ANALYSIS NO. 2 With the inclusion of the various maintenance programs, the project list grew from 13 to 55 and the individual pieces of logic were now in excess of 1500. Figure 6 represents an unconstrained summary schedule of these projects. The results of Analysis No. 1 (A,C,D and E) were either still valid of magnified many times; however, the schedule impact manpower loadings could now be accessed as constraint (area loadings and site density) and balance (Regulator Improvements versus Plant Betterment Programs) strategies were developed.
The four major issues to be addressed were:
- 1. All of the desired work could not be accomplished with the present level of site resources.
( 2. The area density on El. 23 and in the cable spreading room peaked at levels that would jeopardize the safe operation of the plant while on line and cause outage levels to reach in excess of 150 people on a watch.
- 3. Appendix R Modifications, if all other projects could be accomplished, caused the 84 outage to extend until June without any constraints.
- 4. Accomplishing the feedwater heater replacement in l
l parallel with the Torus Internal Modification caused a loss of water storage capability of approximately 200,000 gallons.
! As a result of the initial analysis, the total manhours to accomplish the scoped Regulator work was known. This indicated that with 50 work-ing contractors, it would take approximately 18 nonoutage months to 4-5
CO,Mt f rE.Ts/EEFuEL OWTa4E setEDulE PROJEc1/2 8252 McT Pt 0? GEF/M%.
s&s94t* 2 ,
SEc0 nucLEne OpsamtLTf D. MODE 04 Ba# cosa#, cearwics puu oe f t 2iseneg3 00$fo. Eof sc Carra.' f.?f et al e i scu f w (si P AGE i seEf f i staaf sus.eart PLa..t G sce(ouL E corPLff to.250cf8s 29JasS3 scRf cc00Es r3
/ . 2s *saLO. svstEM 29AP883 29E P93
(/ 24 aPPt.ots R 3nM193 u E 2smf al 2r FFfo.afER MEnfER 2SJa.53 E ,
I i9Ma#84 29 Bast PL af f s i2 mat 83 Q 23Juhll3 29 'IPE ssPPcRTs $2MaTB3 0 23Ju.ll3 3i TMt 28JauS3 I E 24Ja.84 32 steam of sc>ancE #0 Lure 23FEB83 E m 20Maese i
33 #Ecl#c PIPE - 310cf 83 [l iSJa.44 34 Stoct.ALL 64.4 28u.43 c., , I MFf BH 36 Puest a.o vf=f vaLTE - 29 0183 [] ismate s 31 foRus 29 mat 83 I J itFE004 38 foRus fFrP poest? ORT.c 2BJa.s3 i g4Pp33 39 #Ps Po.Ee suPPLT 2944 43 (((([ ((*[ ] eFf 8H 4 REFLEL-4 3OoEcS3 ] 4JU.S e ei Ma.Po.Ep L.Aof.G E 23Ja.33 4sAeS4 I 42 c.9PtR9ce. . ORE UGdl kRKPM 43 c.ePnecc. .ons tHZalmyrp3 ;
44 c.88/ss. 085 E 23u.SI 25DCTB5 I 4s c.8P/sta mafER sYs E 2 Bas.3 3 *((j#
4s nPinesc 2ean3x :l rJane er n <ures asuo3i nn u.n es vo*re.cu asume3 m ,:] 77Ees4 4, verrMs 2su s3 i .:t ,Jann so ne/a re asunn i l ru. .
si mia stoce out asu n t ::::::a3 2u.s4 s2 wireoce. mEuP nsaT:: _::3@m s3 nnaus isun [--32sereu s4 ..<c a asuun t]irms, ss ..n0. ancuse 2emn c:;-) 2au:s 3 54 #./sFPo MC.f ? svs 29Ja.83 29JU.13 sr R / cit sEP 2ssa.83 O 26*P#83
.V se ..,.touce uo. voc 2su=3 c:D isun se ..<ve.1 it a r r o. isme3 e ismn so n.moctounts isu ng2om u 41 R./ct. Os POOL 29u.43 23 mat 4 i 62 R.s e aco F L f # 2SJa.03 I I 22ndC93 43 c0 uMT -vE.T valve 23sa.33 C~~,[*,[,,[:]
_ iimp u co e um. uuaso.rc sfast c - -
sas. 0 3uu e4 is co o oEm. cicto.e seP 2 ems 3 ta ioJu.o u c0 o um unoEn our.s 2sua3 C:::Z:::a smo er co.o um.une 2su o312 u.e3 u cc.o um. att retreatro. isJuLai r_:. _.,;1 sJu.si.
u co.o uma sto. retaulatro. 2.Jao3 c::; J isaPu re como uma aro. van asuo3 C:::li3mn ti como oEm. vaarr o Peoctou Es isms 3 l 2eme3 r2 co . oEm. vLe Euovut, 2.u 3 c;;;1 sun n ec.. um. cc oucirem ,oiarons ism.3 e i m.3 r4 n P. racrLittas iaPas] 0 2r='si
,s co. Pu- .tPuce,E., 2.m.3 ta .Ju o
- r. co.. Pu,, era.c m. roo. iunC-3 i.,ine rr co . pun 1.sf A urcRaoE 20Ja.83 ((] SJutu
- r. a,. . 2.mn c . 30:i P.3
- r. ..ni.c.insE sa,ets u.E sitt 2.m.: c:a tiun so Petcess ao no no. i asun3 C J 2rmsi
., a-c ru.smirE.s 2.mn . --, 3mu l
LEGEND vonra seu i i m LEsfo.E *D
\
b/
Figure 6. Unconstrained Three-year Schedule 4-6
accomplish the same scope of work. Fifty working contractors corresponds to approximately 100 total contractors on site (including Administrative, HP, QC, and general support). Inclusion of the betterment programs would require approximately 20 more contractors over the same period of time. It became obvious that the evolving strategy would focus to achieve the following results.
e Control the area density on elevation 23.
e Minimize the impact on Water Management.
e Balance Plant Maintenance needs with Regulators Improvement needs.
The key decision made during this phase was to test a mid-cycle modi-fication outage to include Torus Internals, Scram Discharge Volume Tie-in and TMI Tie-ins, if not completed on line.
It was also decided to limit Regulator Contractors to 50 maximum so that the various betterment programs could be included and margin existed for new requirements during the same time frame.
O 4-7
- 5. FINAL PLAN AND SCHEDULE DEVELOPMENT Figure 1 represents the final schedule produced as a result of the application of the key decisions from Analysis No. 2. The initial analysis produced the following results:
- 1. The following outage durations.
e RFO # 6 - Approximately 10-12 weeks e Mod Out # 1 - Approximately 5-6 weeks e RFO # 7 - Approximately 6-7 weeks
- 2. Alleviation of the Water Management Issue
- 3. Alleviation of the manpower loading issues.
( Figure 7 demonstrates the effect of controlling the resources in accordance with the proposed schedule for all modifications required to meet ragulatory requirements while Figure 8 shows the alleviation of working contractor density on elevation 23 in the Reactor Building from the original schedule to the proposed.
I I
l 4. Allowance for Plant Maintenance Programs l
i i
e Radwaste e Valve Betterment e Cooling Water Betterment e Instrument Upgrade
- 5. A defined and controllable scope of modifications for Operations.
O 5-1
C' ')
- L
.. +. . en.
v .,u. ...,w.
MANHCUR USAGE B ASE D CN RESCURCE CCNSTRAIN:NG REGUL A TCR CCNTRACTCRS LI*1!Tf D AV AIL ABILITY OF 55 MEN PER WEE K
'9&M9/ICI
- NH9/2WK 2'sooC - [;COC;; U U
L i
o w Y 3 2 w e {*SCOC; ?
y 22 00 -
W Y E E 5 5
400000 20000 - 5 h-5 :
2 4 4 0 a - 3300C0 g y + '500 -
Y
- B g
- 300000 3 e SCOC -
m (J1 .=********...
, , , . * * * . . . . * * * * * * . .-2000C0 1
h) ,2000 - ...
/
.s=-
l.: -2n:=
..oo ,
' ' = coq a
,'#cc::
- co, ~
':00 ...
' ooze e ' *.. %g %, n- . %,~,
/
g%*% %% h s,,
= ",;,:" "" "'*'" a"' lt,:M/r/ZJ ';";;"""d
/ ll" ,,u.".,r"#;'"%
. n .- .n x. , Jr"%
/ E , '*J' nu Figure 7. Working Contractor Usage for Proposed Plan
I O
oc4$m -
0 0 5 6 5 2 7 - - - - -
- l I 0
r
. 1 O N Fi I l i I l I 1 l I I l I I i I I i I R O I
S I
A s e i
\ I J
l l
u s
y J
d l e
i a
M h n l
c A A S 1
3 1 k M d 2 I
e D ;
I l I I l I 1 I I I I I I I i F s n o
I 9 J p o O;I l I I l I 1 l I l l i o
l ,
D t M I r a N P v I
e l
O I E S
~ I n
A o A>
O /
l J
e g
J a
i s
M U
- I
- 1 l i I l i I l I l 1 l l 1 l A r 6 g1 { g1I i o
- Il ig g
M e t O :l1 iIl l I l a F :I1iIlIlI I III I ill F
I u r J d t R I 1 l I l 1 I I l l i e n o
l 1 l 1 l l h
\ O c C s S 1
N I
g\ l l .
O a
1 8 s S n I i e
/ A l
i g r u
r g
\_
J
- /
I O i
- J F
A I
I M
f I
1' A I
Tf M I
F 0 0 0 0 0 5 0 5 2 1 1
$
SUMMARY
This attachment is a synopsis of the technique utilized to assemble the data base, perform the situation analysis, develop the logic and produce the various reports and schedules.
DEFINITIOFS Prior to commencing this effort, it was determined that a uniform planning vocabulary needed to be established to break-down the communication barriers and ensure uniform processes.
The major definitions are as follows:
Commitment - an agreement to perform an assignment in a fixed period. A commitment can be initiated by the Regulator, by station need and/or Management directive.
Program - the sum of all projects within the organization with the benefit of corporate direction and constraint.
This integration may impact individual project schedules as their interaction and impact on the entire organiza-tion is viewed as one entity.
Project - a set of related activities by elements or com-ponents which lead toward the completion of a commitment.
A project has definite starting and ending points and requires time to undertake and complete. It will typically involve multi-department interaction, and has resource demands - people, machinery, materials, work space, all of which result in costs incurred. Projects have inter-mediate and final goals (milestones) by which progress
() can be measured. All items that comprise a pr3 ject have A-1
a common goal; completion on tima, within budget, at a prescribed quality level.
() Component - a systematic reduction of a project to an item for which a series of scope statements apply to resolve related issues. The component level need not exist for each project or may be added as more knowledge is gained regarding a specific issue.
Element - an element specifies an individual scope state-ment to resolve a specific issue.
Activity - the activities that make up a project can be thought of as departmental projects. Each activity repre-sents a measurable work product and has a definite starting and end point. A few will require no material resources, but do require time to accomplish, and must be included in the planning due to the time constraints it imposes
( on other activities. Most activities have associated costs, whether the actual costs of materials or machinery, people costs or incidental incurred expenses such as general supplies. The collection of all activities at j the element level, together with their resource require-ments, cost requirements data and precedence relationship form a plan to resolve a specific issue.
Tasks - work assignments to specific engineers or individ-uals. A task is usually the lowest level of work assign-ment and monitoring, typically at the group or individual level.
Plan - a scheme or method developed typically during the scope definition phase. It indicates a logical O
A-2 i
.------n---
sat of activitics and their relationships as they relate to the accomplishment of goals. A plan re-() presents the best estimate on the way we will pro-ceed in accomplishing our goals (meeting a commit-ment).
Schedule - a program of forthcoming events. The schedule represents in detail a logical set of ac-tivities and their relationships as they relate to the accomplishment of goals. A schedule, depending on the phase the project is in, wdllrepresentthe responsible persons' actual estimate of resources, people, machinery and materials required to meet goals. A schedule is fixed in time.
NOTE: The main differences between plans and schedules are that a plan is a process to represent an overall strategy while a O schedule represents a fixed set of events in time and leading towards the accomplishment of a commitment.
The elements of both plans and schedules must be prepared and supported by the individual (s) responsible for delivery of that element.
i O
A-3
WORK BREAKDOWN STRUCTURE
- A work breakdown structure (Figure 1) was utilized to develop the relationships that existed between the various pieces of work within the existing standalone tracking and planning systems'of the Organization.
Figure 2 depicts a typical Project - Component - Element Relationship vhile Figure 3 shows the key to the detail that was gathered regarding each element.
WORK LIFE CYCLE To aid in the situation analysis the Five Phases of the work life cycle were utilized (Figure 4) and a scheduling confid-ence level was developed as shown on the same figure. .
PRIORITY Priorities were established in accordance with the system shown on Figure 5.
_ (])
DATA COLLECTION AND REPORTS This program utilized Project 2 as the scheduling and reporting tool which requires structuring and adhering to uniform code fields which allows reporting formats to be developed which meet the users needs. Figure 6 shows the code field use while Figure 7 demonstrates the output for one of the Projects.
CONSTRUCTION / MAINTENANCE SCHEDULES For the initial planning and scheduling efforts to be valid required the uniform transmittal, estimating and receipt of construction / maintenance data. Figure 8 represents the data transmittal form for each element. The estimating was done in accordance with a developed standard considering O
A-4
previous industry experience, station experience, construction standards, productivity factors (local craft, environmental, O radiological) and a contingency factor recognizing the adequacy of scope definition. The element implementation schedules were completed on a form represented by Figure 9 and summarized as shown on Figure 10.
PLANNING AND INTEGRATION For each construction / maintenance schedule that could impact the next full cycle of operation, a detailed logic was developed (Figure 11 represents one minor element). These logics considered plant conditions, material availability, priority, design efforts interrelationships with other elements, manpower requirements and plant locations. There exists in excess of 1500 logic elements within the network. To aid in accessment four types of implementing personnel were designated:
O&M - Work to be accomplished by Station personnel MC - Modification craft to accomplish work for plant betterment programs RC - Regulator craft to accomplish work required by the regulator UC - Utility contractor to supplement the maintenance force for routine peak workload, turbine overhaul, CRD change out, etc.
O A-5 A
~
SCHEDULING
'With the requirement to logic and integrate each element, O(_/ the scheduling activity is straight forward. The Project 2 software program manipulates the data, assigns the resources, constrains by the logic, defines critical path, defines float (time available for one piece of work prior to it impacting the next piece of work), summarizes related logic to a project level report and produces manpower usage reports. Figures 12 and 13 are representative of the systems output.
ANALYSIS Once the base logic and schedule have been established, ties can be added or deleted, manpower constrained, proposed plant conditions altered, float removed, etc., to allow impact studies regarding existing or new commitments.
O O
1 A-6
O O O "i
f_oo LONG TERM PROGRAM 1
PaoonAm p-----__. _______y i
F- 7* vsTEwissur T* - 7*
l PaoJECT l Pn0 JECT l PaoJECT l t___a e___;
I :=. - := _ ::= _ = = .- =
[
- ]
m'== ::==' --
COMPONENT COMPONENT n. l ... ., j-.. l- _.~;-., l miga..j= ,
T
" \
o'msee. oosse ca.es o o 0,
, , l , r/// - ///n scope scope scope ELEMENT ELEMENT ELEMENT AC ua6Paceasse I
- l ACTIvfTY ACTivlTV ACT8vlTY e
- I
w tu t*
o, o o u~
5-YEAR PROGRAM COMMENTS REV a..
MSTH ',18.>. PROJECT Edi,s.o.E, n .R E. ., R E. ., s SHT APP..Y DATE op REQUIRE MENTS SCOPE PRODUCT iMPLEMEh TATION CLOSE ANALYSIS D E FINITION SPECIFICAf SON START UP AND OUT JUSTtFICATION PROCUREMENT TURN-OVER I AND APPROVAL AND DELIVERY como.maat. sy st.m
,,, e , ,,,
,_9 .,,__9._ 9o I I I a l _.
9 I I I E'1%*!#1"'ci"",'"
^%T.'c'."cTe::t"
~
.? h h h O
==:=.=-
cutaveoes.
==.... messm.h %www ssssssssss ws I I I N
H O
i C
0 Q Q
, m -
=- mm i l i I
O O O 5 YEAR PROGRAM COMMENTS REV C
$0$TDs%d'.d. .' PROJECT KEY: PLANT COND.
R
- RUNNINO EDISON PREPSV REVSY S.O. Sv8 TEM OTO CellPANY P.O.
- PLANT OTG R.O.
- REFUEL OTG P.R. . POWER REDUCTION SHT APP.8Y DATE OF REOUIREMENTS SCOPE PRODUCT IMPLE ME NTATION CLOSE PROJ' ANALYSIS DEFINITION SPECIFICATION START-UP AND OUT N O' N JU STIFIC ATION PROCUREMENT TURN-OVE R l AND APPROVAL AND DELIVERY N ME DEV. EVAL. SCOPE JUSTIF. APPVL. SPECIFY DELV. IMPL. START TURN
, CLOSE I.D. PROCURE UP OVER OUT I
OR G. PRIO. PLANT ,
CONDITION TO IMPLEMENT
>l PROJECT 1.D.s \ [ COMMITT DATE
/TO COMPLETE AND ELEM e A l\l[l#
W DESCRIPTION f l , ly,-CONFIDENCE LVL
/
RELATED I N PROJECT ELEM(S) PROJECT ELEM(S)
PROJECT ELEM. CONSTRAINED ST CONSTR AININ G l THIS ELEMENT THIS ELEM.
i l
I H
O
!C "
iN ll ws-um
[ MILESTONE 0 DATES 0 0 0 g- ACTUAL DATE ACTUAL PRocRESS l
i l
l
O d
TYPICAL WORK LIFE CYCLE o
None LIST
. C COMPLETED LEVEL I PLAN u
2 .
LEVEL 1 PLAN o
} B COMPLETED LEVEL 11 PLAN CLOSEOUT PACKAGE o A COMPLETED LEVEL 11 PLAN COMPLETE Task Material to implement Activity Rsady COMPLETED p Available I
w o
Scope Definition Product implementation Requirements Specification Justification & Turnover &
Analysis Procurement & Startup Approval Delivery Requerements Statement scope Defiaed Products specified Task Reedy Pkg Complete Operettag Data / Analyste Alternatives Considered Procurement initiated Integrated with On-going work Problem Analysis Long Lead Procurement identified Task Reedy Package Developed lenplement Schedule Requirements Make / Buy Decision Startup Package Developed Turnover Requered Reevite Leveli Plan Approved Close1ut Package Developed Startup Inittel Approval Justificauon Complete implement. Turnover a Startup Startup Pkg Complete M Conceptual Pkg. Developed Level 11 Plans Approved Accept y lategrated with Emieting worm
.pprovei to Proc.e. integrated
.p.ove, t.witn Esis.
P,0ce. ting work c
50 M
.p.
. O O O PRIORITY SYSTEM RELAYS RELATIVE IMPORTANCE OF AN ISSUE
- 1. THREE DIMENSIONS INDICATE IMPORTANCE OF ISSUE
- LOGICAL JUDGEMENT REQUIRED 4
A. SERIOUSNESS - R AISES QUESTION OF IMPACT ON PEOPLE, RESOURCES, OTHER DEPARTMENTS, SAFETY, FUTURE PROBLEMS, CONSEQUENCES OF NOT GIVING THIS PROBLEM HIGH PRIORITY B. URGENCY - RAISES TIMELINESS ISSUE. CRITICALITY OF TIME
> PRESSURE, ARE INTERIM OR STOPGAP ACTIONS TO 1 GAIN TIME INDICATED I
C. GROWTH - RAISES QUESTION OF TREND OF THE PROBLEM SUCH AS: WILL PROBLEM GET PROGRESSIVELY WORSE OR BURN OUT AND DISAPPEAR.WHAT IS PROBABLE TREND PREDICTED FOR IT
- 2. COMMITMENTS MADE TO OR MANDATED BY REGULATOR MUST ALSO BE PRIORITIZED
?
i a S A. REGULATORY - MUST BE TAGGED BY SYSTEM TO INDICATE
[ REGULATORYIMPORTANCE B. CLASSIFICATION - INDICATES FIRMNESS OF DATES C. SERIOUSNESS - SAME AS 1.A. ABOVE
O ii
)
o r
e a z re er s eA y n a it s e w ds sen nsoya s l no y A EC r onit h s (
a ieti P m gg n m t pi r e e nns o m axdoe t s iit i u cEnil s U tt n t S N o/or c y nne a O .
LlCP y S -
l eem z t I a C a mmt i c T tttG t i eer n P ninR e n c ll a a e I j R
apaO f a e p p p, g o C
lalU i l PCPN L P S p mme r r S IID O P E .
D -
O E D
O C I 9 9 I 9
. D R
A D 8 l 8 8
_ N A
T
_ S 7 .
7 I 7
6 6 6 5 5 I 5
4 4 I 4
I 3 3 I 3
i 2 I 2 I I 2 I
1
_ 1 1 E 1 I A B C O;
yg m s :oM m
O O O FIVE YEAR PLAN SORT AND SELECT ANALYSIS l
I
!I (32 AUGMENTED OFF-GAS) i DE SCRIPTION REG NUORG URGENCY GROWTH PLANT RESOURCE ELEMENT CONDITIONS NUMSER CLASS PRIORITY N/A B4 PRIORITY HIGH STE ADY (R) PLANT RUNNING TECH 32010101 R/A EVALUATE AND IDENTIFY SOURCES OF WATER IN AOG SYSTEM PROSLEM STATEMENT: SYSTEM ROUTINELY SECOMES WATER
>i SOUND AND LACKS DRAINING CAPABILITY WHICH INTERRUPTS OFF GAS FLOWS, SLOWS LOOP SE ALS AND RELE ASES H RADIOACTIVE GAS W N/A B4 PRIORITY fHQH DE CRE ASING (PR) POWER REDUCTION TECH 32020101 R/A ID T CORRECT VALVE PROBLEMS (LS ETC)
PROSLEM STATEMENT: VALVE POSITION SWITCHES AND DRAIN VLYS WERE MISAPPLIED IN ORIGINAL DESIGN. OTHER MISC VALVE PROSLEMS EXIST (PCWo TO PREHEATER, ELEVATION OF LCVe AT LfHw SEAL)
N/A B4 PRIORITY LOW STE ADY (50) SYSTEM OUTAGE TECH 32030201 R/A UPGRADE AOG INSTRUMENTATION ORIGINAL AOG SYSTEM INSTRUMENTATION l$ DEGRADED AND/04IMADEOUATE N/A S4 PRIORITY LOW INCRE A$ LNG (SO) SYSTEM OUTAGE TECH 32040101 R/A DEVELOP ME ANS FOR CHANGEOUT OF AOG CHARCOAL PROSLEM STATEMENT: AOG SYSTEM CHARCOAL CHANGEOUT l$ NOT F AC3LITATED BY PRESENT DEssGN N/A A2 PRIORITY LOW STE ADY (50) SYSTEM OUTAGE TECH 32010202 SOJA INSTALL (ADD) REMOTE OPERATORS ON ORAIN VALVES AND LEAN OFFS PROBLEM STATEMENT: AOG SYSTEM ROUTINELY BECOMES PTj WATER BOUND AW3 LACKS DRAINING CAPASluTV WHICH H INTERRUPTS OFF-CAS FLOW. SLOWS LOOP SE ALS AND C RELEASES RADIOACTIVE GAS i
C N/A B4 PRIORITY LOW STEADY (SO) SYSTEM OUTAGE TECH N 32030103 PSPD CLOSEOUT EXISTING AOC PDCR trj PROBLEM STATEMENT: EKISTING AOG PDCR is PARTIALLY OBSOLETE 4 N/A B2 PRIORITY HIGH INCRE ASING (PR) POWER REDUCTION 04M 32050104 ITAS RESTORE *A" CATALYTIC CONVERTOR PROBLEM STATEMENT: "A" CATALYTIC CONVERTOR APPE ARS TO SE INOPERABLE AND HAS NOT SEEN IN SERVICE FOR SEVERAL YEARS l
i l
l
Revision Date
() FIVE YEAR LEVEL I PLANNING
- 1. System / Issue: No. Description
- 2. Problem Statement:
- 3. Scope Statement:
i i
i l
l
- 4. Priority:
- 5. Funding: Capital Expense Authorization No.
Work Order Account CA l
l
- 6. Products Required:
(Analysis, Report, PDCR, Spec, etc.)
O V
l l
A-14 FIGURE 8
G. Special Construction:
(Tools / Methods)
H. Constraints:
I. Work Areas II. Manloading III. Procedures IV. Plant Environment (ALARA)
V. Other
- 9. Turnover /Startup Requirements:
(Training, Spare Parts, C) Procedures, etc.)
, 10. Closeout Requirements:
(Documents, etc.)
O A-15 FIGURE 8 l
l
- 7. Work Assignments: BECo Contractor
( 'h,) A. Analyze / Design (Group) (Specify)
B. Procurement (Group) (Bechtel/Other)
C. Installation (Maint/CMG) (Bechtel/Other)
- 8. Implementation:
A. Material / Equipment:
(pipe, valves, con- (Indicate size, type, qua,ntity) duit, cable, etc.)
B. Plant Status: Running System Outage Plant Outage _
Refuel Outage e
(,q) C. Plant Work Areas:
(Where? - elevation, quad, building, plant coordinates)
D. Pipe / Conduit Routing:
(From - through - to)
E. Interferences:
F. Mods to Associated:
(Systems / Structures)
O A-16 FIGURE 8
s a _ as. A J 2. __
4 4
4 f
D SW g
, a a.
1 b
4 O
E
+
5 m
=
M a
w 1 3 y
w 2 M 1 M y
- c
.a 2
w O
c w 5 E I
en M
i .
- 5 m
=
i
=
n
. I Z
e, m .
En3 b
s-t -
l M
E N $
?.
w V 3
1
! l l v' r
i A-17 FIGURE 9
,l XN _
IO _
MI T
WA ER RU h) CD (L 3
/- )2 1
G N
I r-1 TY r NC ON CE 5 5 6
/ i 1-X
/-
G r O o L
O M RI /
T S '
U _-
J D X
/
A
- r N o -
/
O R A I
V NT N E E M Y 5 R 5 1
A -
M I X D)%
M U
S S
H D
o-CN Bg E
/ ., - /
M DS -
TRH IAME FD S KNTA CAIB ATN BSU-N O
I T
P I
R C
S E
D y
T N
E Q M E
L E
- M9m m o_
2
-- am y; h 4 2
o " s -
( <2 o
o-Qu'
~
Cn A o .
n s w e %. Eo an Wo -"
, < --<- u<w s a o w W -I gh d v, E N p s_ g eew; < a2d 8 3 E [ 55*f. N cow V Te
- -o
== m oc$ w E n r
- WW---
a"" > wa r a w go w
~ -r w n M
- ,e3 H 0 d'2C s=-= l 5<o 1 e &<
4 WW O *
< O M o *t** d .,,a J ~
z "o o x ks.=as56 m ea u,w2 W < > d e eo e \ Zu o O C *~ LJ O O
< 2 **#* H OM E > 0 W W - * ** Q QN N 3 w r J d 4 .
W wd 4 o b a N
' QM LJ N w 7 2 e w Qm ow O
Cf Y w c P- O J o$< wY Q
1
- w ca *,
C-or T. ^
T o E o <
<A
- N .s o C: e L U L 7 0 I
T C cd CO " O ?O ho Go Q O O
, & . @ 40 s v ,,
c, -g-es --s es--- ca --t - --*t - -- w - w e O ['
a 4^
O T 3 @
O
--$w 4^
Q
--[w s C
O T O
s a
O 8a t, O' -%
d 3'
4 g
v O.,i., .
v o .Z, w e O .;.;.
. a s
o .:;.o,s
- v o .Z sa v
o.,
=
v' c'
~
A 33 = A A jg A 2 .340 A 24 A
^y=2' A,
- xt - ,
~
2
?r5 143 d0
- sf*
- yW \ g
.r
'W .
l l [
6 b b
\ ! ) 2 L
\/ / fo &* 10
, 4 a c Co8. m e , o =-ad = =--e - =-
2 O*~ ~ # Y~s # JU C
< o3 y.'
ca .
c .
l,s, at o T T, , a g o d "E E g $' 1 y $' = *~
~
to 3'
~
1,g
\[/ :: Nl*'
'. )7 :: 3 3%
! 1 J
> 1 e M*. **
m a ej--u n
v c ->
y a
O o 1 L:
5 i
i O
c
}
4 8
A
- A -e 8 -
5'3 O
o
- n *A o -- ,
9 -$
4*
o -h
~w 4
Q o' N88. a T
o [E a are a a p NYa -
Rd i
Abi 1 005 1 1 1
x l
d A-19 FIGURE 11
t t
i 9 M
F *
- A 4 fE i# E a t' M S
2f
/9 4 4
'C t 8 C" N O
E s F 39 C U R 4
- J PB*
4 J 4 I l
1 8 M R 4 A l
8 v
n 4 A A I
4 9
8 9 M l 4 8 I 1 M 5 8 N I 2 4 R A 8 P J l F R A 8 I I
I A l 0 1 4 4 8 4 J 9 M
1 f a
1 3' 8 3
E 8
E 8
E l
I D 3 8 A N [ F I
F 6 IF 3 8 .
J
[3[
1 P
I N E 5
6 2
1 3
8
[6 C E
D 9 V 0 t
0 2 3 1
0 8
[ 3 S I T
t M
T I S 3 8
3 8
C 0
[ 9 2 [
N O
M A 3 8 [ N U
N U
1 3 [ 3 8
[
l Y J J Y 6
3 J 8
A 1 [ 3 2
3 2 [ A 1 3 [
FL 8
[8 I
/ A Dv R
9 1 J 3 1
~
I
~ -
R P
[ -
I [
EE I
A DT 0#l 1
r I N ~ I I 3 8
~_ 9 1
[
[8 I
3 3 B IlI A 3 r 8
f E [ ]
[
f A A E
[3 I
D L
U M R P ]8 M 2
M 2
3 8
3 2 ]3 8 8 F
l A N N I N N M
C F 8 2
A J
1 1 A
J }J [ 3J
[@
S I 8 8 G
w J 2 l l 2
I 3
i 8 m N 4
A J
A 8 8 7
2 O
L S
P E D
O 7 C 4 C A
M M
o f s R O
S IlI
?
w ma I 0fr 11D AC 2
E1 N AAS DCI LA D 9 O MOE ,
C -
ACO JB 1us O
O
_ LC D _
fE E uS N L F
E O A R N T C I
S
/
S I E T N
Fi r
E L I
I R
f n N C
_ o ir i
r G C
aO E -
mN AU E I JJ M C 8
24 U E N L L V I O L R N
0 V A O l R V T Y I
( E E I L L
T G 4, T N P IRP A S R N O P I A P O N E I A 4 E M U TSC E P R H E 6 V S T R S O C P P N S R E P S i L D M R Y X E T P I P L N E E 6 H O A -
0D S T J D A A T W C 0o DI A L S C W O L S 1
/ r i
N N W P N R K E S S P E O E D E E A I C C U U U G FF r / ses L P E S P I R C O R R R S F N EE RR e A P E A I M C E L U O O P E I w P S R B P R R K f t H A F B i T T C R E s.
e O
Jf s oO 5 6 7 8 9 4 2 3 4 6 7 8 9 0 W p L e 2 3 J J 3 J J J J 4
- m 2 2 2 2 J
Ibo HOC [
i/*T V Q U
, CRAPfC REPORT WRITER j F1ANPOWER AND 00Lt. AR DISTRIBUTION l
FOR NRC C0tittliit1ENTS muttouRS 30000 -
U s
p aroo.- .
3
=
emo r
aiooo -
i .- -
> 13000 -
3.
j *g I
hJ 3%
~ .! %.
.2000 -
,% j %,
! \.!
T i
i %
.00. -
/
~.-~---% .
.t 3000 -
. . %. i.
,,%**** **.,,,==******
{ g m
H
._.e:*_____________________________________.
,_~.
i /
t g m /
C * "-
.& . -- . . ; . r7. . . . m,...; ,nv..; ."n . m,- . pa . . .rt .m... . r .. ; "-- m.: .--...: . . - - - :'.- '
M ?!.ke? " ^"
~
u /. .s?rrr= xr
,a gee .. f,en..e
. ,1
/ .27.'".L.. 1 . * ' "
/ L' 'n-
k >A L m 1.- + _,,-
,:4-,.- - a -a A a - u a _- - ,
1 f
1 i
I i
ATTACHMENT ,
B me ,
LISTING OF REGULATOR REQUIREMENTS BY SYSTEM / ISSUE 4
I i
I l
l I
i i
P O
-r, w-,- ,,m--,.~-~-----~-e,-
~ I
-) ot t
- \
I F I VE Y rA R P L A N 00'iTON EDISCN COMFANY g ;
- *
- 5 0 R i '
% ts 75 TF I?A"Ju3 1511693 & L E LE C T A AA L Y S I S * *
- P RO JE C T START 3JAN83 In0 JECT: tyrA>A NUCtrAR ORGANI7ATION O
On!GINAL COMPL. 3JAN83 rr5 - r, 31ATInN Cuf tPUT E 9 EJECT NODES DATA DA TC 3JANR3 PAGE 1 g rt: .r N T UE '
C r! P i I O N CEG NUDRG UR GE NC Y GROWT4 PLANT RESOURCE NU" v7 CLASS PRIORITY CON DI TI CN S g 6111201 R/A CoNivl RPOM REVIF W R3 R4 (7 ) TECH (NED) g U"C HLt M S T A f f F.E N T : r .
- N T C O '4P U T E R IS AGINb R U,a r t_ I A HL F paris ARE UNAVIALPLE ADDITIONAL C t.P A C I T Y IS NEECf3 i PROPLEM3 HAVL TFCH SPEC g 1" PACT.NUUEG f)T?7 SurP I REQUIRES ADDITICN Cr < ,0 5 5Y ST E M.NE W C C"1P U T E R WILL HEOUIRE C P N V F D S I Of: 5. AD71 TION OF SOFTWARE g (711531 ' / .i l' I WUTS/0UTPUTS '. rrRIFERAL CONF IG. P3 fi 9 (R ) TECH (NED)
(INC ar AS5 SIONAL CAPAq!LITV) lorut 4 : t A f f. M E N T P L AN T COPPUT E R IS AGING &
O O'4 E L I A Pli PAPT5 ARL UNAVIALHLE ADDITIONAL g C.S ACITY 15 MIDP '. P R CPLE ftS HAVL TECH EFfC g trPACT.NUCL3 C T ?. 7 SUPP I R E '2 V I R E S ADDITION Y ST N 3 Sr sIE M.NEW CC"PUTEP WILL REQUIRE 7, C O N V t. P S I O N 4 ADDITICA 0F SOFTWARE g
(:119 $ C 1 P/A INTEGRATE N r' W COMPUTER SPOS R3 04 (R ) TECH (NED)
- g M C 5t t r. M SI AitMEN T
- PL AN T COMPUTER IS AGING 8 g UNPfLIARL$ PAPTS ARE UNAVIALCLC ACDITIONAL I ni- A C ! T Y IS NEEOFD r. P R 0!!L E N S H A VE TECH SPEC I u r A C T . N Lt d E G 9737 SUFP I REQUIRfC ADDITIPN $
("- 9f D3 5 Y S T F. f t .N E W CCPPUTER WILL REGUIRE C DN V! P S I C". -
- A30!TIOr, OF SOFTWARL 3
9 0 i 0
O O
(3
i o
I
. I t
r F I V E Y E A R F L A N 8400 TON FOIS CN COMPAN Y g l i
u t i'J 1str 12Appf? 1,17F P S * *
- SO R T & S E L E C T A N A L Y S I S * *
, retr e
.__.____.... ___...+_ __..._..._.......,__....__.s____..._.+ ........+___... ._s.......
DATA CA TE 3JAN83 PAGE
.+______...s...._____+__..__.._+.. .........
2 g r tr v. N T 0E 3 C 4 I r i ! O N HEG NUORG URGEhCY GROWTH PLtNT RESOURCE
's A L" E ' CL ASS PR IORI TY C ON91 TI CN S g 1/S r, 04 TECH (NED) s 7 '111 ' C 1 O # UP P C.i l TO Cn" PLY WITH NRC S'; C UR I T Y R3 (R ) g W 1Uit E%NT3 P 'i P t L L M s i A T E .vE r4 i : NCNE P P 0119r e 71's0? '1 .r / t. RCVira F. iLAL E rr . C T IVr LAY TO IrJS T RUME NT R3 F4 (1) TECH (NED)
CURIi Y r r NCr
, P < 0 t* LE fi STATEPENT: NCNi FROVIDED g 9
9 9
9 3
1
. 3 0
J t
O i O
I -
O i 4 ,
) (
- r. ) ol i
eI i
F I VE Y E A H F L A N ROSTON EDISON COMPANY g i nun DAIr 3 ) A r. l a 3 1,17h13 * *
- G OR i 8 ". E L E C i A N A L Y S I S * *
, ..___....._......_....._..___....._......... ..._ ...................+_........+ ......_...._______.___......+..___ .....___ .___.__
st.c* NT C E 5 C h I 9 I I O N PEG NLORG URGE NC Y G tt 0 W T H PLANT RESOURCE w7
_ _ . " . _ . _ _ . . . . . _ _ . . . _ _ . . . . . . . . . . . . . . . _ _ . . . . _ . . . . _ . . _ .CLASS
. . . . _PFICRITY _ _S . . . . . . . . . , . . . . . _ _ _ .g. . .
N I.
. . . . . . . . . . . . . . . . . . + . . _ . . . . . . . . .C_ON91
. . .TI. CN 43?'101 3/A u ' I C, N AND C oh iH!C T HAZARCOU3 MATERIAL R3 P4 (t) TECH (PT) g t'li ! L C I N G P30DLLM S T A T E ME t; T : P 4 r' ~ t. N T F ACIL I TIES F OR HS'A40001 MAirPIAL STORAGE IS INADEQUATE g aq'710* IT8c '
3IrN ann CONSTRUCT GAS 40T TL E STCPAGE R3 D! (9 ) MC 5tCIL!TY g r u C 9 t *' M 5 f A f t !!E N T : F.<! STING FACILITY 00FS NOT CnNFChM T T' CODES /%iAA3AAL',.
9
.i 9
S 9
3 O
l 0 i O 1
l '
O O
4
- v. J .
O e e as F ! V E Y E A R P LA N 00STON EDI50N COMPANY g oVN 7 ATE 12 *. ; i s _t I SI Ton" * *
- S 0 R T t nE i E C T A N A L Y S I S * *
- PROE CT START 3JANa3
- r w C.IP C T : ~YFA!A r NUCLFAR ORGAN!7ATION 09tGINAL COMPL. 3JAN93
,- C O Dr - 11 C4D '. f S T E M S EJECT NODES
.___.......... .........___. ......___.,............. .____+.___................__....___. ......__,_............._____, ________..-
DATA CSTE 3JAN43 PAGE 4 g FLrPrNT DL ". C 4 I F T I O N WEG NUORG URGENCY G90WTH PLANT RESOUPCF
, N L" " R CLASS rRIORITY CONDI T! CN S g
. . . . . . . . . . _ . . . . . . . . . . . . . . . . . _ . . . . . . . . + . . . . . . _ _ . _ . . . _ _ _ . . . . . . . . . . . . . . . . . . _ . . _ + - _ . . . . . . . . . . . _ _ _ _ . _ , . . . . . . . . _ + _ . . _ . . . . . + . _ _ . . . . . . . . .
, 11010731 P/4 iVALLATE AND tir 3 P ACE CR0 HYD. SYSTEM R3 P4 (P O) TECH (NED) g ovNAFICS INCLUDING LATER HAMM;9 rR 3HLt ft 5 f t.T E ME N T :NR C WILL SCSN PECUIRE A00!NG
, WATED HAMMER LOA 35 TO C40 FIPE ANALYSIS WHICH g WILL 8ECUI4E h E AN AL Y SI S & F O *J I H L E MODS
, 1104^11' P F :: N S I S P, ? KtDUNCANT SCRAM R3 P1 (P O) TECH (NED) g C'5ChARME VOLUMfG AND HEA7ER DRAIN LINES r o q [il e v ;rArgetyr; spy upopADF 84EGUIREC.
11140139 I t ^ INSTALL P REOUNCANT E C R A r* R3 P1 9
(P O) RC r[ CHARGE V r' L U P E G ANL HEADER LRAIN LINES WOHLF M STAILPENT: SCV Urf,RADE REGUIRED. g 1104120' D'<U J SIGN SOV VENT VALVES AND R3 P1 (P O) TECH (NED)
P I I N G
- t Pa0PLEM STATEPENT: SCV UrGie A DE REQUIRED.
g 11041?0s I T <. , I N .; T A L L MV Vf NT VALVFS AND R3 P1 (' 0 ) RC g rloING p q r, alf P TTAIEFENT: SCV UFGRADE REQUIPED.
11143305 "SPC !" E T M AN7 IN 1Att SUV DRAIN V ALM S AND R3 81 P O) TECH (NED) e i r i t,g
, O'"0 PLF M :TATEFENT: SCV UPGRACC REQUIRED. g 11141334 IT'S !*i T AL L '; J V 9 3 A I'J VALVES AND R3 P1 (" 0 ) RC
, rh7it6 fl CTAILFENT: SCV Ur'iR A DE RfGUIRED. $
110'*0405 D*'; f ", I :.N IMPROVEJ %CV INCTPUMEN- R3 n1 P O) TECH (NED)
TATILL Sys tr e ANO cAFINET:
r : q qt' n s t :1r ty N1: *HC SUV UMRRPt TO SILGLE 9
fn! LURE P > nnr / S' P A:4 A li C ^YSTF M .
1194n414 O
ITe- 13 ; TALL I i1 P l> n V i ' DV I t.S T R UM' N. R3 t- 1 (' 0 3 RC T a T I r t! :) ,1 F M AN3 ( SG!N Tj I: 7dLEM 'i l A l i t'L N T : NoC V Ul SH Au' TO C ILGlf Q l rAIttrr r.ccr/m rr.nAlea rvETir.. I 111,1111 P/A IN 9 f SLL J. T A 41 L I 217 G U L Vi e g3 ul (' 0 3 TECH (NED)
('1RL'" ;TA1;" NT: N L i r 3 161 t' E C U : h t "E P, T TO Q
't i te t r t f r r$ Pr T R A ' #. I'NT".
11150?C1 R/i r V AL /M rL E Ct ~U';GN "TEtt caC RWCU F v P A U ". T R3 O
P1 (' 0) TECH (NED)
L ." 4!TH dlT NLE '_ T E E L 0 .l
b.- O O .
Crre- 11 Ug ty;TEMS EJFCT bOCFS DATA C4TE 3JAN93 PAGE 5 g ,
J __.....__.___.........__...__.............___.___.___.................-......................__........... ......_ . ...............
~Lt"~NT U E ',C P I F' T I O N PEG NUORG URCE NC Y *POWTH
, PL A NT RESOURCE N L" 'r 0 CL ASS PR IORIT Y C ON DI TI CN S g f N o r t3 ** STAT;"ENT: NU7LS C61?: PDTENTIAL FCP C r' A C F f IN I k f4 0 2ilf !. 3 C77 RLTURN LINE N0ZILES. g i
9 9
9 9
1 J
9 I
I
- - o i
3 9
- a i
9 3
f 6
l .
OI O
3
j o{
, . I !
(
- s F I V E Y E A R P L A N B03 TON E3ISON COMrANY g '
% f4 1A17 17tr;s3 l' 17eP S * *
- S 0R T & S E L E C T A N A L Y P I S * *
- PROJCCT START 3JANB3 l'
r> w ct:
O yr a g t. r:e:Lr As ORGANIZATION ORI GI NA L COMPL. ?JAN93 l 6
!, CoCe r 14 A '. C I 9 U L A T I O N ",YSTEM EJECT NODES DATA CA TE 3JANR3 PAGE 6 g r i E '" ?! i 0 E . C R I F' i I O N REG NLORG UR GE NC Y GROWTH PLANT RESOUNCE f fM " n CLASS PRIORITY C O NDI TI CN S g r 1471')I04 T T '. ; INS. pr.c!pc wrtg5 ANc rVALUATE INSPECT n3 el to 0) UC g RiSULIS FN O P L E 't "TATEPENT: RECIRC AUS SS PIPE ExHIDITING C r< A C v 5 MUST FL RFF-LACEC AND/0W RrPAIRED g (Ifn 3 01).
, 14 0 ": n I 1 's ITtr INSPECT J1 P t J f'P e t. A *' - R3 f3 I (4 03 UC g r1ChlEM STATEMENT: GENERIC JET PUPP UEAM INSPECTION RFOUIRED FOR PO TE rJII AL
, C ' A C k ". . g O
9
' S i 9 9
'D
') i f)
Ol 4
O O
/\
l l
^
OV l ?
( ei l
rI V E Y E A R P L A N 903 TON ED IS ON COMPANY g 1LN nAfr 17annpi 1,3 79p s . . . sou I & S ELE C T A N A L Y 0 I S * *
- P QO JE C T START 3JAN63 1
! P'0F CT: SVEA"A f. U C L E A R CAGA1IZATION ORI GI NA L COMPL. 3JAN83 e
l rnc : li MISC r L F C T '< I C A L EJECT NODES DATA CATE 3JAN83 PAGE 7 g
............_-.... ..........+_-----.--s.--............-___e_...--.-_+......._-s.-......_s.__...---+.. __..._s.......__s.__--..--+-.
l F LF ' 'N T DE S C 4 I P T I O N REG N L:0 R G UR GE NC Y GROWTH PLA NT RESOURCE NL H r >
...'._-_. ...___..........._-. __-- ...............__ -----....----... ......__ ......._...-__ __ ........-___,_____-__ ......____+..
CLASS PRIORITY CONOT TICNS g o/A M'P:ITCR x l AND t?2 AND t V ALU ATL MOD
~
1 ".? ! 9 ? c t R3 P4 (90) TECH (NED) g FOR LOAO "ALAhCIhG
! P 4 0 RI.r f* STATEPLNT;UNCLR CE RT AIN CPERATING COND I T I ON' T H A f4SF O R"i R O x-21 R M-22 C AN [ kFE RI g f4CE ACCEtt R A fl C AGIAG CLE TO LO AD IN G 9
1 3
9
, 9 3
1 0
0 0
0 >-
s i
t al 1
o
-s
- 4. o m xs o [
I O
O[
n f F I t E Y E A H F LA N 905 TON EDIS ON COPPANY g '
auq Pair t?AP799 ? ;17up ; * * * 'i 0 R T E #, E L E C T A N A L T S I r *** P 9O JE CT START 3JANs3 PGGJrtT: ..yr p A Ng;Lt Aq O R r;g *JI 7 A I I C N Op! GI NA L COMPE. 3JAN93 roCE- l ' ! ', C EJECT NOCES
______.....__'.__'......__.___'AL T R U '. T U DATA CA TE 3J AN8 3 PAGE 8 g
- LE""NT C E ". C 4 I P T I O N REG NUORG LRGE NC Y GROWTH PLANT RESOURCE NL" C. CLASS PRIORITY g CONCI TI CN S
, lo3M"10' 3CJA H VIEW OPrfiATGW TRAIN!NG PROCFDLFES WITH R3 P1 (R ) TECH (PT) g PrGaeC0 TO LIF TIN ANO DIGGItss P004LEM SIATE"ENT: NL9E S 0613 ISSUED WITH AN GiJECTIVE TO CONT;CL MOVEMENT OF HEAVY LOADS TO g
FINIv!2F LOAC C9005 AF FECT ING SAFE OPERATICN/
"HUTCOWN OF FLANT.
' a 13 r' 10 4 I T '. e, pr VIF W OPFPATOR T R A l f.I Nii P PO C E DUPF S WITH R3 P1 (9 ) 0 & M FEGAPDS TG LIFTING AhD RIGGING
, OP09Lr H S I A T E M E P. T : N L r: F G C619 ISSUEP WITH AN g WiJECTIVE TO CCNTRCL "0V7"ENT OF HEAVY LOADS TO MINIMI?F LOAD DROrS Ar F E C TING S AF F OPERATICN/
, CHUTCcWN OF PLANT. g l uG 3 U0? 30JA " ". T A a L I S H " SAFE LO AC P A TH3 8 INCORPORATE R3 bl G) TECH (NED)
I',10 pnp; p,a r)C E D UR E g
1% D H LI M STATEMENT: NLkEG 0C19 ISSUED WITH AN noJECTIVE TC CONTRCL F0VIPENT OF HEAVY LOADS TO
, "INI*!/E LOAD 09 CPS AFFECT!t,G SAFE GPERATION/ g
" H 'J T C n 'W N OF PLANT.
.; 191'1?09 I T '. " r 0 T A "L I 'iH " SAFE LCAD PATFS & INCOPPORATE R3 P1 (R ) 0 & M g INTO PNPS PFCCECURE rc0HLr M :rATEMENT: NLREG P s 19 ISSUED WITH AN g 0"JECTIVE TO CONTROL t10VL"ENT OF HEAVY LOADS TO g FINIFI2F LOAD 04CPC ArFECTING SAFE OPERATICN/
WUTCOWN GF PLANT.
la?tSin? 3'.la rrAFGbH A DESIGN F E V It W CF f*ECHANICAL R3 (31 P) TECH (NED)
LIC TING t r.U I P
, ua0ntrM S T A i t v.i ra T : N L9 E 3 Of19 ICCUED WITH AN ()
C JFCTIV TO CONT 4CL MCV!"ENT OF HEAVY LOADS TC MIF.IFl?L t.C A D 090 '7 Ar r i C l i N's SAFL CPE k Ai! ON/
".H U T C O W N 05 (' l A N T . '
Q .
1'1v40' "'JA Ar ALY?5 "NnN I I N ',L r ,AILLqE Fr09F" C f, A N F ' A3 r1 (t) TECH (NED) j To E T. C P r# r, s M A N . E F'4 FEAVY L9AUe P o t t.t v CIAI. VENT: P! L 7 '.1 361
- IS"UF O WITH AN Q ,
f' 2 J F C T I V TO C T4 T L OL '4 0 V s. < r N T Or bEAVY t r: A r t TO "IN!Flyr L7Au 3p p - UFECTIN., SAft nrEAAlfrN/ g
"."UT M N " iLANT.
I M 'P l? CP IA ")TAF FrLL1W-UP K I I'1 N ( 7 5. V I S E F300~ DUN T F3 ri O) TECH (PT) Q miacear- n a n y.! A a P,Cet: P " TAT: .T: d* UIn.P:4TS AN AL YSI: F E"UL T S
-s
.n ) oj i
e i
t r0Cr: la MISC ",TRU TuaAL rJEC1 NODES DATA OS TE 3JAN83 PAGE 9
..........__.._____.._...............__.__ .__.._+____ ..._+__._____.._.. ...__..........+....__....._...____+________...._____..+..
g {
' L E T.~ 'J i 0C S C R I p T I O N REG NL'ORG UR CE NC Y GROWTH PLANT RESOURCE l NL""r4 CLASC PRICRITY C 3 N CI TI CN S g '
.............._.__ ..________.____..___.............._.....,____...__+- ....__....____.__....___...............__....__,____. .__...
10 0 t r! 614 I T e. ; si t Avr FOLLO -vr ACTinN (DEVISE PROCEDURES R3 P1 (R ) 0 & M g F'U RC UA SE H APh ARE f" O P L E 'i alATEMENT: RFOUI6E FE N T S ANALYSIS RESLLTS OF HEAVY LOA 00 "UST PL TAkEN TO COMPLETION. $
1 n191<,0 ? . JJ A 6 ) F I L r, rIggt 9ErnaT L1TH NRC 00CUMENTING P3 P1 (a 3 TECH (NC3)
I'd oiill M OTATEMENT: H 5. A V Y LOAD ACTION PLAN CLOSE- G CUT.
f I n1 "13 ? 7JA n L V I E .J LGA00 TO Fv! STING STEEL FNOM R3 F4 (3 ) TECH (NEDI g SYHUCIURAL '10 0 "3 P90PLfM LT Af r ME NT: VARIOL" PROJECT MODIFICATIONS (f.E., PLOCNWALLs. BASE PLATES % PIPE SUPPCRTS) g HAVE wr SUL Tf D IN NE W LOACS TRANSMITTED TO EXIST-I 'l G !!RUCTURAL ". T t E L .
9 9
- i. p 4
1 1
1 i
3 i
O o ,f f
O; I
O
,i
l l
... J o' I
'e e i
, F I k E Y E A R P L A N BOSTON EDISON COMPANY g {
PUN ~) a T F l'APR'3 I S 17H R e * *
- S C D T E rEL E C T A N A L Y S I 5 * *
- PR3dECT START 3JAN93 ,
I"0JrCT: iYrAdA f,UC Lr s q op3ANIZATICN ORI GI AA L COMPL. 3JAN93 l, En? - l'a o f f V L / Gt N F. R A T O R FJECT NODE 0
....__.... ....... ....__..__....................+ ................__,...............___.+........................___..+ ________...
DATA CA TE 3JANA3 PAGE 10 g i
rtrurNT U E S C E I P T I O N HEG NUORG UPGEACY GROWTH PLANT RESOURCE Nt i:4: R
_ _ _ " _ _ . . . . . . . , _ . . . _ + . _ _ . . . . _ _ . . . . . _ . . . . . . . . . . . . . _ . . . .CLASS
. . . _ _Pit!CRITV
_ _ _ _ _ _ _ . _ _ . . . . . . _ _ _ . . . . . _ CONDI . . S_ _ _ _ _ _ _ + _ _ _ _ . . . .g. . _
_ . . . .TI.ON I, 19010101 7/A U SnLVE LOAC!hG T ! fiE FOR JIESEL GE NE R A T OR R3 Al H) TECH ( F' T ) g AND "! T T S LE R A ?.C L ri A N')
P'0"LE" STATEP NT: DE">Ir>N 00CU's 00 NOT AGFEE
, WITH ACiust DIELEL e, E N E R A T C R LCACING TIME. g I
O
.f h
9 S
h 3 9
1 k
i O
i o! i i
Ol O
i
j s.
.s ol i
, F I V E Y rA R P L A N 90iTON EDISON COPCANY g l a u f. " A T ': 1?A'a93 1 ",17 e 4 C = *
- S 0 R T 5 c. E L F C T A N A L Y S I S * *
- P RO JE C T START ?JAN93 '
PeatrCf: ' YE A ( A r;UC LI A R ORGANIZATION ORI GINAL COMPL. 3JANH3 C ' Or - 1 NUCL8Ao ! *H T R U P4 A N 13 T IO N EJECT NODES DATA CATE 3J ANB 3 PAGE Il g .
.....................................................................+................... ....................................... ..
r i r " ~ 'i T D E . C P I P T I O N REG NUORG LR GE r,C Y GROWTH PLA N T RESOUPCE ,
'J UW 7 CL ASS PR IORI T Y C O N 01 TI CN S g
'901110.' *0IA Ut VI;r TECH SFEC FOR B Y P A ",5 s
FUNCTION R3 B4 (R ) TECH (NED) g 4 ON A M ' '4 " 5 EnaaLEH ST A T E '4t N T : E x !G T ING CONFIGURATION ON A;'4 F / f F P M HYPA03 SUNCTION P0ffNTIAL FOR g VIOLATION of TECH Sp r C 3.
9 9
9 4
9 9
9 1
9 I
i l
l O!
! O o
~
- _m __ _a
Y o
I e
f% g a I
l a f I V E Y E A P P LA N 901 TON EDISON C O P 52 A N Y g 7UN 157E 10Ar"F9 l'17"RS * *
- 0 0R T & c. E L E C T A NA L Y S I S * *
su> 0.J c : T : ; Y '. 0 :A NUCL! A R ORGANIZA110N ORI GI NA L COMPL. 3JANR3 i
, c q qr - %, 1T ANrmy r, A S TFEAl"FN1 EJECT NODES DATA CATE 3J ANH 3 PAGE 12 g Li "r *l i O E SC F ! P T I ON REG NUORG UR r.E NC Y f'ROWTH DLANT R L P.0 U R C E
, %LM 'I' CLASS PRIORITY CON CI TI CN S g ,
, ?c0M10' r* -'O SU"MIT A FEPS9T VLd!FY SV'S REPLALED R3 P4 (R ) TECH (PT) g an C U"UJ T CAMPER PEPAIR A TEST 00CUPENT LU4V. INS. CCCUMENT CH AWING VERIFY
, ODCUprqi pcy,3 p I"' 0 8 L F M S T A TE ME N T :10 /2/ 91 FAILURE TO PASS 9fCONDARY CONTAINMENT L E T. < RATE TE ST HAS
, F PUL TI C I tJ trR 81-55 g 9
9 e
9 9
9 t
9 r) '
l O
O 0
0 h.
m _
j O
^
- e 1
- a F I V E Y E A R P L A N A F TON CDISON COMPANY g .
aLN asic !?sona5 t r. l iop t * *
- S 0 R i %
E L E C T A N A L Y S I ! * *
~ L P F '! T
......_'_'_____._______...____.................__.._... ......... ___.... ........._...............................+.......__ ..
D E ". C F I P i I O N REG f400RG OR GE r.C Y G 9 0 W I64 PLA NT RESCURCE NU"" A CLASS PPIORITY CON 31TIONS g
'A111191 R/A It:S T AL L t A "> $ IC P 101r C T !")N/ ISOL A T ION T OF R3 HI TCCH (NED)
P O) g P P ". PtN F P JUPPLIE' in PEET NPC'a ronPLEM JTAILw.NT: "F" PCWER '2VPFL IF S NOT C L t.E S
, If PFUTECTED. g
\
l l'
1
- a g
is 3
-( $
- / 9
'D
')
9 0
0 0
i 1
0 ;
i l
0
- v. - o
' n g 1
, F I V E Y E A R F L A N POSTON E31 SON COMPANY g '
'< u 'J 21TE 1>A'44 1*>17HRE * *
- S OR T F. 5 E L E C T A N A L Y C I S * *
- P93/ CT START 3JANR3 ,
i'" O F_ C T ! ' : YEA 7A N U C L'_ A R ORFsANIZATION ORIGINAL COMPl. 3JANA3 I
- , r n 'r - ') w4 9 / C 1 A l-
- PkAY fJECT NODES DATA CATE 3JANA3 PAGE 19 g f L t *" 'J T 0E , C P I T T I O N REG NLORG UR G8. NC Y GROWT4 PLA NT PESOURCE
, fL" d CL ASS PP Icp!T Y CONCI TI CN3 g
. , '114'40* I i v. n I r., r r C T EACH quTAGE R3 HI (7 0) UC g PROHtLM : T A T E.*1E !J T : G E NL R IC INSPECTION F f Q U f f> E rar N T .
j
- 9 9
l 9
9 9
9
, 1 1
0 0
0 9
O O
- J J O- o! l
- ! I
, F ! V E Y E A k F L A N P03 TON EDISON COMPANY g f s t a; nAir 12 A P 4 F 3 t il 7wa s * . . 0 C P T t S EL E C T A N A L Y S I S . . . P RO JE CT START 3JAN93 PuoarcT: 5yLALA NJCLIAR GRGAN!2Ai!ON 9
O9I GI NA L COMPL. 3JAN83 "T- Il FIFE PRCT CTION EJECT NnDEO DATA CATE 3JAN83 PAGE 15 g i LF " N Y DE 5 C R I P T I O N REG NUCPG UR GE NC Y SROWTH PLA NT RESCURCE NL CLASS PRIORITY CONDI TICA S g
.._'T9 _......___.__...................... ...._............___.....____...--..__._.._. ___...__..........___............__........_.. _
- 19 5 710 t PSPO c*RnUTE A" Pro *. 70 C A ILE TO PEET H3 L' 4 (? ) TECH (NED) g S PA?ATICN CRITLPIA (Apprnggy aga)
POutr M STATEMfNT: ICCFR *0, APP H IS A LEGAL
+ QUI 7EFENT. g
'031010+ o r# C '" 0 U T E APPR0x. FC CalLE TO MCET R3 04 (4 ) RC
', cetITrptA gapprgcIn apa) g PP o r t t t' S T A 15. N E N T : trCFR 50, APP P IS A LEGAL M 10 I et E *C 1 T .
ALIERNAlf 5HUTDCWNRELOCATE ONE PANEL PCO
,, 2 P ANLL S (APPLNCIX "R") g i P9 09tE " ifATE"5NT: 10C F R 50, APP R 1% A LEGAL Pt GUIPE Mt N T.
' 9 0 i N G 's P ',P D 5 m TE s a t I AL IPPACT ON C40Lr REPOUTE R3 04 (R ) RC SHU T C1WN-SI EL OC A T E ONE PANEL MnD 2 FANtLS
, (tPP: N3It "R*)
S T A T E P E *4 T : IrrFH 90, APP F IS A trGAL g
P 7 0 4 L f P' P E Q U IR E "E N T.
- 101331' Pc"P ANALY?E b c E A r;t. R TO F LSE ISSUE ( APPt NDIX R) R3 He (9 ) TECH ( f.E D )
tu fi n L E M e, r A T E p:E N T : I CC F R 50, APP P IS A LFGAL P' G L IP E PE r. i .
Q
?91 1409 T's P O c~EM '.WE W T 0 *. FIFE 70NL !SSurs, Fr,0 CESS R3 H6 (1) TECH (NED)
'J ; D I Al E S HI/LO P " F '.; ' INTrRFACE g
( at P 7 t!n I X "4") arm SCHEOLLE
'JeftrM St ali"f N T : I CC F :4 *i 0 , APP W IS A LEGAL
% 1UI4Lpryy, g
031160' 7 P P"5 VAL /9EiL9MIil I 'T V T or NRC HF11 A P:t P3 51 (9 ) TECH (Nrop t r. f E N A T E W/ y r 3, ,tAy O
r r c alt re 51 A T E t't g i : N ot IPU0iED C0"PLEilCN '
e, c 4 : Stit t i c!s APUanIt L F%e.
3co.1 tot 9/: m salvt ac, n r . r. P r Cve st 93 e4 (t) TECe (NED) O, e r O i l t '4 S T A f t r *17 : Vac19UT F 14 E PROTECTION I t strc. !
gl O
I
r l
I i k' h H
I o! r l
7 t r, F I V E Y E A R P LA N B03 TON EDISON COMPANY g -
'UN ' Air 1.? A P 4 F 3 151 TH1S * *
- O OR T L T E L F C T A A A L Y S I O * *
- PROJECT STAdi 3JANR3 it.
040J~_CT: s y r. A R A g i A. U C L t A A ORGA'JIZATION O RI GI P.4 L COMPL. 3JAN95 Yi CONTAl440:T ATMOS CONT SV3 (CACS) EJECT N0CEO DATA DATE 5JANR3 PAGE g r
'r Dr :
...._._____....._______....____.... ___....__..____.___...........,__...__.,_......__... __..._,__ 16 F L r '4 "J T D E S C H I ri !O N REG NLORG URCE NC Y GROWTH PLA N T RESOURCE
- < NU" C CLASS PRIORITY C ONDI T I ON 3 g i
f 3 C33101 a/A CONT. E V AL 50 49 MFMC TO LIC. STATING THAT R3 fa '6 (R ) TECH (NED) g IN C NJ J. 'JITH THE HMCRG FEPORT WL MAY NOT VE0 A RECOM91NER HECAUSF A - EVAL AIR I r.
], LEAKAGf (PELATED TO h2 I P. C O N T A I P.ME N T ) g H - 00 ALONG WITH PW CP G REPORT P S O P L E ** ST A TEMENT: TFE NPC HAG 105UE0 A FE VI SI ON
, To 1PCFR ' 0 . 4 '6 ON C0k. TROL OF COMHUSTIPLE GAS IN g
fMt CON T AI NME tJT.
l 9
1
- e 3
3 4
4
')
0 1
i t
f i
O !
~
c, v % -
O o e,
[
6 F I V E Y E A R P LA N P-M T O N E3 IS ON COMPANY g "
DUN GAfr 17Apaw3 1517893 . .
- S O R T 4 S E LE C T A N A L Y C I S * *
- PROJECT START 3JANR3 PDOJECT: 'YFARA NUClegg nRGANIZATION O 01IGIP.AL COMPL. ?JAN43
, 000': l' PRPr,qAMS EJECT NODES CATA DA TE 3JANA3 PAGE 17 (p E Lr
- N T 0E ,C R I R T I ON REG NLORG UP GL P.C Y G90WTH PLANT RESOURCE N L'? v a CLASS PRIORITY C O N DI T I CN S g
--.....--..........e--.......s........s.....-..........-........----e..............--...+.........e........-+...-.--...-......-.+..
-i T1713 7 4 I T *. S 54 NP/7LE TO VESCEL GHELL WELDS AND THE R3 P1 (10) UC g INNER RA3fl
'i9371404 IT40 IN NO22LE TO SAFE-FND WELDS R3 P1 (10) UC g i90705C4 !T4S % RrACTOP PRE CSuor VE S SEL STUDS, NUTS, R3 P1 (4 0) UC WASHF90,M AND LISAMEP.TS g
"90776C4 IT4G h RfCIRCULATION PUNP STUDS R3 H1 (R O) UC 09070704 I TE S VAPICUS PqESSURE PE T AINING BOLTS (<?") R3 81 (4 0) UC
, '9070404 ITSS A6 PR0x!MA TELY 7 HUN 0bE D FEE T OF SKIRT WELD R3 H1 (* 0) UC g 49079304 IT45 AFPRCXIMATELY 2 HUN 0 RED CIRCUFF ERt NTI AL R3 H1 (90) UC g PIPF WELCC IN CLAGS 1 SYSTEMS g
'i'971004 ITts ?" INTESPALLY WOLD SLPPORTS IN PII E , VALVLS R3 HI (10) UC
, AND P U tiP S
}
'971109 IT4C VI SU ALL Y EXAMINE APPROXIMATELY 2 HUNDRED R3 P1 (10) UC
- L'PP C P T S IN ftE CLASS 1, 2, AND 3 SYSTEMS 9
9'3671704 ITtS VISUALLY 5XAMINE THE INTERNAL SURFACE CF R3 UI (10 ) UC TarNTY-FIVE V A L Vf. C A TE GOPIES g 9
. O O: !
OI i O'
q (
,. N ._.Y ,
i t
c 9 i
- PROJiCT OTART 3JANR3 PG0JrCT: ;yrAaA O
NUCLE AR ORGANIZATION 01I GI NA L CCMPL. 3JANR3 CPOT: 101 PAJ08 LIC N3ING ICSULS EJECT NODES DATA 0%TC 5JAN93 PAGE 1A g FLc"rNT 3E 0 C R I P T I O N PEG NLORG UR GE P.C Y SROW T64 PLANT RESOURCE PM "TR CLASS PRIORITY C ON D! TI ON S g
__......_............_.._....s.._.......__......e__._....+..._...-_s_...--.+-......_.s...____..+_--...-..._-_-.....+......--+-.
1031?'101 D%C 05VELOP MASTEu LIST CF ECUIP. TO sUPPCRY R3 P1 (1 ) TECH (NED) g 77-015 Fan 4LE M e, T A T E PE N T : LIST OF r NVI RONFE NT ALL Y g Ar r r C T F.C 5 CUIPMENT O CE S NOT Ex!ST. g 1000?MC? P"P r C! F I Nr ENVIRON *LNT PfF 79-CIO R3 P1 (R ) TECH (NED) 1000?1301 9:PC C5VELOP 0'J A L . DATA PER 71-013 R3 HI (R ) TECH (NED)
N9HLF M STATLFENT: CIANDADOS TO CETERMINE FNVIRCNMENTAL QUAL. E5VIAT10NS DO NOT Ex!ST. g 1071?1439 5' 7 C F '; T A rit ! SH AND MAINTAIN E QUIP ME N T GUALIFI- R3 81 ('t ) TECH (NED)
CATICN FILE PER 73 0lH g PDOHL5 M STATE"ENT: QLALIF! CATION FILLS REF LE CT-ING 71. 01 - Fs HAVE NOT REEN ESTABLlaHEC.
13 002M0 4 P 3P D CM AWE 11-013 QUAL CATA TO SERVICE DATA R3 01 (R ) TECH (N'3)
FP0HLFM STATEMENT: E x! S T ING 55RVICE DATA MAY NOT g S' f P F R T NL b ENV!NON"lNTAL CRITERI A AND PUST PF g DOCUPENTED.
1000'1;04 I l f. ~ PEPAIR/ REPLACE Co RE LOC ATE T9-10B UNot AL- R3 PI (7 ) RC g 15 ItC EQUIP' TENT A ". 4EGUIRED F UO9LF " S T A T E ** E N T : W HE N OUAL/ SERVICE CATA CEVIA-TION EXISTS, IT PUST 4E C 0 54 R E C T E D .
, g 100?'9704 I T #. : I ?# F L F M E N T CGUIP OUAL. "AINT PROGDAM R3 P1 (1) O & P rqn9LrH STATE'4ENT: O A F. EOUIPMENT IS ENVIRON- g M'N T ALL Y J P b h A O t. 0. IT; 1UAL. L IF L C A P.N C T HE J sP0001F D.
1900?C407 7/n A ! POND 10 79-014 TO NPC . R3 F1 (1 ) TECH (NED)
PiM L f " STATEFENT: 79-01'i CLOLE-0UT DOCUFfNTA-TION 9fGUIPLO AFTrp m CJEC T COMPL5TICN. '
()
110111?1' r 7 Nt u t - 0757 PG;T !"6 Lt% N T t II ON RE VIF L R .i P4 (1) TECH (NEJ)
I T ! " ".
P , '14 L E u STATt" INT: C E
- n t f f I q '. OF 903T IMELfMEN-Q 8 TaTION PiVIEW I Tt ": A CUI7tD UNCtk ICCF F EC.44 10C01)401 'CP" ': V!rW AND ECTA'L15H 7 BIT T ; T a r F I N G/ t.C ? M A L 05 rt (4 ) O & P q r j7 , p;4 T T' I - 0 7 4 '
P 9 q P t r it TTATE:1 TNT: N L'4 E , 09'? E S T A - L I H E '
c :tv I A > c nv u si e we Tw P.ai Er tr Cir e IN Q
,<qC lua ;' .
m D
(V (V ('
U f
O l
Ol t
CW: 100 FAJOR L I C r f.0 I NG ISSUE; EJf Ci NGDES DATA CATE 3JANp3 PAGE 11
_........,_._......+.........+....__. _s....-....e...--.-..+-.....---+-.-------+--.-.----s.. .-~~--+---------*-.-~~~~~-+-----~~~~*--
g ;
r LF u N T D E 5 C R I P T I O N REG NUORG UR GL NC Y G20WTH PLA NT RESCURCE P. L " B r o CLASS PRIORITY C O N11 T I CN C g 100340701 4/A RfOUCTION OF 100!NE CONCENTRATION LIMITS R3 B4 (9 )
(oEG"O TECH SPEC C H A friE )
TECH (DT) g F'd O F LE M STATFFENT: PFCO/rE P00!T!nN ON NtfREG 0"03 (SEE NE DO-22?C 9 ) 13 THAT PNPG IS PRECENTLY g AJCCUATE. NRC E V AL U A TI ON M A Y RE QUIRE F URTHER MMS / AC TIONS.
10 0 c a '14 r: t R/3 RTVIEW ranCECURFC (M AINTrN ANCE A fw0 EFER- R3 P1 (9 ) IECH (NEDI GE NCY) FOR *0V SYSTFP RUPTURE. .
P rHLeM OTATEVENT: NLPEG 0803 ESTA6LISHE: g CNITERIA FOR 'DV ' Y S TE M RUPTURE NOT PE FLECTE D IN PRCCEOLREO.
123S41~01 R/A FNVIPONMENT ')UAL OF E (2 U I P REQUIREMENTS P3 f4 4 (R ) TECH (NED)
T1 'i ! T I G A T E THE EFFLCTS CC SCV. RUPTURE
, ( r N C P!O US FINANCIAL I'4 P A C T ) g PanPLEM STATEMENT: N6C FEELS SCRAM DISCFARGE VOLU"E INTEGRITY IS IN OLESTION. DECO /GE E VALUA-TION CONCLUDING 3CV Irt I E G91 T Y IS ACEQUATE !$ g L'.D E F' NRC HEVICW.
, 17 0 017 M C/n CLCSLCUT A TWO MODS C C'PLE T ED TO DATE R3 H4 (R ) TECH (NED) g T'G 0 h lE M 3TATEFENT ATWS "0D3 PERFORMED TO DATE
( 1. E . , ARI, RPT) REOLIRE CLOSE001.
I C 7'? i 3 9 31 R/A CE if kft! NT NEEDS FOR ARI TECH TPEC P3 P4 (1 ) TECH (NED)
P c n F Lf r1 T A T E "* E N T : AN EVALUATION I S RE QUIRED TO
. 'MTrRFINE THE NF f 3 F t'c. A TECHNICAL OPECIFICATION ,g T9 SUTPORT AUTOMATIC 400 INSPECTION MOD.
0 0
0 0
i 0
0
(
. rT
{}
i rs gg .i i
- rs F I V f Y E A R P LA N S03 TON EDISCN COMI AN Y gg g 7UN CITE I?AF'*? 1917"R S * *
- 5 0 R T F, S E L F C T A N A L Y 9 I 5 * *
- P 90 JL C T START 3JAN93 P"CJrCT: CYTARA NUCttAP GRGAN!ZATION O RI GI hA L COMFL. 3JAN83
- , C n 0" - 101 ! ?. I EJECT NODES DATA DA T- 3JANR3 PAGE ?3 gg
.......... ....____._.... .......___.............,_................__+................__........__ ................ ___.............
i FL Nf DE S C R I P T I Oh REG NLCRG UR C E P.C Y GROWTH PLtNT RESOURCE
- r NL 4~9 CL ASS PR IORI TY CONDITICNS
_ _ . " . . . . . . . . . . . . _ _ . . . . . . . _ _ . . . . . . _ . . . . _ _ . . _ _ _ _ . . . . . . . . . . _ . . . . . . . _ _ _ . . _ _ _ . . . . . . , _ _ . . . _ . . . . . . . . . _ _ _ . . . . . . . . .gg. . .
,g INDU^ f R Y INCIDENCE OF FELD NCZ2LE gg l CSACKING. wCOT CAUSE D E T E R M ! r.F D TO PF <
{ iurpest ga Af;SIEN T S AT THE N0Z7LES. CRD j, PEIUPN L ! ?;E MOZllis FA VE SIMILAR PROBLEM.
gg l
Sh
!< 9
- f l>
I l
is 4 19 1
l 3
I 0
1 0
l'
()
i' I
O >
m N
( ,/-- ,-
n i
v) V' '
(
v
)
q V
v' Q
r, F I V E Y E A R F L A N P. 03 T O N CDISON COMPANY g CUN 7 ATE 12ArppT I m 17Ha 0 . . . 9 0 R T & 5 f L E C T A N A L Y S I S * * . P RO JE C T START NfAN43 e
r4CJECT: Syr ap A suctr aq ORGANIZATIOf.
Q ODib!NAL COMPL. 3JAN'13
, cnct : Ils 3ECY-?C-111 EJECT NODES DATA DATE 3JANP3 PAGE 21 g)
C L E *F N T D EC C R I F T I O B. REG NUORG UH GE NC Y GROWTH PLANT HESOURCf NLW a CLASS PRIORITY C O N 01 T ! CN S g
, 10'0101')! R/A fVAL AND SPECIFY SPLS R3 t! 4 ( 't ) TECH (STA) g PF O :lt r M S T A T F ME N T : T R AI N IP,G , FROCEDURES, INDICATIONS (INTELLEGt4CL)MAf NOT PE PROVIDED TO OPERATICNS TO 4ECCGN!7E & MITIGATE THF g CONSEQUENCfG OF A DEGR ADED COPE SITUATION 103310'01 R/A M RFC9ft C C N T R 01. E00M DE3IGN & RECOMMEND R3 FM (4) TECH (NED) g Pa 0"LE M STATEMENT: TPAINING, P9OCEDURES, INDICA T10N" (INT ELL IGE NCE) MAY NOT BE FPOVIDED 10 cvL d AT IONS TO RfCPGNIZE AND FITIGATF THE CCN ZCUE*.CLS OF A Dr GR AGEO C0wt 5!TUAT10N. $
113913591 9/A EVAL IMPACT 1 77 & R COM R3 B4 TECH (NED)
P40"LEM ST ATEMENT :TR AINI%, PROCfCURES,
( ~t ) g INDICATIONS (INTELLEGENCE)4Af NOT E0 FROVICFD 4 TO CPE9ATIONS TO LECOGNIlC & NITIGATE THE 9 CONCE.CUENCES OF A CEC 4ADEJ CORE SITUATION g IC?O104n3 PSPC Cf CICE FORMAT % CONTENT 8 CEVELOP FOP"O R3 P4 (7 ) TECH (STA) 9 P O P LE *4 STATLMENT:TuAINING, PROCEDURES, IND IC A T IONS (IN TELL EGENCE )" AY NOT HE FROVICED TC CFERATIONS TO "LCCSN!?E 4 '4 I T I b A T E THE g CONSFCUfNCES UF A Drca ACEO COPE SITUATION 133711;P1 P/A P E V If bs 1 UPDATE LE GLIGED TRAINING N C h lE STATEMENT:TRA!NIr.G, FROCEDURES, R3 04 (R ) TECH (NED) g INCICATICNS(INTELLEGENCElvaY NOT rE FROVICfD in CrEnaTICN3 TO FECC1NIlr & MITIGATE T HF ()
CCNSEGUENCES GF A DE G4 AJEC CCFL SITUATION 1010?0101 P/A EVAL t UPGRACE TOC R3 P4 (P ) TECH (NED) g DC OR Lr st S T A T E ME N T :E MS GF.NC Y P!SPONTE FAC'-
C1 NCT PUT NRC C P I T E '< I A 1C3070231 R/A V A L s UPGR40E E G O
R3 P4 (P ) TECH ( B.E D )
PG 0HLE ft CIATFvENT f_vCJGENCY R '. 0P CN S E FAC i M NCT M t. i T NFC CMITERIA Q
11 M P 19 01 a/A IVAL 4 UPSPADt n ic Rt *% (1 ) TF CH (PT)
P 4 :) a t c p; g y g y ;. n y t : r'I r a n c hC Y N SFON3f FAC CP NCT M:. T FC CiITfRIA Q '
h O
73 i g ,
r ; i n
i v
/
,v-- s v/
e
, F i V E Y E A R P L A N H03 TON E7IOCN COMFANY g ryy nAir 17 A n a 3 Iggypas . . . 3 eq t g S E LE C T A N A L Y S I E * *
.g hvn'o CLASS PRIORIIY CONOI TI CN S g
, 109019203 P~PC CrSIGN CCLUMN TIr 0 0 La. INSTALLATION R3 R4 (R ) TECH (NED) g (P 08LE P GIATE"ENT: NEW TORUS LOACS DISCOVERED
, "< ! inRUS DESI3N3 WERE FOUND TO PC LESS THAN g THE CfSIGN SAFETY M A r< G I N AS A r( E S U L T .
f 10'M 10 ? O '. IT%S COLU"N TIE LOWN INST ALL A TION R3 h4 (t) RC g PE OSLF M STATEPENT: NEW TORUS LOADS DISCOVERED HY GL ASSOC. WITH srb LIFTING TRANSIENTS. ALL 7 PK I TOPU3 CESIGNO LERE FOUND TO BE LESS THAN g THE CE S I iN SAFETY MARb!N AS A RESULT.
1991930' P3PO DESIGN REINF0fCEO RING GIOCER TO SHELL R3 P4 (70) TECH (NED) g WfLOS (T - SUE NCH+ R PAYS) IN THE TORUS FunnLF P S T A TE "E N T :GE HAS ICENTIFIED NE W SIPUC
, TURAL LCA9S TO THE TCRua A SSOCI ATED WITH SPV g TRANSIENT 3.ALL MAFK I 10400 CESIGNS RLOUIRE M1LDIr IC AT ION 1 M010 3 0 4 !TES INSTALL PE INFORCLD R ING GIRDER TO R3 H4 (0 0) RC SHELL WELOS (T - GULNCHER HAYS) IN THE TORUS
, Pr0HLLP ETATEMENT:GE HAS IDENTIFIED NEW STRUC 3 TUDAL LOAUS TO T b t. TCDUS ASSOCIATEC WITH SRV TAANSIENii.ALL T1 A R K I T00US DESIGNS RECUIRE "nlD!cICATION 3 10%10603 P ~J C VSIGN ACCli!GNAL S U rP O R T S ON SRV LINES R3 P1 (P O) TECH (NED)
P ? E L L M STATE"ENT: T C9US LEs!GN CEFF. I D F f; T ! -
rIED IN tt A R v I FROG 9A'i (SHORT T E R t' ) .
()
199011c34 I T v. S 14; TALL AOCITIONil OLPPOP15 CN Ci V LINE0 R3 F1 (P O) RC g)
H C R L E tt S T A T L ** E N T : T CDU I DE S IGN CLFF. IDENTI-FICD IN '4a N. I N e r, R A'1 (SHCPT TEW).
119:1713 PmC M C r ', I G N 10aus Q .
3< LL PE N: T G A TION' P3 4 (?) TECH ( f4 E D )
p; I N r N C L t N I .-
r- ') H l i f f $1 ATE"rni: gg TcpUS L C AC1 D I S C O V E R f t' 41 G r. A*^0C. LITH S3V LIFTING T R A4 f S I t' N T S . ALL Q
W I TOPU- r r S t .;q ', yr1E FOLNC i n f.r LFSS THAN I T H '._ M SIM SM LTY "a >IN 40 A o f it'L T . Q ,
119011T'4 IftS I N '. T A L L TOCUS 3H .t L i NETRATION, A3 "4 (' ) RC l-s! V wCF 'tE N T C P'0"LLM JTATT"ENT: Jr W T;0US LOAC OIOCGvrPIP Qf l l
~
r
.es
() i r
GP l Cn CF : 104 TC"UT MOS EJECT NODES DATA Ctir 3J ANH 3 PACE 23 gg
..____.__........_...________.........+.......-.---...___...._...-+-.___....+_......_.......-...-._...--........__+_-___.--....
~LE"ENT C E S C 9 I P T I O N REG NLGPS UD GE NC Y GNOWTH r' L A N T RESOURCE N U'1 d E 2 CL ASS PR IC A I T Y C ONDI T I CN S gg
.....____.________.......__._.___. .. ......._.......... __+__....................-____.......__....... __................____ ..+--
HY Gr AGSCC. WITH SRV LIFT!NG TRANSIENTS. ALL wK I TGRUS CE,1GNE WERE FSUND TO DE LE SS THAN gg T"E CE3!GN GAFETy PAPGIN AS A RESULT.
199]I3413 D 7'n u r D E S I G N tkTEfNAL PIFING TO TORUS R3 P4 (a q) TECH (NED) gg PFC3LEM STATE"ENT Gf HAS ICE NT IFIED NEW STRUC-TURAL LOADS To THE TCDUS A SSOCI A TE D WITH SPV 19ANi!ENTr.ALL .w A A K I TOFils DESIGNS dE GUIRE gg P1L D IF IC AT ION
) I ? M10"0 9 I T '. " 1NSTALL CXTERNAL PIPING TO TORUS R3 P4 PO) RC gg D70HLEM STATEMENT:GE HAS IDENTIFIED NEW STRUC-
! TURAL LOA 05 TO THE TCRUG ASS 1CI A TE D WI TH SRV
, inANSIENT3.ALL MAPK I TCPUS DESIGNS F:E Q U I P E gg j PrL D IF I C A T 104 i
19 7 0 'e n 10 4 IT ts INST ALL T3 PUS TEPP. FONITORING R3 P1 (P ) RC gg LYSTEM AND CHSNGE TO TECH SPEC PF04LEM STATEVENI: Ew! STING TEMP. MONITORING
- 19'l,010' P ~# P C F ", I ". N W F. T L E L L VACULM MREANERT MATERIAL R3 H1 P O) TECH (NtD)
LWipABF }
P40HLLM STATEMENT: TCR US DESIGN CFFF. 10FNTI-rIED IN '1AOK I PROGR AM (SHORT TERM).
-)
179050104 I T ', ; v.TW5LL VACUUM M A f A K E R S P A T F_ R A I A L UPGRADE R3 P1 (9 0) RC P"9P LE M ffATfPLNT: TCRUS DESIGN C(FF. ICFNTI- ,)
r fitt IN MARK I PROG 9AM (5HORT TEEM).
d l
0 c; ! .
4
,I 1
CJ i
()
_ ___ -_ -. ___l
f.
s '
c) '
e e
.,s F ! V E Y E A R P L A N H3STON E0! SON COMPANY gg PbN SAir 12Ar4E! 1517 HRS * .
- C 0 R T & S [ L E C T A N A L Y S I S * *
- PROJECT START 3JAN85
('
GD PJCJECT 5YCARA NUCliAR OHGANIZATION 3RI GI NA L COMPL. ?JANR3
- ,- Cc 0' : 11' OLOCKWALLS EJECT NODES DATA 1 ATE ?JANH3 PAGE 24 gg ELE Mr N T C E 5C w I P T I O N PEG NUORG UR CE NC Y G40WTu PL4NT RESOURCE NU UR CLASS PRIORITY C O N DI T I CN S gg
, 11211013? P SP L 6 VAL 13a 4LOCMWALLS FOR ANCH09 AGE R3 84 (R ) TECH (NED) gp f d ') H L t M ST AILMENT : I ?9 HL]CMWALLS UNDERGOING ANCHCRAGE LVALUATION. OEVCRAL ANCHORAGE MOCS
, P109LEM STATLMENT: ! ?S MLOCKWALLS UNDERGOING gg ANCHCoAGE EVALUATION. SEVfRAL ANCH0PAGE POCS APE EXPECTEC.
11?319794 ITtS I'* P L E Mt N T (15) HLOCKLALL ANCHOR AGE S MOD Hi H4 (R ) RC pqnstt M 3TATEMENT: 120 HLOCKWALLS UNUERGOING
, ANCHCRAGE E V AL U A T ION. SE VF R AL ANCHORAGE PCDS gg ARE EWPECTED.
, 11?01030' DSDD COMPLETE OR PCH9VE PA9TIAL BLOCKWALL PODS R3 Pg (9 ) TE CH (NED) gg PR0bLtM STATEMENT: F IVE NON-0UTAGE (COPE BLOEK-kALL ANCHORAGE MOCIF IC A T TONS WERE LLFT PARTIALLY g COMPLETED AT THE END OF RFOW5. gg 112010504 I T 3. 0 C0 fiP LE T E O F REMOVF PARTIAL HLOCKWALL N003 R3 P4 (d ) PC i
, PdOPLEM STATEMENT: F IVE AON-OUTAGF SCCPE PLOCK- jg
.ALL A NC H,lP A GE MODIFICATIONS WERE LEFT P AR TI AL LY CC"PLETED AT THE t N3 0F PF0#5.
112911404 ITtE IN%IALL J! NT AECIPC FG WALL R3 P1 (P O) RC P90RLEM STATE"ENT: Jes!GA PdOPLEP REQUIPING POCS
- (!EB "9-11). g) 112910411 r-"C T VELOP SP CONTR1L N al A r ASS R3 E4 (t) TECH (NED)
" OulE P LT A IEVENT:IE R 8 0-11,UNC OVt RE C CE"I GfJ d L A"TrUCTION Ot F IC IE f4 I s. >
Q
()
O ,
i
() '
O
i I
r vs O :
i e G l
a F I V E Y E A R P L A N DOSTON ED IS ON COFDANY g "LN 7%TE 12AP7h3 1517 HRS * *
- S 0 R i & , E L r C T A N A L Y 5 I S * *
- P90JrCT START 3JAN93 oRCJECT: SYEAkA t.UC LE A R ORCAN!2ATION 9
ORI GINA L COMPL. ?JAN93 C Oc : 114 PrACf00 WATER LtVEL EJECT NOCES DATA CATE 3JAN83 PAGE 25 g r L E *1:~ *J T DE , C R I P i I O N REG NUCPG UR GL NC Y rdOWTH - PLA N T RESOUNCE N t/* i ' 9 CL ASS PP IORITY C O NDI TI CN S g 1
l 114710'01 D/4 INVFCT FLRIHLR ROOT CAUIE PPCH WIIH R3 L4 4 (PP) TECH (PT) g C C 't" C ?; R f. F . Lt Gd HX kATE9 LEVEL PC,0 d L E t1 STATEMENT: C C" p 0 N R E F E R E P.C E LEG APPEARS T CAUSE INCICATION PR00Lr=45 r.URING CHANGES IN g i 'O L f it LEVfL'>. CPfWELL E NV I RON"E N T CHANGES AL SO A6FECT h"V LEVEL IND.
9 9
e d
D 1
l 1
')
'a l
9 0 ;
O 9
O' ;
i 1
()
1 rs
$ l f F I V F V E A H P L A N RO1 TON EDIS CN C0FPANY gg j i
i PUN 01TF 12 A F o 9 3 1311HR: * *
- C 0 R T & O E LE C T A N A L Y S I C * *
- D RO JE C T START 3JAN93 P'CJ5CT: " Y r t.9 A O
NUCLfAR CPGAN!/AIION O GI GI NA L COMPL. 3JAN83 I
. . . . . . - - _ .12. . . . nesE
' . . . PLATLL
. . . . . . 3. .PIPt
. . .Sle'P
. . . .O. R
. .T. 3. . . . . . . . - EJECT C70~:
. - - . . . . . - . . . . . . . . . . . . . . . . . - - . . . . . . . . - -DATA
_ , . - - . .NOCES . . . . DA
. . .TE
. .3J
. .AN4
. . , 3. .PACE
. . . . . . . .26
. . . . - -gg- . .
'L M' N T DL 0C a I F T I O N PEG NUORG UR GE NC Y G70WTH PLA NT RF00U9CE y N L ;* r ? CL ASS PHIOPITY
...--........................s.-----------.....-...---------.....-s.------...----.....s.......--........-,.........+.....-...s..
00NCI TI CN S g
, 120111105 e iP C I UUF REpAIN!NG HASL FL A TE PCCR'S AND R3 P4 M) TECH (NED) g P'CR';.
PRODLf 4 CTATEMEhl:GE N: R IC DESIGN OEFICILP.CIES
, WITH CESIGN AnLupFTICNE.N7C I S ", U E 0 IL HULL gg i I -02/77-14 g I?2010104 P "S J In0Ut REM 1INING oASE PLAir PD(R'S ANC R3 L* 9 U) HC gg rnCP'S.
r"O $LE M OTATE"ENT: GENERIC CE C IGN D E F IC I E NCIE ",
, NTTH D E s t r, N A ; 0 U P s' T I CT. E . N R C ISSUFO IE PULL gg 77-CP/7?-14 12271120' C/1 CLOSr-NUT IE tiU LL E T I N 77-02 R3 H1 D) TECH (NED) g E '0 ilt " 3T ATEMEN T: F IN AL CLOCE-0UT OF 79-02 P.0 T CC"DL5 TEC.
!? 1?0111 P ^. P D I'GUE PEMAINING PIPE JUPPORT PDCR"3 R3 P4 (7 ) TECH (NED)
F;0SLFM CTATLMENT:GEfERIC CE *. I G N D E F I C I E N C I E ".
, w!TH CE7IGN A ;50Mr TI CNO .N7 C I S S U F L- IE PLLL j) 73-07/79-14
[g l ' 2 7 7 010 's ITES 1"rL' MINT P F P A IN IP.G FIPE SUPPORT R3 n4 (P ) RC Jg l r:Cdtt M S T A f t M EN T : GS. P.E G I C DESIGN OLF ICIENCIE S l WITH CECIGN A 5 00 P P T I CN S . P.1 C ISSUE 3 IE PULL
, F - 0 2/ 7 9-14 gg j 1'212170' C/1 CLOSE-NUT IE t-ULL F T I N 79 14 R3 P1 F) TECH (NED) n904Li P CIATEMENT: F IN AL C LO SF -0U T OF 77-14 NOT rg l rerLrifP.
~
l CI i
() i 1 4) t i
L) l
) i I
iJ j e
o Of 1
(
L
, F I V L Y E A R F' L A N POSTON E0!50N COMPANY g PUN DAfr I?APRP3 151FH95 * *
ORI GI NA L COMPL. 3JAN93 C O D- : 131 PA*S H00) FJECT NODES DATA CA TE 3JANa3 PASE ?? g
+------------------+---------+---------+---------+---------+---------s-~~------+---------o---------+---------s--
rtcuryy g g- ; cp ] p T I O N REG NLORG UR GE NC Y GROWTH PLtNT prSOURCE N U # R CLASS PRICRITY CONCITICNS g
......----,-----.---+---------+---------+---------+---------+---------+---------+---------o---------+---------+---------+--
15301010, rnac rfNALIlE PDCR 30-30 F202 R3 01 (D D) TECH (NED) g PIPIP.G PHPOLEM ilATE9ENT: PCST ACCIDENT SAMPLING IS 9t CUIRE O UNCEP A LONG TERM LESSON 9 LEARNEC PRO-6PAM F R 0 58 TMI-2 (NUREG 0737). e 133011104 I T *. ! I"PLEMENT PDCF A0-30 H202 R3 R1 (3 0) AC g c r P I Nr.
P404LEM STATEMENT: POST ACCICENT GAMPLING IS d' ".U I D E D U f:Dr P A LONG TF PM LESSCNS LfARNfD PRO- g 04AM FROM IMI-2 (NUPEG 0737).
I ' t0102 0 t PcPO FINALI2E PUCR FO 11 PASS R3 P1 (30) TECH (NED) g p i P i r.s PPPHIEM S T A T E '8 E rJ T : PC T ACCIDENT CAMPLING IO f PLQUIDED UNDER A LONG T E R ** LESSCNS LEARNFO PAO- g GFAP FROM TPI-2 (NUPEG 0757).
, 1T301G004 IT45 I t'o L E ME N T PCCR 80-21 PASS R3 f;l (p n) RC g VIVI %
PR07LEM STATEMENT: Pr5T ACCIDENT 'AMFLING It PFQUIRED UNCE9 A LONC TERM LE3 SONS LEAFNEO PRO-WAM FROM IMI-2 (NU9tG 0737). 1) 1*??!190' '
PD FItALIZF PDCH 80-E2 (PASS R3 F1 (1 ) TECH (NED) g H .:07 rs t A rA N I 6AS PROPLFM S T A T r fK i4 T : PC3T ACCICENT SAMPLING IS c
- r.U I R E O U N C E R A LONG TEF" LESSONS LEARNED FPO-F A f' F 4 0 ** TM1-2 (NUREG 0737). )
l'Illlica ITs3 If PLEMFf4T POCP 80-S? (PAC 7 R3 P1 (?) RC C02 P E A'it N T .i A S Q
i 30HLE M 5 T A T E P't N T : P0;T AC C I CE N T S A *1PL ING IS N CUIPEC UNDE 1 A 10NC TEM LESSCNS LFAPNFC PDO- Q ,
W A" FROM TMI-2 ( f.U l i G 0757). i f
I'191040' P90 FINAL!!E DLCR AC 5 C-11 MECH R3 i: 1 u) TECH (NED) Q
("A;' HPO?)
i Pr C alt M STATEPENT: PC1T ACCIL!NT "AMPLINt, I e. '
r r ; U I R E C 'M H A LOhr Tr p tt3;CN t f Ar Nr D PLC-W AM F R Oft TUT-2 ( f.U R T . 0Ti73.
g I'?310404 !T S - !"n L' f*E N T POCW PC-Si .-11 MtCM P3 41 (1) RC (rAq' H?n-) Q
Fe o
n e r i
!,- " 0 Cr - 151 D A ^, 0 H202 EJECT NODES DATA 01TE 3JAN43 P A r# '9 g i Ctr" NT DE C 4 ! r i ! 0 N REG NUORG UR GE NC Y GROWTH PLA NT RLSCURCE
, N L'* t 3 CLASS PRinRITY C O N71 T I ON e. g
---........--------.-............------,--....--+------..-+----.--..+-.-------+---------+-------..+....----.s...--.-.+.-------+-
Ps0Ftrf STATEMtNT: P C'. T ACCICrNT '; A NFL I NG IS 5 H CuffC0 UNCc.P 4 LnNr T r c 't LESECNS LtARNr0 PRO- g DAM FACM T"I-2 (NU9EG 0737).
j !!'113705 P F"; FINALIZE PDCR 90-57 f fL S t R3 P1 (R ) TECH (NED) g Cn0 LING 9YSTEM Pr0PLE M CT ATEwE NT: PCsf ACCIDENT .:AMELINr IS i M OUIDED UNCER A LONG TERM LESSCNS LEARNLD PRO- g G7AM FPCM TMI.2 (NUREG 0737).
, 113'11 M 0 s I T i s I'1PLE vE N T FCCd 8C-57 PASS R3 P1 (R ) RC g CPOLING SYSTEM P40FLEM STATEMFNT* PCCT ACCILENT SAMPLING IS
, or0UIFED UNDER A LONG TERM LLSSONS LFARNfD PRO- g 6'3 A F FRCM T f11 - 2 (NUREG 0737).
I'5013;7? PerC FINAlflE PDCR 90-40 CONTROLS R3 El (1 ) TECH (NED) g trASe H202)
P90RLf M : TATE"ENT: PC3T ACCIDENT SAMPLING IE
i SkAM FROM T41-2 (NUREG 0737).
I'301 % 04 ITt IMPLrpEr T PDCR 80 40 C ON TROLS R3 61 (R ) HC g (PAS 3 w20 * )
P7 0 3tE M STATEPENT: PCST ACCIDrNT ",AMPLING 10
, Rt SUIRE D UNDER A LONG TLbM LESSON". LEAPNED PPO- 9 i
f'W A M FROM TMI-2 (NUREG 9737).
15.'319713 P ". P 0 FINALI2E PCCR 80-42 RAT R3 M1 (10 ) TECH (NED) 9 T3 ACE A PJ1 I'J SL'L A T E (PASS H202) rr Chl5 ft STATE"ENT: P Cf. T ACC IDE N T S AMPL I P,G IS PrSUIkED UNorF A LO!JG TERM LES3CNT LEARNFD PRO- 3
- PA" FD0" TPI-2 (NUPEG 0737).
11'011704 Ific I"P L E ?iE N T POCD 80-42 4 EAT R3 F1 (3 0) RC }
TcACE AN) INSULATL (CASS H202)
PN O"tr M S T A T E f'E N T : PC3T ACCIDE NT SAMFLING IS W OUIRF D LNCE P A LONC T F. fC1 LE9SCL LFAkNED FPO- Q ,
G'AM FROM TMI-2 ( f;UD E G 0717).
I'531340' P U .~ r!NAlllf PCCR A0 49 FKH "I T v I I' U T I O N (PASS H02)
3 ? a l F !? 21ATEt NT: PC: T ACC CCNT sA" FLING I" #
r, wIarg i a ;c A (09-cr3y ,pq9 yng.p ggyurG C7i7).
7L63 tr:3CNe LEARNED PPC- Ql [
It P11a14 i Y '. ! > P L ~ " F "J 1 IDC4 43 'LR 35 "1 (in) RC OI Ta'd L T!t" (PA " *23')
Q 'l P " C " L '_ M C T J T ("F :J T : PCC T ACCIC NT - A'if L I NC IS
- 9 0U IT E ^ U " "! 4 A LONS T"0" L 7 5 0 C2 *
- LE ARNT L Pan. <'
-AM rhCU IvI-2 (s!Ust , 07'7). '
f
- 1. n i m . - rauTm a m : 1- r, m e n) Trre (Nr n,
C f
rs
() r Of I
i C90: 183 ra**. H2C? EJFCT NOCES DATA CA TC 3JANK? <AGF 21 gg I
F L* "r N T D E S C R I P I I O N REG NUDPG UR GE NC Y GROWTH PLA NT RESOURCE !
NL He 1 CLASS PP!nRITY
. 07N0!
. _ . TI
. .CN
. . S_
...".._........._.._,_._......._..........__........__....._+...........__........ gg P909t"M STATEFFNY: PCCT ACCICfNT SAMPLING IS D' QUIFED U ". f 7 4 LCNG TCPM LESSCNS LEARNEC PRO-gg F A" TROM 191-0 (NUPEG 0737).
1!3110'04 lis! !"PLEMENT P0Cp AC-53A C-11 R3 F1 (10) PC gg tLFCf. (PAES H232)
P9 0E LF M STATE"ENT: PC3T ACCIDENT SAMPLING IS U. 7U IDE D U NUER A LONG T E R '4 LESSCNS LEARNfD PRO- gg 7 AM F R O*t TMI-2 (NUREG 0137).
19?11170! prop r!NAL!!! FDCR AC-46 CIVIL / R5 P1 (1 ) TECH (NED) gg c4 ??LL M STATEMENT: PCST ACCIDENT 5AMPLING IS R ;UIDED UNDER A LONG TERM LESSON % LEARNED PRO-G3AM FROM TMI-2 (NUREG 0737). gg I'3011C34 I T P. 5 I MPL f "C N T PCC4 80-46 CIVIL / R3 U1 (P ) FC pdO9 TEM STATEMENT: PC5T ACCICENT SAMPLING IS g)
REQUlkEC HN2EE A LONG TERM LESSCN" LEARNEC PRO-GEAM rqog TMI.2 (NUREG 0117).
19531110' D'PO FINALTOC rDCR 80-37 FVAC R3 61 9
(SO) TECH (NED)
('AS# HCP/)
!g Pf0PLEM ST Ait MENT : PCST ACCIDENT PAMPLING IS jp 9 0UIREC UNCER A LONC TERM Lf1SCNS LEARNED PRO-CC AM FRC4 TMI-2 (NUREG 0137).
l4 193011114 !Ti: !"rL E"E N T PCC4 8C-37 HVAC R3 H1 (10) RC II (par
- H202)
"sentFM %TATEMCNT: PCST A*CICENT C A M PL I '.C IS 1) j H :UIRLD UNata A L O *M T E a ?' LESSCN; LEARNED PRO-p AM FRCM TMI-2 (NURtG 0737).
I'F'll?3* P "' C FVALLATE AND TINALI?E SALE ANALYSIS AND R3 at (1 ) TFCH (PT) 44NCtING FF9Cstypr any paqDWARE (PASS H202) ra04Lt M 9? ATE"ENT: IT MAR NOT UEfN DL T E P"I P.E C r)
H"W FA*S4?02 GA"PLE! WILL BE HANCLED OR A*i A L YZ E D.
I) 0 (3
L) -t I