Application for Amend to License NPF-30,revising Tech Specs 3/4.8.2.1,3/4.8.2.2,3/4.8.3.1 & 3/4.8.3.2 Re Electrical Power Sys Dc Sources & Onsite Power Distribution
ML20073A684
Person / Time
Site: Callaway Ameren icon.png
Issue date: 09/09/1994
From: Schnell D
UNION ELECTRIC CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20073A686 List:
References
ULNRC-3071, NUDOCS 9409200365
Download: ML20073A684 (20)


Text

g,

?s' s 1901 CticJteau henue

  • . Post Office Box 149 f ,

St iavis, Maaun 63165 s 314 554-2E50 UNION September 9, 1994 Dondd f. Schnen swior v,ce riesisen ELECTRIC nuaear 53 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk -

Mail Station PI-137 Washington, D.C. 20555 ULNRC-3071 Gentlemen:

DOCKET NUMBER 50-483 CALLAWAY PLANT REVISION TO TECHNICAL SPECIFICATIONS 3/4.8.2.1, 3/4.8.2.2, 3/4.8.3.1 AND 3/4.8.3.2 ELECTRICAL POWER SYSTEMS D.C. SOURCES AND ONSITE POWER DISTRIBUTION

References:

1) ULNRC-2873 dated October 6, 1993 -
2) ULNRC-3020 dated May 13, 1994 Union Electric Company herewith transmits an application for amendment to Facility Operating License No. NPF-30 for Callaway Plant. This amendment request revises the 125-volt D.C. Sources Specifications (3.8.2.1 and 3.8.2.2) for battery bank and chargers to address the 125-volt D.C. busses and includes provisions for installed swing chargers which will be added to the plant design at the next refueling outage. The Onsite Power Distribution Specifications 3.8.3.1 and 3.8.3.2 are revised to address only the 120-volt A.C. Vital Busses. The Specifications 3.8.3.1 and 3.8.3.2 provisions for the 4160-volt and 480-volt A.C. Emergency Busses are not necessary since they supply power to the battery chargers which have more restrictive Limiting Conditions for Operation, Acd on Statements, and Surveillances in Specifications 3.8.2.1 and 3.8.2.2. The Specification 3.8.3.1 and 3.8.3.2 requirements for the 125-volt D.C. busses are incorparated into Specifications 3.8.2.1 and 3.8.2.2.

This amendment request revises Specifications 3.8.3.1 and 3.8.3.2 such that the amendment requested by Reference 1 and supplemented by Reference 2 will no longer be needed. .The Reference 1 request is withdrawn upon approval of this request.

Attachments 1, 2, 3, and 4 contain the Safety Evaluation, the Significant Hazards Evaluation, the Environmental Consideration, and the Proposed Technical Specification Changes in support of this amendment

,'r jj 9409200365 940909 PDR ADDCK 05000483- / l P PDR

Nq m . U.S. Nuclear Regulatory Commission-Page 2

- September 9, 1994 request. This chenge has been approved by the Callaway Onsite Review Committee and the Nuclear Safety Review Board.

This amendment includes provisions for flexibility.

provided by installed swing battery chargers which are being added to the plant design at Refuel 7 in Spring 1995. We request approval of this amendment request by March 31, 1995.

Venar truly yours, ,

i-GZGs '

/ Donald F. Schnell DS/dls P

Attachments: 1 - Saf ety Evaluation 2 - Significant Hazards Evaluation 3 - Environmental Considerations 4 - Proposed Technical Specification Changes  !

STATE OF MISSOURI )

) SS CITY OF ST. LOUIS )

Alan C. Passwater, of lawful age, being first duly sworn upon oath says that he is Manager, Licensing and Fuels (Nuclear) for Union Electric Company; that he has read the foregoing document and knows the content thereof; that he has executed the same for and on behalf of said company with full power and authority to do so; and that the facts therein stated are true and correct to the best of his knowledge, information and belief.

,ime, ,

By N

!!  :; j j Alan C. Passwater

{ ( NOTARY ! !

5 Manager, Licensing and Fuels-Nuclear

,, SEAL O

v,,es,.F M.\ , s

.....is BEp ar SUBSCyv.oholydsworntobeforemethis /2 f/> day of u uo , 1994.

/

,bhAa uC eah v

BARBARA LUNGWTTZ 0 M Ss on hp U g

Clix og gy gnygg ,, 9

.o, cc:- T. A. Baxter, Esq. f Shaw, Pittman, Potts & Trowbridge 2300.N. Street, N.W.

j Washington, D.C. 20037 M. H. Fletcher Professional Nuclear Consulting, Inc. .f

-18225-A' Flower Hill Way

  • Gaithersburg, MD 20879-5334 .;

i L. Robert Greger Chief, Reactor Project Branch 1 ,

U.S. Nuclear Regulatory Commission

~ Region III .

801 Warrenville Road Lisle, IL 60532-4351  ;

Bruce Bartlett ,

callaway Resident Office

  • U.S. Regulatory Commissio..

RR#1 Steedman, MO 65077 ,

L.-R. Wharton (2) ' -

Office of Nuclear Reactor Regulation .

U.S. Nuclear Regulatory Commission 1 White Flint, North, Mail Stop 13E21' 11555 Rockville Pike  :

Rockville, MD 20852

  • Manager, Electric Department {'

Missouri Public~ Service Commission P.O. Box 360 Jefferson City, MO 65102 i

Ron Kucera

~

Department of Natural Resources P.O. Box 176 Jefferson City, MO 65102 f

h 9

(

l

.- o

'- ' : ULNRC-30 71.

}

6-- _.

.- n '

6 i

. 1 h

ATTACHMENT ONE ,

SAFETY EVALUATION ,

i 4

1 L

9 t

f

?

I i

i t

1 1

n l

I s

is

  • Attachment 1 Page 1 of 7 SAFETY EVALUATION -

Proposed Chances This amendment request proposes a revision to the 125-volt D.C. '

Sources Specifications 3.8.2.1 and 3.8.2.2 and the Onsite Power Distribution Specifications 3.8.3.1 and 3.8.3.2. These specifications are restructured and simplified such that.all requirements for the 125-volt D.C. Sources are included in Specifications 3.8.2.1 and 3.8.2.2. The Onsite Power Distribution .

Specifications 3.8.3.1 and 3.8.3.2 will be limited to the 120-volt  !

A.C. Vital Busses.

The 125-volt D C. Sources Specifications 3.8.2.1 and 3.8.2.2 for battery banks and chargers is revised to also address the 125-volt D.C. busses. A surveillance (4 . 8. 2 .1. a . 3 ) ) is added to assure the '

busses are energized by verifying correct breaker alignment and indicated voltage on the busses at least once per 7 days.

Specifications 3.8.2.1 and 3.8.2.2 are also revised to include  :

provisions for installed swing chargers which will be added to the plant design at the next refueling outage.

The Onsite Power Distribution Specifications 3.8.3.1 and 3.8.3.2 are revised to address only the 120-volt A.C. Vital Busses. The specifications for the 4160-volt and 480-volt Emergency Busses ~are not necessary since these busses supply power to the battery chargers which have more restrictive Limiting Conditions for '

Operation (LCO), Action and Surveillance Requirements (SR) in .

Specification 3.8.2.1 and 3.8.2.2. The definition af " Operable" t as used by Union Electric requires that when a lir.e is de-energized the most restrictive allowed outage times' (AOT) for the bus and/or the loads it supplies governs the plant actions as prescribed by the Technical Specifications.

Plant Descrintion Figure 1 is a' simplified drawing of the existing. safety-related 125-volt D.C. system at Callaway. This figure shows the connections from the two 4160-volt A.C. Emergency Busses (NB01 and ,

NB02) through the four 480-volt A.C. Emergency Busses (NG01/NG03, NG04/NG02). The NG Busses supply power to the four full capacity chargers (NK21/NK23, NK22/NK24). Each charger supplies ~a Class 1E 125-volt D.C. bus (NK01, NK03, NK02, and NK04) and an associated i I

125-volt battery bank (NK11, NK13, NK12, or NK14).

Each D.C. bus also supplies a class 1E 120-volt A.C. Vital Bus

- (NN 01, NNO3, NN02, or NN04) through associated inverters (NN11, NN13, NN12, or NN14). Final Safety Analysis Report (FSAR) Figures 8.3-1 (sheets 1 and 2), 8.3-2, and 8.3-6 provide a more detailed depiction of these interconnections.

Class 1E A.C. System The Class 1E A.C. system distributes power at 4160-volt, 480-volt,  !

208/120-volt, and 120-volt A.C. to all safety-related loads.

l Also, the Class 1E A.C. system supplies certain selected loads l l

p g - .y

, ** Attachment 1 Page 2 of 7 l which are not safety-related but are important to the plant operation. FSAR Figure 8.3-2 lists the major safety-related and ;

isolated nonsafety-related loads supplied from the Class 1E A.C.

system.

In addition to the above power distribution, the Class-1E A.C.

system contains standby power sources (diesel generators) which provide the power required for safe shutdown in the event of a loss of the preferred power sources.

Each 4160-volt load group (NB) is supplied by two preferred power supply feeders and one diesel generator (standby) supply feeder.

Each 4160-volt bus supplies motor loads and 4.0-kV/480-volt load center transformers with their associated 480-volt busses (NG).

The Class 1E A.C. system is divided into two redundant load groups (load groups 1 and 2). Either one of the load groups is capable of providing power to safely reach cold shutdown for that unit.

Each A.C. load group consists of a 4160-volt bus, 480-volt load centers, 480-volt motor control centers, and lower voltage A.C.

supplies.

Class 1E D.C. Power System The existing D.C. power system consists of four independent Class 1E 125-volt D.C. subsystems, four non-Class 1E 125-volt D.C.

subsystems, and one non-Class 1E 250-volt D.C. system. The D.C.

power system is designed to provide reliable and continuous power for controls, instrumentation, inverters, and D.C. emergency auxiliaries.

The Class 1E D.C. system provides D.C. electric power to the Class 1E D.C. loads and for control and switching of the Class 1E systems. Physical separation, electrical isolation, and redundancy are provided to comply with the requirements of IEEE 308. The four Class 1E D.C. power subsystems are shown in FSAR Figure 8.3-6. Subsystems 1 and 4 provide control power for A.C.

Load Groups 1 and 2, respectively. These subsystems also provide vital instrumentation and control power for channels 1 and 4, respectively, of the reactor protection and engineered safety features systems. DC subsystems 2 and 3 provide vital instrumentation and control power for channels 2 and 3, respectively, of the reactor protection and engineered safety features systems. Each Class 1E D.C. power subsystem consists of one 125-volt battery bank, one battery charger, one inverter, and distribution switchboard busses. The battery chargers for D.C.

subsystems 1 and 3 are supplied 480-volt A.C. power-from different Class 1E busses of Load Group 1. Similarly, the battery chargers ,

for D.C. subsystems 2 and 4 are supplied 480-volt A'.C. power from l different Class 1E busses of Load Group 2. The inverters provide four independent 120-volt A.C. Vital instrumentation and control power supplies for the channels of reactor protection and engineered safety features systems. 4 1

Currently, one spare battery charger and one spare inverter are i provided for the power block. These items are physically located

  • . Attachment 1 Page 3 of 7 central to all of the Class 1E D.C. systems. They are not, however, electrically connected. In the event of the failure of a charger or inverter, the spare could be connected to the affected system. Therefore, the malfunctioning equipment may be repaired without imposing long-term disruption of the system. A design change to be implemented at Refuel 7 to permanently install seismically qualified swing chargers is described below. The spare inverter will be removed in conjunction with the inverter upgrades described below.

The batteries, racks, chargers, inverters, and auxiliary distribution equipment (switchboards and transfer switches) are l designated seismic Category I, and are designed to maintain their functional capability during and after a safe shutdown earthquake (SSE).

Vital Instrument A.C. Power Supply Four independent Class 1E 120-volt vital instrument A.C. power  ;

supplies are provided to supply the four channels of the protection systems and reactor control systems. Each vital instrument A.C. power supply consists of one inverter, one distribution bus, and one manual transfer switch. Normally, the inverter is operating to supply the vital A.C. bus. Each inverter is supplied by a separate Class 1E battery system, as described in FSAR Section 8.3.2. Currently, if an inverter is inoperable or is to be removed from service, the vital A.C. bus via a 480/120-volt transformer can be supplied from the 480-volt A.C. backup bus associated with the same load group through the manual transfer switch. A key interlock is provided to ensure that only a single transfer to the inverter backup transformer can be made at one time for each load group.

Refuel 7 Modifications Two modifications will be implemented during Refuel 7, one providing permanently installed swing chargers for the 125-volt i D.C. system and a second modification providing uninterruptable j power supplies (UPS) for the 120-volt A.C. Vital Instrument Power 1 Supplies. l 1

The current spare battery charger will be permanently installed as  !

a swing charger for the 125-volt D.C. Busses NK01 and NK03. l Another charger is being procured and will be installed as a swing l charger for 125-volt D.C. Busses NK04 and NK02. Each Class 1E

'D.C. power subsystem will then consist of one 125-volt battery, one primary battery charger, one UPS, distribution switchboards, a shared swing battery charger, and swing battery charger transfer switches. The battery chargers for D.C. subsystems 1 and 3 will supply 480-volt A.C. power from different Class 1E busses of Load Group 1 while their shared swing battery charger will supply 480-volt A.C. power from either a Class 1E bus of Load Group 1 or ,

a Non-class 1E bus from load group 5. Similarly, the battery '

chargers for D.C. subsystems 2 and 4 will be supplied 480-volt A.C. power from different Class 1E busses of Load Group 2 while

.their shared swing battery charger will supply 480-volt A.C. power i l

.. ** Attachment 1-Page 4 of 7 ,

from either a Class 1E bus of Load Group 2 or a Non-class 1E bus from load group 6.

Two swing battery charger subsystems will be provided for the Class 1E D.C. power subsystems. One for use with Class 1E D.C.

subsystems 1 and 3 and the other for use with Class 1E D.C.

subsystems 2 and 4. The swing chargers are permanently connected

{

to their respective Class 1E D.C. power subsystems via manually controlled electrically operated transfer switches. In the event of a failure of a primary battery charger, the respective swing battery charger can be quickly aligned to provide power to the ,

affected D.C. power subsystem. Therefore, the malfunctioning i equipment may be repaired without imposing long-term disruption of the system. Once the swing battery charger is aligned to a given l D.C. power subsystem all of the required annunciated trouble conditions are monitored on the swing charger and an annunciator J window on the main control boards is lit to alert the control room i staff that a swing charger is in use.  !

L The batteries, racks, chargers, inverters, and auxiliary l distribution equipment (switchboards and transfer switches) are l designated seismic Category 1, and are designed to maintain their functional capability during and after an SSE. This modification I is being performed under the provisions of 10CFR50.59. The modification allows the changes to Specifications 3.8.2.1 and 3.8.2.2 to allow the 125-volt D.C. power to be supplied from the installed swing chargers, where the previous-design did not allow switchover in the Technical Specification AOT of 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />.

The second modification is an upgrade to the existing inverters (NN11, NN13, NN12, and NN14). Each existing inverter will-be replaced with a state-of-the-art uninterruptable power supply (UPS) consisting of an inverter, a standby 480 to 120-volt isolation transformer, and an automatic transfer switch. The gating and synchronization circuit of the new UPS will monitor the plant A.C. system and keep inverter output in-phase and at the same frequency as the backup supply. This allows make-before-break any time.

transfers so that the bus is not de-energized at The load will be automatically transferred to the backup supply when any one of the following conditions is present:

1. Undervoltage detected on the output of the inverter SCR bridge.
2. Undervoltage. detected on the output of the inverter.
3. Manual initiation.
4. Output overcurrent.

Each of these conditions will be locally alarmed and will generate a main. control board annunciator and plant computer alarm.

Technical Specification Action 3.8.3.1 or 3.8.3.2 will be entered when loads are transferred to the backup supply. Figure.3 provides a schematic of this' design change. This modification requires no Technical Specification changes and is being performed under the' provisions of 10CFR50.59. It will provide improved plant reliability in the event of inverter problems or failures.

i

Attachment 1 Paga 5 of 7 Detailed Description of Technical Specification Chancee

. Specification 3/4.8.2.1 D.C. Sources - Operating The LCO is modified to include in part a), Busses NK01 and NK03 and installed full-capacity charger NK25. Part b) is modified to include Busses NK02 and NK04 and installed full capacity charger NK26. The busses have been added to the LCO so this specification becomes stand-alone and does not also rely on current Specification 3.8.3.1. The swing chargers are added to the LCO to allow for the flexibility provided by the modifications being implemented at the next refueling outage.

The chargers will be installed such that each can only supply one bus at a time. The chargers are equivalent to those in present design. They are seismic Category I and meet separation criteria by use of appropriate isolation devices.

The Action is modified to replace the term battery bank and/or full capacity charger with D.C. electrical source. This term describes the battery bank, full capacity charger, and the D.C. bus. This is also clarified in the Bases.

Surveillance 4.8.2.1.a.3) is added to this specification.

This surveillance was included in Specification 4.8.3.1, but is added here also since the D.C. busses are now contained in Specification 3.8.2.1. The term D.C. electrical source is -

also used.

. Specification 3/4.8.2.2 D.C. Sources - Shutdown The LCO is modified to address the D.C. busses and the swing chargers consistent with 3/4.8.2.1, with the exception that only one D.C. Source is required in Modes 5 and 6.

The Action is modified to use th? term D.C. electrical source consistent with 3/4.8.2.1.

The SR is modified to use the teni D.C. electrical source.

. Specification 3/4.8.3.1 Onsite Power Distribution - Operating The LCO is modified to address only the 120-volt A.C. Vital Busses and their associated inverters (UPS). The requirements for 4160-volt A.C. Emergency Busses OTB01 and NB02) and 480-volt A.C. Emergency Busses (NG01, NG03, NG05E, NG02, NG04, and NG06E) are deleted. The definition of " OPERABLE" as used by Union Electric requires that when a bus is de-energized the most restrictive AOT for the bus and/or the loads it supplies governs the plant actions as described by Technical Specifications. Busses NB01/NG01 and NB02/NG02 will supply a.

Class 1E battery charger. If they are de-energized, the 2-hour AOT of LCO 3.8.2.1 will apply since a battery charger will be de-energized. As an example, busses NG03 and NG04 will normally supply Class 1E battery chargers. If one or both of these busses were de-energized and the D.C. bus was i supplied by the associated swing charger, the AOTs of its

Attachment 1 Page 6 of 7 remaining loads would be assessed. In all likelihood, it would be restricted to the AOT associated with a containment isolation valve which would be 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />. Busses NG05E and NG06E supply loads associated with auxiliary equipment of the Essential Service Water System. The AOT for them would be 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> which is consistent with Specification 3/4.7.4.

LCO 3.8.3.1 contained a requirement that tie breakers between redundant busses be open. This requirement pertains to tie breakers 52 NG0116 between 480-volt busses NG01 and NG03 and-tie breaker 52 NG0216 between 480-volt busses NG02 and NG03.

, The purpose is to assure the 4 kV grid degraded voltage I setpoints are appropriate. This requirement is relocated to Table 3.3-3. Functional Unit 8.b. (Loss of Power 4 kV Bus Undervoltage - grid degraded voltage) which allows a single bus tie breaker to be closed for up to 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />. This is justified based on the small probability that voltage requirements on the system would be low enough to affect the setpoint, and the redundant train is fully independent and protected by its grid degraded voltage instrumentation and logic. A requirement has also been added to Table 4.3-2, Functional Unit 8.b. to verify on a weekly basis that these breakers are open.

The portion of LCO 3.8.3.1 which addresses the 125-volt D.C.

busses NK01 - NK04 is deleted since it will be incorporated into 3.8.2.1.

Action 3.8.3.1.a is deleted. It only provided actions in the event an A.C. emergency bus was not fully energized. As described above, this action is not necessary because the loads the busses supply power to dictate the appropriate actions to be taken to meet Technical Specification requirements.

Action 3.8.3.1.c is deleted. It is covered by proposed LCO 3.8.2.1 and its action statement. Action 3.8.3.1.c is {

actually less restrictive than 3.8.2.1 because of the logical i connector "or" and should also be deleted to eliminate a source of possible confusion.

. Specification 3/4.8.3.2 Onsite Power Distribution - Shutdown The LCO is modified to address only the 120-volt A.C. Vital and delete those portions that address the A.C. Emergency Busses and the 125-volt D.C. busses. This is consistent with Specification 3/4.8.3.1 proposed changes.

, The action is also modified to address only the 120-volt A.C.

f Vital Busses consistent with 3/4.8.3.1. f p

Evaluation l The changes represent a restructuring, so that all requirements associated with the D.C. Sources, including the busses, are addressed in a single specification. Provisions are added to

.- '.- Attachment 1 Page 7 of 7

  • ~'

, i allow'use of installed swing chargers to meet the LCO. The  ;

installed swing chargers are equivalent to existing full capacity .

chargers. The Onsite Power Distribution Specifications are ,

revised to delete LCO and Action Statements for the A.C. Emergency '

Busses. The actions associated with equipment which are powered

  • from these busses will dictate the plant actions as prescribed by Technical Specifications. l The proposed changes do not involve an unreviewed safety question because operation of Callaway Plant in accordance with these ,

changes would not:

1) Involve an increase in the probability of occurrence or the consequence of an accident or malfunction of equipment important to safety previously evaluated in the FSAR.

These proposed Technical Specification changes do not involve any hardware changes nor do they affect the probability of any event initiators. There will be no change to normal plant operating parameters or accident mitigation capabilities. There will be no increase in the '

consequences of any accident or equipment malfunction.

2) Create the possibility for accident or malfunction of equipment of a different type than previously evaluated in the FSAR. The proposed Technical Specification changes do not involve any design changes nor are there any changes ,

to the method by which any safety-related plant system '

performs its safety function. The normal manner of plant 1 operation is unaffected. No new accident scenarios, transient precursors, failure mechanisms, or limiting ,

single failures are introduced as a result of these changes. -

3) Involve a reduction in the margin of safety as defined in the basis for any Technical Specification. There will be no affect on the manner in which safety limits or limiting  ;

safety system settings are determined, nor will there be any effect in those plant systems necessary to assure the accomplishment of protection functions. There will be no ,

impact on DNBR limits, F,q F-delta-H, LOCA PCT, peak local power density or any other margin of safety.

Based on the information presented above, the proposed amendment does not involve an unreviewed safety question and will not adversely affect or endanger the health and safety of the general public.

.. J

- s NB01 NB02 L

01 N 3 04 N 2

  • 125V 125V 125V 125V BATTERY BATTERY BATTERY BATTERY NK 1 ly NK_13 NK 2 l) l) NK 4 l)

BATTERY ~~

BATTERY BATTERY BATTERY -

BATTERY 9 0 Ifh0 CHARGER NK21 AH CHARGER CHARGER AH CHARGER IfH CHARGER NK23 (SPARE) NK22 NK24

^__

S S S S S S S &

^_ ^

^_

TEST

) ) ) ) ) ) ) )

' ~

~

NKO1 NKO3 NK02 ~ NK04

) ) ) ) ) ) ) ) ) )

NK51 NK54 INVERTER Dl DI DIST DI pg INVERTER pA INVERTER p INVERTER INVERTER NN11 NN13 (S P ARE) EL pA NK41 NK43 NK42 NN12 NK44 NN14 3 -kh8hNG 3 ) -LSELS -LSELS ) -BKR CONT )

-BKR CONT -RCP PT -ESFAS .gspg r

.MCB U

- AUX FEED -MCB

-LSELS RCP PT y 120VAC -SSPS 120VAC 120VAC 7 INSTRUMENT INSTRUMENT INSTRUMENT DIESEL 120VAC BUS BUS NN01 NNO3 BUS FL A S HIN3- INSTRUMENT B

NNO2 BKR CONT- gN04

- EMERGENCY LIGHTING LSELS

- RCP PT RCP PT -

-ESFAS ESFAS

-MCB EMERGENCY LIGHTING-SAFETY RELATED 125VDC SYSTEM 0dkTTTTD G ET II '

Figure 1

LC NG01 LC PG19 LC NG04 LC PG20 SEP. GRP.1 SEP.GRP.5 SEP. GRP. 4 SEP. GRP. 6 (52NG0109) (52PG2010)

Y ('52PG1910)

' (52NG041d1 NK71 i O NK75 e o NC NO NC NO LC NG01 LC NG03 LC NG02 LC NG04 SEP. GRP.1 SEP. GRP.1 SEP. GRP. 4 SEP. GRP. 4 Bauen Bauey (52NG0103) , harger (52NG0303) (52NG0203) (52NG0403) gf w gf gf Charger gf NK25 NK26 Battery NC NO Battery Battery NC NO Battery Charger 4 9 Charger Charger , g Charger NK21 NK23 NK24 NK22 i . a i NK72 NK76 NK73 NK74 NK78 NK77 NC NO NO NC NC NO NO NC 125Vdc 125Vdc 125Vdc 125Vdc BUS BUS BUS BUS NK01 NK03 NK04 NK02 FIGURE 2

4 8 .

ll , if, A'y-5I E - _

v_

E 28 y Y

~

8  !: E 1 1 6666666 r

( 'S f

ig!+

s,g

  • 7
  • 9 II i if^gT

, ,, ssa

=

'I $$$$$$$!!

v 8 E . = v@ g

^I A is It I --4-"

gg

~j j I, a

m-G e

s vi to fl'T 3N 5 . 1 hh b ,? : * -

. r_ si , ,

! 5 6

~~

gI 1 1' y. $333333 i' s

,,* 5:

f.-

Y '

s f_

E

, b -

lI II li f'~Y 5 51 si y

'[fhhhhhh6$$

v I

! I  !

d!

a e  !. ^- +k E $

a ,1 q L

h, . ; . .

[ . ' *,

  • c.

ULNRC- 30 71-

j. ,

1 I. J f'

I e

']

h

.i ATTACHMENT TWO '

i n

I SIGNIFICANT HAZARD EVALUATION t

I t

t b

L t

i i.

b

?

L

- U i

1

)

6 6

f i

s f

D e

-r L b

b r

p

. s, , _

c 1

. i

.. ' Attachment 2 i Page 1 of 2 )

l SIGNIFICANT HAZARD EVALUATION I

Proposed Chances l This amendment request proposes a revision to the 125-volt D.C.

Sources Specifications 3.8.2.1 and 3.8.2.2 and the Onsite Power Distribution Specifications 3.8.3.1 and 3.8.3.2. These specifications are restructures and simplified such that all i requirements for the 125-volt D.C. Sources.are included in Specification 3.8.2.1 and 3.8.2.2. The Onsite Power Distribution Specifications 3.8.3.1 and 3.8.3.2 will be limited to the 120-volt A.C. Vital Busses.

The 125-volt D.C. Sources Specifications 3.8.2.1 and 3.8.2.2 for battery banks and charges is revised to also address the 125-volt '

D.C. busses. A surveillance ( 4 . 8 . 2 .1. a . 3 ) ) is added to assure the ;

busses are energized by verifying correct breaker alignment and >

indicated voltage on the busses at least once per 7 days.

Specifications 3.8.2.1 and 3.8.2.2 are also revised to include  !

provisions for installed swing charges which will be added to the plant design at the next refueling outage. -

The Onsite Power Distribution Specifications 3.8.3.1 and 3.8.3.2 are revised to address only the 120-volt A.C. Vital Busses. The specifications for the 4160-volt and 480-volt Emergency Busses are not necessary since these busses supply power to the battery chargers which have more restrictive Limiting Conditions for  ;

Operation (LCO), Action and Surveillance Requirements (SR) in ,

Specification 3.8.2.1 and 3.8.2.2. The definition of " Operable" '

as used by Union Electric requires that when a bus is de-energized the most restrictive allowed outage times (AOT) for the bus and/or the loads it supplies governs the plant actions as prescribed by ,

the Technical Specifications.

Evaluation The changes represent a restructuring, so that all requirements associated with the D.C. Sources, including the busses, are addressed in a single specification. Provisions are added to allow use of installed swing chargers to meet the LCO. The installed swing chargers are equivalent to existing full capacity chargers. The Onsite Power Distribution Specifications are revised to delete LCO and Action Statements for the A.C. Emergency Busses. The actions associated with equipment which are powered from these busses will dictate the plant actions as prescribed by Technical Specifications.

The proposed changes to the Technical Specifications do not -

involve a significant hazards consideration because operation of Callaway Plant in accordance with these changes would not:

1) Involve a significant increase in the probability or consequences of an accident previously evaluated. These  ;

I i

l j.; . Attachment 2 i Page 2 of 2

. j i

proposed Technical Specification changes do not involve any hardware changes nor do they affect the probability of any. event' initiators. There will be no change to normal plant operating parameters or accident mitigation i capabilities. There will be no increase in the i consequences of any accident or equipment malfunction.

2) Create the possibility for accident or malfunction of equipment of a different type than previously evaluated in the FSAR. The proposed Technical Specification changes do not involve any design changes nor are there any changes to the method by which any safety-related plant system performs its safety function. The normal manner of plant operation is unaffected. No new accident scenarios, transient precursors, failure mechanisms, or limiting single failures are introduced as a result of these i changes.
3) Involve a significant reduction in the margin of safety.

There will be no affect on the manner in which safety limits or limiting safety system settings are determined, nor will there be any effect in those plant systems necessary to assure the accomplishment of protection functions. There will be no impact on DNBR limits, F, q F-delta-H, LOCA PCT, peak local power density or any other-margin of safety.

Based on the information presented above, the proposed amendment does not involve a significant increase in the probability or consequences of an accident previously evaluated, create the possibility of a new.or different-kind of accident from any previously evaluated, or involve a significant reduction in a margin of safety. Therefore, it is concluded that the proposed changes meet the requirements of 10CFR50.92 (c) and does not involve a significant hazards consideration.

9

J g m 4mhe g A.+4e41AA =anWi 4 4 .h.4-a. 1da-r ~d.4--*F4 an sow Jmr45 a. h .h i.A4 4,4..e ,4 , i %q._,.J4 ,A

..J 'i . ULNRC-30 71 I

ATTACHMENT THREE ENVIRONMENTAL CONSIDERATION i

f J

i t

4 h

g a

__._.a._ _ . .,._.. .-. _ _ ,,-. - -_. .._. , -.. ,

,\ *. Attachment 3 Page 1 of 1 l

ENVIRONMENTAL CONSIDERATION

-This amendment request proposes a revision the 125-volt D.C.

Sources Specifications 3.8.2.1 and 3.8.2.2 and the Onsite Power Distribution Specifications 3.8.3.1 and 3.8.3.2. These specifications are restructured and simplified such that all requirements for the 125-volt D.C. Sources-are included in Specifications 3.8.2.1 and 3.8.2.2. The Onsite Power Distribution l Specifications 3.8.3.1 and 3.8.3.2 will be limited to the 120 Volt i A.C. Vital Busses.

The 125-volt D.C. Sources Specification 3.8.2.1 and 3.8.2.2 for battery banks and chargers is revised to also address the 125-volt D.C. busses. A surveillance (4.8.2.1.a.3)) is added to assure the busses are energized by verifying correct breaker alignment and 4 indicated voltage on the busses at least once per 7 days. l Specifications 3.8.2.1 and 3.8.2.2 are also revised to include i

, provisions for installed swing chargers which will be added to the plant design at the next refueling outage.

The Onsite Power Distribution Specifications 3.8.3.1 and 3.8.3.2 are revised to address only the 120-volt A.C. Vital Busses. The specifications for the 4160-volt and 480-volt Emergency Busses are not necessary since these busses supply power to the batter chargers which have more restrictive Limiting Conditions for Operation (LCO), Action and Surveillance Requirements (SR) in Specification 3.8.2.1 and 3.8.2.2. The definition of " Operable" as used by Union Electric requires that when a bus is de-energized the most restrictive allowed outage times (AOT) for the bus and/or the loads it supplies governs the plant actions as prescribed by the Technical Specifications.

The proposed amendment involves changes with respect to the use of facility components located within the restricted area, as defined in 10CFR20, and changes surveillance requirements. Union Electric has determined that the proposed amendment does not involve:

1) A significant hazards consideration, as discussed in Attachment 2 of this amendment application;
2) A significant change in the types or significant increase in the amounts of any effluents that may be released offsite;
3) A significant increase in individual or cumulative occupational radiation exposure.

-Accordingly, the proposed amendment meets the eligibility criteria for categorical exclusion set forth in 10CFR51.22 (c) (9) . Pursuant to 10CFR51.22lb),'no environmental impact statement or environmental assessment need be prepared in connection with the issuance of this amendment.