Text
.
f 1
(
t4w orrices or g
to DEBEVOISE & LIBERMAN
<\\
,s f 200 S EVE PDTEENT S TR E ET.
W 4 G TO *e dO36 sy
___ W B
TEan O 02; as r-seoO I 319a3 3 q5 7,,$ g July 12, 1983 e
y 4 I \\j-l'.orton Margulies, Esq.
Adm. Judge Frederick J.
Shon Chairman, Atomic Safety Atomic Safety and Licensing and Licensing Board Board U.
S.
Nuclear Regulatory U.
S.
Nuclear Regulatory Commission Commission Washington, D.
C.
20555 Washington, D.
C.
20555 Dr. James H.
Carpenter Atomic Safety and Licensing Board U.
S.
Nuclear Regulatory Commission Washington, D.
C.
20555 Re:
Washington Public Power Supply System (WPPSS Nuclear Project No. 3)
Docket No. 50-508 Gentlemen:
Attached for your information is a telecopied facsimile of a letter from the Washington Public Power Supply System, the Applicant in the captioned proceeding, to the NRC advis-ing it of an immediate construction delay of WNP-3 until an assured source of funding for continued construction can be obtained.
We provide this letter to the Board mindful of our res-ponsibilities to apprise the Board of developments bearing on matters within its jurisdiction.
Sincerely, Nicholas S.
Reynolds Counsel for Applicant Attachment cc:
Service List h
O PDR Mo3
4 Washington Putdle Power Supply System Ben 1223 Elms. Washington se541 (208)482-4428 Mr. Harold R. Denton, Di mctor Office of Nuclear Reactor Regulation Division of Licensing US Nuclear Regulatory Commission Washington. D.C.
20555
Dear Mr. Denton:
Subject:
CONSTRUCTION DELAY ON WNP-3 Refemnce:
603-83-451. GD Bouchey to HR Denton. dated June 3. 1983 The reference letter infonned you of implementation of a 30 day construction slowdown on WMP-3 while the supply System investigated alternative sources of financing.
On July 8.1983 the Supply System Executive Board adopted a resolution calling for an imediate construction delay of WNP-3 until an assured source of funding for continued construction can be obtained. A detailed implementation plan is currently in development anti is expected to be completed around August 1.1983. The Supply System will attempt to preserve the capabi.ity for a reasonably efficient restart during the next 3 to 9 months by mtaining the key class 1 contractors.
The Supply System remains committed to preservation of the physical plant and maintenance of the constructicn pemit during the period of construction delay. Additionally, the Supply System will continue to seek to remove the impediments preventing further financing of WNP-3 in order to msme project construction activities.
[
G. C. Sorensen. Manager Nuclear Safety and Regulatory Programs kWC/ss cc:
J. A. Adams - NESCO D. Smithpeter - 8PA A. Vietti - NRC Ebasco - Elma WMP-3 Files - Richland