MONTHYEARML20211D1321999-08-20020 August 1999 Application for Amend to License DPR-50 to Revise TS Bases Re Degraded Undervoltage Relay Setpoint Calibration Frequency & Degraded Voltage Relay Tolerance Rev ML20210J0941999-07-29029 July 1999 Suppl TS Change Request 274 to License DPR-50,revising ESF Sys Leakage Limits in post-accident Recirculation Surveillance Tss,As Result of NRC Generic Concerns Re CR Habitability Issues ML20196K5901999-06-29029 June 1999 LAR 285 for License DPR-50,clarifying Authority in Encl License Pages to Possess Radioactive Matls Without Unit Distinction,So That After Transfer of TMI-1 License to Amergen,Radioactive Matls Can Continue to Be Moved ML20209C0551999-06-29029 June 1999 LAR 77 for License DPR-73,clarifying Authority in Encl License Pages to Possess Radioactive Matls Without Unit Distinction,So That After Transfer of TMI-1 License to Amergen,Radioactive Matl May Continue to Be Moved ML20195E3341999-06-0404 June 1999 TS Change Request 265 to License DPR-50,modifying Conditions Which Allow Reduction in Number of Means for Maintaining Decay Heat Removal Capability During Shutdown Conditions ML20209B5891999-05-26026 May 1999 LAR 281 to License DPR-50,revising TMI-1 UFSAR Chapters 5 & 14 to Permit Use of Conservative Deterministic Failure Margin Methodology for Seismic Analysis of Portions of Auxiliary Steam Line.Rept 240046-R-001 Encl.Rept Withheld ML20206R1111999-05-13013 May 1999 Application for Amend to License DPR-50,requesting That License Sections 2.a.(3) & 2.c.(7) & TS Section 3.1.1 Be Revised to Incorporate Administrative Updating & Changes to Bases Statement ML20205H0691999-04-0101 April 1999 TS Change Request 262 to License DPR-50,revising TS by Adding LCO Action Statements & Making SRs More Consistent with NUREG-1430,correcting Conflicts or Inconsistencies Caused by Earlier TS Revs & Revising SFP Sampling ML20203B0421999-02-0202 February 1999 TS Change Request 274 to License DPR-50,expanding Scope of Systems & Test Requirements for post-accident RB Sump Recirculation ESF Systems & Increasing Max Allowable Leakage of TS 4.5.4 for Applicable Portions of ESF Systems ML20196G4401998-12-0303 December 1998 LAR 278 to License DPR-50,requesting Consent to Transfer & Authorize Amergen to Possess,Use & Operate TMI-1 Under Essentially Same Conditions & Authorizations Included in Existing License.Supporting Documentation,Encl ML20196H9751998-12-0303 December 1998 LAR 279 to License DPR-50,reflecting Decrease in RCS Flow Resulting from Revised Analysis to Allow Operation of Plant with 20% Average Level of SG Tubes Plugged Per SG ML20196G7671998-11-25025 November 1998 TS Change Request 277 to License DPR-50,changing Surveillance Specs for OTSG ISIs for TMI-1 Cycle 13 RFO Exams Which Would Be Applicable for One Cycle of Operation Only ML20154Q6201998-10-19019 October 1998 TS Change Request 248 to License DPR-50,adding Operability & SRs for Remote Shutdown Sys Similar to Requirements in NUREG-1430, Std Tech Specs - B&W Plants, Section 3.3.18, Remote Shutdown Sys ML20154P8441998-10-19019 October 1998 Application for Amend to License DPR-50,providing Allowable RCS Specific Activity Limit Based on OTSG Insp Results Performed Each Refueling Outage.Proprietary & non- Proprietary Calculation,Encl.Proprietary Info Withheld ML20154M3691998-10-15015 October 1998 Application for Amend to License Amend Request 276 to License DPR-50 Revising UFSAR Chapter 14 Accident Analysis Atmospheric Dispersion Factors.Ufsar Revised Pages Encl ML20249B2391998-06-11011 June 1998 TS Change Request 273 to License DPR-50,incorporating Alternate High Radiation Area Control Consistent W/Reg Guide 8.38 ML20217E5131998-03-23023 March 1998 Application for Amend to License DPR-50,revising TS Section 3.1.2 to Incorporate New Pressure Limits for Reactor Vessel IAW 10CFR50,App G for Period of Applicability Through 17.7 Efpy.Request Also Submitted in Response to NRC ML20217G0161997-10-0303 October 1997 Suppl to License Amend Request 268 to License DPR-50, Replacing Pages 4-80 & 4-81 Previously Submitted w/TMI-1 License Amend Request 268 on 970812 ML20211C3211997-09-19019 September 1997 Supplemental Application for Amend to License DPR-50 Re License Amend Request 269 Submitted on 970814.Suppl Includes Addl Change to TS Section 3.1.4 & Proposed Page Rev Clarifying That UFSAR Analysis Is More Conservative ML20211C2221997-09-19019 September 1997 Supplemental Application for Amend to License DPR-50 Re TS Change Request 266.Supplement Provides for Phased Review & Issuance of License Amends & Involves Administrative Correction to TS Decay Heat Removal Sys Leakage Rate ML20210J9951997-08-14014 August 1997 Revised License Amend Request 269 for License DPR-50, Revising TMI-1 UFSAR Section 14.1.2.9 Environ Dose Consequences for TMI-1 Steam Line Break Analysis ML20141J3981997-08-12012 August 1997 Tech Spec Change Request 268 for License DPR-50,revising Surveillance Specification for Once Through Steam Generator Inservice Insp for TMI-1 Cycle 12 Refueling (12R) Exams Applicable to TMI-1 Cycle 12 Operations ML20198E7871997-07-30030 July 1997 TS Change Request 266 to License DPR-50,incorporating Addl Sys Leakage Limits & Leak Test Requirements for Systems Outside Containment Which Were Not Previously Contained in TS 4.5.4 ML20141E1311997-05-0808 May 1997 Application for Amend to License DPR-50,consisting of Change Request 264,incorporating Addl NRC-approved Analytical Methods Used to Determine TMI-1 Core Operating Limits ML20140E2351997-04-21021 April 1997 Application for Amend to License DPR-50,requesting Rev to TS 3.3 Re Emergency Core Cooling,Reactor Bldg Emergency Cooling & Reactor Bldg Spray Systems ML20134M1111997-02-0707 February 1997 Application for Amend to License DPR-50,incorporating Certain Improvements from Revised STS for B&W Plants, NUREG-1430 & Addl Changes as Described in Encl TS ML20133D2651996-12-24024 December 1996 Application for Amend to License DPR-50,requesting Reinstatement of Auxiliary & Fuel Handling Bldg Ventilation Sys TS ML20132F3221996-12-16016 December 1996 Application for Amend to License DPR-50,consisting of Change Request 260,reflecting Change in Legal Name of Operator of Plant from Gpu Corp to Gpu Inc & Reflecting Plant License & TS Registered Trade Name of Gpu Energy ML20135C5201996-12-0202 December 1996 TS Change Request (Tscr) 75 to License DPR-73,relocating Audit Frequency Requirements to Pdms QA Plan ML20117H0181996-08-29029 August 1996 Application for Amend to License DPR-50,consisting of TS Change Request 257,incorporating Certain Improvements from STS for B&W Plants (NUREG-1430) ML20113D1901996-06-28028 June 1996 Application for Amend to License DPR-50,consisting of Change Request 259,allowing Implementation of Recently Approved Option B to 10CFR50,App J ML20112C8751996-05-24024 May 1996 Errata to Application for Amend to License DPR-50,consisting of TS Change Request 243,replacing Pages for App a ML20101R1361996-04-10010 April 1996 Application for Amend to License DPR-50,consisting of Change Request 243,revising Addl Group of Surveillances in Which Justification Has Been Completed Following Receipt of 930623 Application ML20100J6831996-02-22022 February 1996 Application for Amend to License DPR-50,consisting of Change Request 254,revising Proposed TS Page 4-46 on Paragraph 4.6.2 That Provides Addl Testing Requirements in Case Station Battery Cell Parameters Not Met ML20095J2261995-12-21021 December 1995 Revised TS Change Request 254,raising Low Voltage Action Level to 105 Volts DC ML20091L2831995-08-23023 August 1995 Rev to TS Change Request 223 to License DPR-50,incorporating Ref to 10CFR20.1302 ML20087F4881995-08-11011 August 1995 Rev to TS Change Request 252 to License DPR-50,removing TS Section 3.2 Re Makeup,Purification & Chemical Addition Sys Requirements.Certificate of Svc Encl ML20086R3001995-07-24024 July 1995 Rev to LAR 250 to License DPR-50,clarifying Section III, SE Justifying Change for source-range Nuclear Instrumentation SRs ML20085N1551995-06-22022 June 1995 TS Change Request 227 to License DPR-50,replacing Pages for App A.Certificate of Svc Encl ML20084N3461995-06-0101 June 1995 TS Change Request 223 to License DPR-50,deleting Remaining Portions of RETS & Relocating TSs Per Guidance in GL 89-01 & NUREG-1430 ML20084L4201995-06-0101 June 1995 TS Change Request 251 to DPR-50,revising TS 5.3.1.1 to Describe Use of Advanced Clad Assemblies ML20084B3261995-05-24024 May 1995 Application for Amend to License DPR-50.Amend Would Change Surveillance Test Requirements for source-range Nuclear Instrumentation ML20083N7771995-05-17017 May 1995 Application for Amend to License DPR-50,consisting of Change Request 252,removing Chemical Addition Sys Requirements from TS to COLR ML20079A7771994-12-23023 December 1994 Rev to TS Change Request 221 to License DPR-50,revising TS Page 3-32a ML20073F9241994-09-26026 September 1994 LAR 246 to License DPR-50,revising License Condition 2.C.9 Re Long Range Planning Program ML20069A6731994-05-20020 May 1994 TS Change Request 244 to License DPR-50,requesting Revised CR Trip Insertion Time Testing Acceptance Criterion for Remainder of Cycle 10 for 12 Specific CRs Which Initially Experienced Slow Rod Drop Times During Testing on 940317 ML20065M6681994-04-19019 April 1994 TS Change Request 237 to License DPR-50,deleting Audit Program Frequency Requirements from TS & Relocating Subj Requirements to Operational QA Plan ML20065K0381994-04-11011 April 1994 TS Change Request 238 to License DPR-50,relocating Detailed Insp Criteria,Methods & Frequencies of Containment Tendon Surveillance Program to FSAR ML20073C7701994-03-22022 March 1994 Application for Amend to License DPR-50 Re TS Change Request 242 Concerning Control Rod Trip Insertion Time Testing ML20064J3771994-03-11011 March 1994 Application for Amend to License DPR-50,revising TS Re Allowable Outage Time for Emergency Feedwater Pumps During Surveillance Activities 1999-08-20
[Table view] Category:TEXT-LICENSE APPLICATIONS & PERMITS
MONTHYEARML20211D1321999-08-20020 August 1999 Application for Amend to License DPR-50 to Revise TS Bases Re Degraded Undervoltage Relay Setpoint Calibration Frequency & Degraded Voltage Relay Tolerance Rev ML20210J0941999-07-29029 July 1999 Suppl TS Change Request 274 to License DPR-50,revising ESF Sys Leakage Limits in post-accident Recirculation Surveillance Tss,As Result of NRC Generic Concerns Re CR Habitability Issues ML20209D6651999-07-0808 July 1999 Corrected TS Pages 3-21,4-5a,4-9,4-38 & 6-3 to Amends 211 & 212 to License DPR-50.Pages Failed to Reflect Previously Approved Changes Granted in Amends 203 & 204 in Case of Amend 211 & 207 in Case of Amend 212 ML20196K5901999-06-29029 June 1999 LAR 285 for License DPR-50,clarifying Authority in Encl License Pages to Possess Radioactive Matls Without Unit Distinction,So That After Transfer of TMI-1 License to Amergen,Radioactive Matls Can Continue to Be Moved ML20209C0551999-06-29029 June 1999 LAR 77 for License DPR-73,clarifying Authority in Encl License Pages to Possess Radioactive Matls Without Unit Distinction,So That After Transfer of TMI-1 License to Amergen,Radioactive Matl May Continue to Be Moved ML20195E3341999-06-0404 June 1999 TS Change Request 265 to License DPR-50,modifying Conditions Which Allow Reduction in Number of Means for Maintaining Decay Heat Removal Capability During Shutdown Conditions ML20209B5891999-05-26026 May 1999 LAR 281 to License DPR-50,revising TMI-1 UFSAR Chapters 5 & 14 to Permit Use of Conservative Deterministic Failure Margin Methodology for Seismic Analysis of Portions of Auxiliary Steam Line.Rept 240046-R-001 Encl.Rept Withheld ML20206R1111999-05-13013 May 1999 Application for Amend to License DPR-50,requesting That License Sections 2.a.(3) & 2.c.(7) & TS Section 3.1.1 Be Revised to Incorporate Administrative Updating & Changes to Bases Statement ML20205H0691999-04-0101 April 1999 TS Change Request 262 to License DPR-50,revising TS by Adding LCO Action Statements & Making SRs More Consistent with NUREG-1430,correcting Conflicts or Inconsistencies Caused by Earlier TS Revs & Revising SFP Sampling ML20203B0421999-02-0202 February 1999 TS Change Request 274 to License DPR-50,expanding Scope of Systems & Test Requirements for post-accident RB Sump Recirculation ESF Systems & Increasing Max Allowable Leakage of TS 4.5.4 for Applicable Portions of ESF Systems ML20196H9751998-12-0303 December 1998 LAR 279 to License DPR-50,reflecting Decrease in RCS Flow Resulting from Revised Analysis to Allow Operation of Plant with 20% Average Level of SG Tubes Plugged Per SG ML20196G4401998-12-0303 December 1998 LAR 278 to License DPR-50,requesting Consent to Transfer & Authorize Amergen to Possess,Use & Operate TMI-1 Under Essentially Same Conditions & Authorizations Included in Existing License.Supporting Documentation,Encl ML20196G7671998-11-25025 November 1998 TS Change Request 277 to License DPR-50,changing Surveillance Specs for OTSG ISIs for TMI-1 Cycle 13 RFO Exams Which Would Be Applicable for One Cycle of Operation Only ML20195C6811998-11-12012 November 1998 Amend 52 to License DPR-73,relocating Audit Frequency Requirements from TMI-2 to TMI-2 Post Defueling Monitored Storage QA Plan & Extends Max Allowed Interval Between Certain Audits from 12 Months to 24 Months ML20154P8441998-10-19019 October 1998 Application for Amend to License DPR-50,providing Allowable RCS Specific Activity Limit Based on OTSG Insp Results Performed Each Refueling Outage.Proprietary & non- Proprietary Calculation,Encl.Proprietary Info Withheld ML20154Q6201998-10-19019 October 1998 TS Change Request 248 to License DPR-50,adding Operability & SRs for Remote Shutdown Sys Similar to Requirements in NUREG-1430, Std Tech Specs - B&W Plants, Section 3.3.18, Remote Shutdown Sys ML20154M3691998-10-15015 October 1998 Application for Amend to License Amend Request 276 to License DPR-50 Revising UFSAR Chapter 14 Accident Analysis Atmospheric Dispersion Factors.Ufsar Revised Pages Encl ML20249B2391998-06-11011 June 1998 TS Change Request 273 to License DPR-50,incorporating Alternate High Radiation Area Control Consistent W/Reg Guide 8.38 ML20217E5131998-03-23023 March 1998 Application for Amend to License DPR-50,revising TS Section 3.1.2 to Incorporate New Pressure Limits for Reactor Vessel IAW 10CFR50,App G for Period of Applicability Through 17.7 Efpy.Request Also Submitted in Response to NRC ML20217G0161997-10-0303 October 1997 Suppl to License Amend Request 268 to License DPR-50, Replacing Pages 4-80 & 4-81 Previously Submitted w/TMI-1 License Amend Request 268 on 970812 ML20211C2221997-09-19019 September 1997 Supplemental Application for Amend to License DPR-50 Re TS Change Request 266.Supplement Provides for Phased Review & Issuance of License Amends & Involves Administrative Correction to TS Decay Heat Removal Sys Leakage Rate ML20211C3211997-09-19019 September 1997 Supplemental Application for Amend to License DPR-50 Re License Amend Request 269 Submitted on 970814.Suppl Includes Addl Change to TS Section 3.1.4 & Proposed Page Rev Clarifying That UFSAR Analysis Is More Conservative ML20210J9951997-08-14014 August 1997 Revised License Amend Request 269 for License DPR-50, Revising TMI-1 UFSAR Section 14.1.2.9 Environ Dose Consequences for TMI-1 Steam Line Break Analysis ML20141J3981997-08-12012 August 1997 Tech Spec Change Request 268 for License DPR-50,revising Surveillance Specification for Once Through Steam Generator Inservice Insp for TMI-1 Cycle 12 Refueling (12R) Exams Applicable to TMI-1 Cycle 12 Operations ML20198E7871997-07-30030 July 1997 TS Change Request 266 to License DPR-50,incorporating Addl Sys Leakage Limits & Leak Test Requirements for Systems Outside Containment Which Were Not Previously Contained in TS 4.5.4 ML20141E1311997-05-0808 May 1997 Application for Amend to License DPR-50,consisting of Change Request 264,incorporating Addl NRC-approved Analytical Methods Used to Determine TMI-1 Core Operating Limits ML20140E2351997-04-21021 April 1997 Application for Amend to License DPR-50,requesting Rev to TS 3.3 Re Emergency Core Cooling,Reactor Bldg Emergency Cooling & Reactor Bldg Spray Systems ML20134M1111997-02-0707 February 1997 Application for Amend to License DPR-50,incorporating Certain Improvements from Revised STS for B&W Plants, NUREG-1430 & Addl Changes as Described in Encl TS ML20133D2651996-12-24024 December 1996 Application for Amend to License DPR-50,requesting Reinstatement of Auxiliary & Fuel Handling Bldg Ventilation Sys TS ML20132F3221996-12-16016 December 1996 Application for Amend to License DPR-50,consisting of Change Request 260,reflecting Change in Legal Name of Operator of Plant from Gpu Corp to Gpu Inc & Reflecting Plant License & TS Registered Trade Name of Gpu Energy ML20135C5201996-12-0202 December 1996 TS Change Request (Tscr) 75 to License DPR-73,relocating Audit Frequency Requirements to Pdms QA Plan ML20134D7761996-10-24024 October 1996 Amend 51 to License DPR-73,revising TS to Extend Surveillance Interval for Demonstrating Operability of Containment Airlock ML20128K1831996-10-0808 October 1996 Amend 50 to License DPR-73,revising TS to Incorporate Improvement from Administrative Controls Section of Revised STS for B&W Plants ML20117H0181996-08-29029 August 1996 Application for Amend to License DPR-50,consisting of TS Change Request 257,incorporating Certain Improvements from STS for B&W Plants (NUREG-1430) ML20113D1901996-06-28028 June 1996 Application for Amend to License DPR-50,consisting of Change Request 259,allowing Implementation of Recently Approved Option B to 10CFR50,App J ML20112C8751996-05-24024 May 1996 Errata to Application for Amend to License DPR-50,consisting of TS Change Request 243,replacing Pages for App a ML20101R1361996-04-10010 April 1996 Application for Amend to License DPR-50,consisting of Change Request 243,revising Addl Group of Surveillances in Which Justification Has Been Completed Following Receipt of 930623 Application ML20100J6831996-02-22022 February 1996 Application for Amend to License DPR-50,consisting of Change Request 254,revising Proposed TS Page 4-46 on Paragraph 4.6.2 That Provides Addl Testing Requirements in Case Station Battery Cell Parameters Not Met ML20095J2261995-12-21021 December 1995 Revised TS Change Request 254,raising Low Voltage Action Level to 105 Volts DC ML20091L2831995-08-23023 August 1995 Rev to TS Change Request 223 to License DPR-50,incorporating Ref to 10CFR20.1302 ML20087F4881995-08-11011 August 1995 Rev to TS Change Request 252 to License DPR-50,removing TS Section 3.2 Re Makeup,Purification & Chemical Addition Sys Requirements.Certificate of Svc Encl ML20086R3001995-07-24024 July 1995 Rev to LAR 250 to License DPR-50,clarifying Section III, SE Justifying Change for source-range Nuclear Instrumentation SRs ML20085N1551995-06-22022 June 1995 TS Change Request 227 to License DPR-50,replacing Pages for App A.Certificate of Svc Encl ML20084N3461995-06-0101 June 1995 TS Change Request 223 to License DPR-50,deleting Remaining Portions of RETS & Relocating TSs Per Guidance in GL 89-01 & NUREG-1430 ML20084L4201995-06-0101 June 1995 TS Change Request 251 to DPR-50,revising TS 5.3.1.1 to Describe Use of Advanced Clad Assemblies ML20084B3261995-05-24024 May 1995 Application for Amend to License DPR-50.Amend Would Change Surveillance Test Requirements for source-range Nuclear Instrumentation ML20083N7771995-05-17017 May 1995 Application for Amend to License DPR-50,consisting of Change Request 252,removing Chemical Addition Sys Requirements from TS to COLR ML20079A7771994-12-23023 December 1994 Rev to TS Change Request 221 to License DPR-50,revising TS Page 3-32a ML20073F9241994-09-26026 September 1994 LAR 246 to License DPR-50,revising License Condition 2.C.9 Re Long Range Planning Program ML20069A6731994-05-20020 May 1994 TS Change Request 244 to License DPR-50,requesting Revised CR Trip Insertion Time Testing Acceptance Criterion for Remainder of Cycle 10 for 12 Specific CRs Which Initially Experienced Slow Rod Drop Times During Testing on 940317 1999-08-20
[Table view] |
Text
. = .
METROPOLITAN EDISON COMPANY JERSEY CENTRAL POWER & LIGHT COMPANY AND PENNSYLVANIA ELECTRIC COMPANY THREE MILE . ISLAND NUCLEAR STATION, UNIT 1 Operating License No. DPR-50 Docket No. 50-289 Technical Specification Change Request No.127 This Technical Specification Change Request is subnitted in support of Licensee's request to change Appendix A to Operating License No.
DPR-50 for Three Mile Island Nuclear Station, Unit 1. As a part of this request, proposed replacement pages for Appendix A are also included.
GPU NUCLEAR CORPORATION A.
By_ _ _
Director, TMI-l Sworn and subscribed to befor- me this _
day of , g r , 1983.
8306270233 830620 PDR ADDCK 05000289 P PDR N:' M . %-
Nota v Public DAWLA JtAN BERRY, NOIARY PUBut WDOLDOWN BORO. DAUPHlh COUNTY .
MV CONNIS$10N EXPlRES JUNE 17, 1985 4 ember. Permsylvansa Assocutvon of 4 Manes
UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION IN THE MATTER 0F-DOCKET NO. 50-289 LICENSE NO. DPR-50 GPU NUCLEAR CORPORATION This is to certify that a copy of Technical Specification Change Request No. 127 to Appendix A of the Operating License for Three Mile Island Nuclear Station Unit 1, has, on the date given below, been filed with the U. S. Nuclear Regulatory Commission and been served on the chief executives of Londonderry Township,. Dauphin County, Pennsylvania; Dauphin County, Pennsylvania; and the Pennsylvania Department of Environ-mental Resources, Bureau of Radiation Protection, by deposit in the United States mail, addressed as follows:
Mr. Jay H. Kopp, Chairman Mr. John E. Minnich, Chairman Board of Supervisors of Board of County Commissioners Londonderry Township of Dauphin County R. D. #1, Geyers Church Road Dauphin County Courthouse Middletown, PA 17057- Harrisburg, PA -17120 Mr. Thomas Gerusky, Director Penna. Dept. of Environmental Resources Bureau of Radiation' Protection P.O.. Box 2063 Harrisburg, PA 17120 GPU NUCLEAR CORPORATION a
BY birector, TMI-l DATED: June 20, 1983
I. Technical Specification Change Request No. 127 The Licensee requests that the attached changed pages replace the following pages of the existing Technical Specifications:
2-2, 2-9, 3-34 and Figure 3.5-2G.
II. Reason for Change Request Since the time that TMI-1 has been shutdown by order on July 2, 1979, infor-mation has been received from our NSS supplier which would result in changes to the existing Technical Specifications. These include the following areas:
- a. Centerline Fuel Melt Limit (editorial)
The Tech Specs bases on page 2-2 incorrectly retained the Cycle 4 centerline fuel melt limit of 19.6 kw/ft. The CFM limit is 20.15 kw/ft for Cycle 5. The Cycle 5 core no longer contains any of the earlier design fuel assemblies (19.6 kw/ft CFM) but consists entirely of the newer Mark B4 assemblies with a 20.15 kw/ft CFM limit (See Cycle 5 Reload Report Table 4-2).
- b. Flux to Pump Trip Setpoint for 2 pump operation (change for convenience)
The nuclear power-based pump monitor RFS trip setpoint for two-pump operation (one pump in each loop) specified in Table 2.3.1 of the Cycle 5 Technical Specifications is proposed to be reduced from 91% t.o 55% of rated power. The existing 91% setpoint was established by the original FSAR analyses for TMI-1. An evaluation accounting for changes in DNBR-related design factors since Cycle 1 has shown that the 91% limit would remain conservative for Cycle 5 operation and was justified for all previous cycles. The GPUN decision to reduce the setpoint to 55% rated power is based on B&W's recommendation for 177 FA plants with redundant pump monitors. The reduced setpoint will provide a consistent bases for any future B&W analyses and is consistent with the setpoint at other B&W plants. This change will not significantly impact anticipated operation of the unit.
- c. Quadrant Tilt Instrumentation (Administrative)
Tech Spec sections 3.5.2.4 (b) and (c) on quadrant tilt have been rewritten so that quadrant tilt is always determined by the most accurate detector system available. The out of core detector system is more accurate than the minimum incore system. This does not represent a change in the existing allowable tilt limits for any of the detector systems.
- d. LOCA kw/ft Limits (safety)
See Safety Evaluation below, i
\
III. Safety Evaluation Justifying Change Initial conditions for the TMI-1, Cycle 5 ECCS analysis were established using the approved TAFY (BAW 10044) fuel performance code. Early in 1980 B&W found a potential non-conservatism in the prediction of peak cladding temperature during a LOCA because the TAFY assumption of instantaneous fuel pellet densification resulted in unrealistically low internal fuel rod pressure early in life. To offset this difficulty, B&W proposed a re' duction in the LOCA kw/f t limits at the lower core elevations (2,4,6 feet) for the first 50 EFPD of operation (See B&W letters 3 Taylor to Rubenstein, dated September 5,1980). The proposed reduced limits reflect a direct comparison, without tradeoffs, of TAFY calculations with the newer approved TACO-1 (BAW-10087P-A) fuel code that incorporates a mechanistic densification model as required by the staff. Therefore, the current TAFY analysis, coupled with the revised LOCA kw/ft limits, provides conservative -LOCA predictions relative to the as-approved TACO-1 code for exposures from 0 to 42,000 HRD/MtU. Furthermore, the TAFY analysis provides conservative fuel rod internal pressure predictions relative to TACO-1 over the same exposure range. The staff reviewed and accepted B&W's proposal for using TAFY with the reductions ~in local power limits in the ECCS analysis (See NRC letter, Rubenstein to Taylor, dated October 28, 1980).
The new accepted bounding values for allowable LOCA Peak linear heat rates are given below:
Allowable Peak Allowable Peak Core LHR, First 50 LHR, Balance of Elevation, ft. EFPD kw/ft. Cycle kw/ft.
2 14.5 15.5 4 16.1 16.6 6 17.5 18.0 8 17.0 17.0 10 16.0 16.0 A revised Figure 3.5-2G of the TMI-1, Cycle 5 Technical Specifications is enclosed.
The Cycle 5 Technical Specification operating limits on rod index, APSR position, and axial power iibalance covering the 0-50 EFPD period were investigated and verified t) bound the interim LOCA kw/ft limits. As a
- result of the additional margin in the Cycle 5 Technical Crecifications, which were purposely set with the intent of boundin- tuture cycles, there was margin available without changing the other Tech.ical Specifications for the first 50 EFPD of Cycle 5.
IV. Significant Hazards Considerntions Evaluation The operation of TMI-l in accordance with this Tech Spec Change Request would not:
a) involve a significant increase in the probability of occurrence or the consequences of an accident previously evaluated since this change adds greater conservatism based on newer models, thereby enhancing safety.
b) create the possibility for an accident or malfunction of a new or different kind of accident from any accident previously evaluated sinbe this change is bounded by more conservative analyses.
c) involve a significant reduction in the margin of safety since again more conservative analyses is used as the primary source. Therefore, there are no unreviewed safety questions or significant safety hazards associated with this change.
V. Amendment Class (10 CFR 170)
The Licensee has determined that this change involves a single safety issue.
Therefore, a check for $4,000 is enclosed.
VI. Implementation Because of the nature of the change it is' requested that the implementation of the resulting amendment occur immediately.