FNP-0-ETP-4389 March 8, 1994
)
Revision 1
]
e f
)
FARLEY NUCLEAR PLANT i
ENGINEERING TECHNICAL PROCEDURE FNP-0-ETP-4389 i
i S
A F
i E
T Y
SERVICE WATER STORAGE POND DAM BIENNIAL INSPECTION R
E i
~L A
T E
D
[
P t
UNCONTROLLEO COPY Caution: This %is
$o'Not use in setery
'naenraineo curres Approved:
i b led AcrMgy, AW I
Systems Performance Manager t
Date:
3, 7,)I fY
~l I
t r
- - - ~
,g;%.J.63;d t
MSL ETP 10
, ;.y m,hs.
4:'e *'
hu
'2.N
,g
\\;.;
x Y
/
g,
t2 rtcavt 0
!p g,3 paint. supped
- j 9408110170 940729 r
ADOCK 050003 8 PDR F
xc- - ; o e. - -
s e
i SYSTEMS PERFORMANCE TEST RESULTS
SUMMARY
REPORT Section I Test Description
Title:
SERVICE WATER STORAGE POND DAM BIENNIAL INSPECTION Procedure Number NP-0-ETP-4389 Revision Number:
1 I
Start Date:
Completion Date:
t Section II Test Results, Evaluation and Recommendations I
r t
D Test satisfactory (test results recournended for approval) l D Test unsatisfactory (explain below, as needed)
D All data sheets and other test data are attached.
O All test data steps and data sheets have been completed and signed off.
O Other disposition as reconsnended below.
Remarks:
t Perfornwd By:
Date Section III Systems Performance Supervisor's Review Consnents :
Approved: _
Date i
PROVISIONS OF FNP-0-AP-24 ARE NOT APPLICABLE MSL-ETP-10 FIGURE 1 i
r L
r-i EtJP-0-ETP-4 3 9 9 LIST OF EFFECTIVE PAGES REVISION NO.
PAGE NO.
O 1
2 3
4 5
6 7
8 9
10 1
X X
2 X
X 3
X X
4 X
DATA SHEET 1 1
X MSL ETP-10 Page 1 of 1
t FNP-0-ETP4380 FARLEY NUCLEAR PLANT UNITS 1 AND 2 i
ENGINEERING TECHNICAL PROCEDURE SERVICE WATER STORAGE POND DAM BIENNIAL INSPECTION FNP-0-ETP-4389 1.0 Purpose 1.1 The purpose of this procedure is to describe the regular biennial inspection of the service water pond dam at Farley Nuclear Plant.
In addition, results are evaluated by Southern Company Services.
Their evaluation is normally submitted within 30 days of the completion of the testing.
The evaluation letter includes recommendations for corrective action when appropriate.
This inspection is designed to prevent operational problems related to the dam by helping to insure that its integrity is maintained, i
The provisions of FNP-0-AP-24 are not applicable.
2.0 Acceptance Criteria 2.1 Evaluation of the dam is based on an inspection performed by the Alabama Power dam inspection team, consisting of engineers selected based on experience and knowledge in the design, construction and operation of dams.
Otherwise, no quantitative acceptance criteria exists.
3.0 Corrective Action 3.1 Proper corrective action varies and depends on a thorough assessment of conditions by qualified engineers.
3.1.1 For any condition which does not present an immediate threat to the integrity of the J
structure or plant, the inspection team will include recommendations for the appropriate corrective action (s) in the inspection report.
3.1.2 For any condition which presents an imminent danger to the integrity of the structure or the plant, the condition will be immediately evaluated and discussed with the appropriate I
plant personnel.
MSL ETP-10 1
Rev. 1
FNP-0-ETP-4389 4.0 Reference 4.1 U.
S.
Nuclear Regulatory Commission 8
" Regulatory Guide" 1.127, " Inspection of Water-l Control Structures Associated with Nuclear Power Plants".
4.2
" Post-Construction Report, Storage Pond Dam J
and Dike Embankments, Joseph M.
Farley Nuclear Plant", Bechtel Power Corporation, September, 1977.
4.3 D-176980, Storage Pond Dam and Dike General Arrangement and Stripping Plan.
4.4 FNP-0-ETP-4381, Service Water Storage Pond Piezometer Well Readings.
5.0 Test Equipment 5.1 The inspection is strictly visual.
No test equipment is utilized in the inspection.
l PGS 6.0 Precautions and Limitations 6.1 Steps of the procedure with a designator (described below) in the left margin denote the requirement i
for the individual performing the step to provide his initial and date on the data sheet.
6.1.1 Designator PGS, APC Power Generation Service 6.1.2 Designator SP, Systems Performance PGS/ 7.0 Prerequisites and Initial Conditions SP 7.1 PGS has coordinated work through the General Manager of Nuclear Support at Southern Nuclear.
7.2 Performance of this procedure has been scheduled by FNP-SP.
7.3 Permission has been obtained from the shift supervisor to perform this procedure.
7.3.3 Notify appropriate site personnel of any conditions found in 7.2.2.1 (b) which are considered to require immediate repair before leaving the plant site.
MSL ETP-10 2
Rev. 1 f
R w
FNP-0-ETP-4389 PGS 8.0.
Instructions NOTE: DESCRIBE ANY ABNORMALITIES IN THE REMARKS SECTION OF THE DATA SHEET.
4 8.1 Scope of Inspection 8.1.1 Inspection of the entire length of the embankment structure, along the downstream toe and along the top of the dam is made on foot.
The appurtenant intake and discharge structures are also examined during this
[
inspection.
Inspection of the spillway-i channel is made at various points by vehicle.
PGS 8.2 Inspection 8.2.1 In the inspection of the embankmen*,
particular attention is given to detecting i
signs of seepage, erosion, differential i
settlement, displacement, cracking, or animal burrows, fire, ant hills, bushes and j
small trees on the embankment slopes,
~
ungrassed areas, and water ponding areas or other undesirable conditions along the roadway surface.
The rip rap on the upstream slope is inspected for signs of movement, excessive bush and tree growth.
Presence of one or more of these conditions to an excessive extent could indicate slope instability, s
8.2.2 Permanently installed instrumentation used h
to measure the performance of the structure is inspected for any. obvious changes or l
indications of improper functioning.
Instrumentation protective devices including above ground piping frames, covers and caps are inspected for damage,. deterioration, missing parts, and other abnormal conditions.
8.2.3 Appurtenant concrete structures are examined I
for structural cracking, deterioration, i
obstruction, settlement or other' conditions that could eventually impose operational j
constraints.
8.2.4 The unlined spillway channel is examined to verify that there are no significant obstructions of flow.
MSL.ETP-10 3
Rev. 1
.l
FbN)-ETP-4339 o
8.2.5 Gravity relief well manholes and the chimney drain central manhole are entered and 6
inspected for obstructions, deterioration, improper functioning or other conditions affecting proper operation.
8.2.6 Areas noted in previous biennial reports as being in need of corrective action or maintenance are re-inspected to be sure the conditions noted have been corrected and have not recurred.
8.3 Documentation PGS 8.3.1 Following the inspection, a meeting will be held with FNP-SP to report observations made i
during the inspection.
8.3.2 A final report of observations made during the inspection will be transmitted to the General Manager of Nuclear Support at Southern Nuclear.
9.0 Restoration SP 9.1 Shift supervisor notified of completion of inspection.
l MSL ETP-10 4
Rev. 1
FNP-O-ETP-4389 PAGE 1 OF 1 DATA SHEET Service Water Storage Pond Dam Biennial Inspection TPNS NO:
MWR/WA NO:
DATE:
STEP DESCRIPTION SIGNATURE
/DATE 6.0 Precautions and limitations have been (PGS)
/
read and understood.
t 7.0 Prerequisites & Initial Conditions (PGS)
/
l Completed / Satisfied.
(SP)
/
8.0 Full length of the dam and the (PGS)
/
structure inspected for abnormalities.
Comments noted in remarks section.
8.3.1 Met with FNP-SP to discuss observation (PGS)
/
made during the inspection.
9.1 Shift Supervisor notified of inspection (SP)
/
completion.
1 REMARKS:
i l
i l
i OAL.2182 Rev. O