Notifies of Status of NRC Bulletin 88-004 Re Corrective Actions Which Were Completed During Unit 2 1990 & Unit 1 1991 Refueling Outages.As of 910214,proposed Changes to Tech Spec Allowing Improvements of Pump Test Requirement
ML20070U634
Person / Time
Site: North Anna  Dominion icon.png
Issue date: 04/05/1991
From: Stewart W
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
90-328A, IEB-88-004, IEB-88-4, NUDOCS 9104090211
Download: ML20070U634 (2)


Text

_ - _. . _ _ __ _ . _ - _ . _ __ _. _ _ _ _ . _. _ . _ _ _ _ _ . . _

  • VIHOIN!A El.iicTuir Axn Pown:n Coxi'Axy lucunoxo,Viuoix A uneon H

April 5, 1991 United States Nuclear Regulatory Commission Serial No. 90 328A Attention: Document Control Desk NAPS /JHL Washington, D.C. 20555 Docket Nos. 50 3T.,

50 339 License Nos. NPF 4 NPF-7 Gentlemen:

yJRGINIA ELECTRIC AND POWER COMPAfiY NORTH ANNA POWER STATION UNIT NOS.1 AND 2 STATUS OF NRC BULLETIN _S8-04:

EOTENTIAL SAFETY REL ATED PUMP LOSS NRC Bulletin 88 04: " Potential Safety Related Pump Loss" identified concerns with minimum flow designs and requested licensees to investigate these concerns and correct them where applicable. Our letter dated August 8,1988 provided a list of corrective actions necessary to satisfy these concerns. Our letter dated June 13,1990 provided a status of the corrective actions associated with NRC Bulletin 88 04, This letteris to notify you that long term corrective actions associated with NRC Bulletin 88 04 were completed during the Unit 2.1990 and Unit 1 1991 refueling outages.

Specifically, full flow recirculation -lines were installed on the auxiliary feedwater pumps. The full flow recirculation liries were added to prevent pump damage during pump testing and during possible extended pump runs at low flow conditions.

On February 14, 1991, we proposed changes to the North Anna ichnical Specifications to allow improvements in the current monthly AFW pu. n test requirements. As we stated at that time, inspections conducted in accordance with NRC Bulletin 88 04 had indicated that some degradation had occurred which was not revealed by the high pressure / low flow monthly test currently required. We noted that the quarterly Section XI testing is done at_ flow conditions near the pump's best

-' efficiency point and observed that testing at the lowei pressure / higher flow conditions required undar the Code could provide early warning of degradation. We stated that if the monthly test could be done under similar conditions, safety would be enhanced because there would be less pump wear and more effective testing. We continue to encourage your prompt review and approval of this proposed change.

9104090211 910405

/

/~

h '

PDR ADOCK 05o00338  ; g l G FDR A l l' _

, _ - _ _l

= i d

These modifications complete the corrective actions associated with NRC Bulletin 88 04, if you have any questions, please contact us. )

Very truly yours, i.j{hlfG3W sh W. L. Stewart Senior Vice President Nuclear cc: U.S. Nuclear Regulatory Commission Region 11 101 Marietta Street, N.W.