TENNESSEE VALLEY AUTHORITY CH ATTANOOG A. TENNESSEE 374n1 400 Chestnut Street Tower II w
January 18, 1983 E
BLRD-50-438/83-06
~
g BLRD-50-439/83-03 p
cc U.S. Nuclear Regulatory Commission N
0 Region II Attn:
Mr. James P. O'Reilly, Regional Administrator 101 Marietta Street, Suite 3100 Atlanta, Georgia 30303
Dear Mr. O'Reilly:
BELLEFONTE NUCLEAR PLANT UNITS 1 AND 2 - DEFICIENT HANDLING OF DESIGN CHANGE REPORTS - BLRD-50-438/83-06, BLRD-50-439/83 FIRST INTERIM REPORT The subject deficiency was initially reported to NRC-0IE Inspector D. M. % ccelli on December 21, 1982 in accordance with 10 CFR 50.55(e) as NCR BLN BLP 8234. Enclosed is our first interim report. We expect to submit our next report on or about July 6, 1983 If you have any questions, please get in touch with R. H. Shell at FTS 858-2688.
Very truly yours, TENNESSEE VALLEY AUTHORITY L. M. Mills,lManager Nuclear Licensing l
Enclosure cc:
Mr. Richard C. DeYoung, Director (Enclosure)
Office of Inspection and Enforcement U.S. Nuclear Regulatory Commission Washington, D.C.
20555 l
OFFbdE6pp 8301260393 830118 DR ADOCK 05000 g
An Ecual Opportumty Employer I
2..
ENCLOSURE BELLEFONTE NUCLEAR PLANT UNITS 1 AND 2 DEFICIENT HANDLING OF DESIGN CHANGE REPORTS 10 CFR 50.55(e)
NCR BLN BLP 8234 BLRD-50-438/83-06, BLRD-50-439/83-03 FIRST INTERIM REPORT Description of Deficiency Design change reports are the method whereby changes to mechanical piping systems are identified to personnel responsible for the piping analysis in order that the analysis can be revised to reflect these changes. The handling of design change reports has been determined to be deficient.
During the INPO self-initiated evaluation, it was determined that two design change reports (Nos. 1061 and 1062) did not have associated design change impact reports nor was a file copy of either available.
Insufficient information was supplied in the design change report log to enable tracing of these reports. In addition, it was determined that there are different understandings within the TVA's Division of Engineering Design, Bellefonte Design Project, Mechanical Design Group concerning the criteria for issuing a design change report.
Interim Progress Bellefonte Design Project's engineering procedure BLP EP-44.76 will be revised to citrify (a) the responsibility and methods for documenting design change reports, and (b) the criteria for issuing a design change report. In addition, all design change reports not adequately documented as having been closed will be identified and evaluated, thus help *.ng to trace the missing reports.