ML20070C225

From kanterella
Jump to navigation Jump to search
Interim Deficiency Rept Re Issuance of Planners by Itt Grinnell W/O Prior Approval by S&W.Initially Reported on 821101.Work Restarted as Planners Released by S&W.Final Rept Will Be Submitted by 830131
ML20070C225
Person / Time
Site: Nine Mile Point Constellation icon.png
Issue date: 12/01/1982
From: Manno S
NIAGARA MOHAWK POWER CORP.
To: Starostecki R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
References
10CFR-050.55E, 10CFR-50.55E, NUDOCS 8212140093
Download: ML20070C225 (2)


Text

. . .

M V NIAGARA RUMOHAWK 8HAGARA MOHAWK POWEft CORPORATl0N/300 ERIE BOULEVARD WEST, SYRACUSE, N.Y.13202/ TELEPHONE (315) 4741511 SAMUEL F MANNO VICE PRESIDENT NUCLE AR CONSTRUCTION December 1, 1982 Mr. R. W. Starostecki, Director U.S. Nuclear Rc9ulatory Connission Region 1 Division of Project and Resident Programs 631 Park Avenue King of Prussia, PA 19406 Re: Nine Mile Point Unit 2 Docket No. 50-410

Dear Mr. Starostecki:

Enclosed is an interim 30 day report in accordance with 10CFR50.55(e). This potentially reportable deficiency concerns a planner issued by a contractor, ITT Grinnell Corporation, without prior approval. This matter was reported to Mr. H. Kister of your staff by telephone on November 1,1982.

Very truly yours, amuel c. Manno Vice President Nuclear Construction Enclosure xc: Director of Inspection and Enforcement Mr. R. D. Schulz, Resident Inspector 8212140093 821201 d gDRADOCK05000

- ~. -- . -- .- _ .

. . 4 NIAGARA M0 HAWK POWER CORPORATION NINE MILE POINT UNIT 2 DOCKET NO. 50-410 Interim Report for a Potentially Reportable Deficiency Under 4

10CFR50.55(e) Regarding ITT Grinnell Issue of Planners Without Prior Approval ITT Grinnell Corporation completed a repair to an ASME III, Class.I penetration weld without a Stone & Webster Engineering Corporation approved planner. This was a violation of a commitnent to the NRC in response to Inspection Report 82-08 (10/14/82) which states that as of July 1,1982 all

Category I welding and/or bending Field Planner Packages must be concurred with by Stone & Webster Engineering Corporation before being released by Grinnell for construction. Stone & Webster Engineering Corporation initiated a stop work on ITT Grinnell activities. Work was restarted as each planner' was reviewed and released by Stone & Webster Engineering Corporation. This matter is still under investigation. A final report will be submitted by

, January 31, 1983.

i l

. _ , ._ . , - - _ _ , . , , - - - .- < - - - - - - - - ~ - - - - - - - . - -