M V NIAGARA RUMOHAWK 8HAGARA MOHAWK POWEft CORPORATl0N/300 ERIE BOULEVARD WEST, SYRACUSE, N.Y.13202/ TELEPHONE (315) 4741511 SAMUEL F MANNO VICE PRESIDENT NUCLE AR CONSTRUCTION December 1, 1982 Mr. R. W. Starostecki, Director U.S. Nuclear Rc9ulatory Connission Region 1 Division of Project and Resident Programs 631 Park Avenue King of Prussia, PA 19406 Re:
Nine Mile Point Unit 2 Docket No. 50-410
Dear Mr. Starostecki:
Enclosed is an interim 30 day report in accordance with 10CFR50.55(e). This potentially reportable deficiency concerns a planner issued by a contractor, ITT Grinnell Corporation, without prior approval. This matter was reported to Mr. H. Kister of your staff by telephone on November 1,1982.
Very truly yours, amuel
- c. Manno Vice President Nuclear Construction Enclosure xc: Director of Inspection and Enforcement Mr. R. D. Schulz, Resident Inspector 8212140093 821201 d
gDRADOCK05000
- ~.
4 NIAGARA M0 HAWK POWER CORPORATION NINE MILE POINT UNIT 2 DOCKET NO. 50-410 Interim Report for a Potentially Reportable Deficiency Under 10CFR50.55(e) Regarding ITT Grinnell 4
Issue of Planners Without Prior Approval ITT Grinnell Corporation completed a repair to an ASME III, Class.I penetration weld without a Stone & Webster Engineering Corporation approved planner.
This was a violation of a commitnent to the NRC in response to Inspection Report 82-08 (10/14/82) which states that as of July 1,1982 all Category I welding and/or bending Field Planner Packages must be concurred with by Stone & Webster Engineering Corporation before being released by Grinnell for construction.
Stone & Webster Engineering Corporation initiated a stop work on ITT Grinnell activities. Work was restarted as each planner' was reviewed and released by Stone & Webster Engineering Corporation.
This matter is still under investigation. A final report will be submitted by January 31, 1983.