Interim Deficiency Rept 82-002 Re Fan Belt Problems During Initial Startup of Diesel Generator.Initially Reported on 820210.Final Rept Will Be Submitted by 830208 Instead of 830120,per
ML20064K427
Person / Time
Site: Saint Lucie NextEra Energy icon.png
Issue date: 01/11/1983
From: Robert E. Uhrig
FLORIDA POWER & LIGHT CO.
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
10CFR-050.55E, 10CFR-50.55E, 82-002, 82-2, L-83-14, NUDOCS 8301180396
Download: ML20064K427 (1)


Text

'

l P. O. BOX 140CD, JUNO BEACH, FL 33408 FLORIDA POWER & LIGHT COMPANY January 11, '583 L-83-14 tz Mr. James P. O'Reilly m

Regional Administrator, Region II V. S. Nuclear Regulatory Commission 101 Marietta Street, Suite 300 Atlanta, Georgia 30303 Re:

St. Lucie Unit 2 Docket No. 50-389, 10 CFR 50.55(e),82-002 Fan Belt Problems Durino Initial Start-Up of Diesel Generator

Dear Mr. O'Reilly:

On February 10, 1982, Florida Power and Light Company (FPL) notified the Region II Office of Inspection and Enforcement, in accordance with the requirements of 10 CFR 50.55(e), of a potential deficiency regarding the fan belts on diesel generators 2A and 2B. An' interim report submitted to you on November 24,1982 (L-82-517) stated that a final report would be submitted by January 20, 1983. We are still working on this problem and expect to submit a final report by February 8,1983.

Very truly yours, Robert E. Uhrig Vice President Advanced Systems & Technology REU/JO/ cab cc:

Director of Inspection and Enforcement U. S. Nuclear Regulatory Commission Washington, D.C. 20555 l