Requests Addl Time to Submit Final Deficiency Rept DER 82-9 Re Thermowells in Diesel Generator Lube Oil Sys by Cooper Energy Not Procured to ASME Code.Initially Reported on 820316.Info Should Be Finalized by 821116
ML20063N797
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 09/15/1982
From: Van Brunt E
ARIZONA PUBLIC SERVICE CO. (FORMERLY ARIZONA NUCLEAR
To: Sternberg D
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
References
10CFR-050.55E, 10CFR-50.55E, ANPP-21834-GHD, DER-82-9, NUDOCS 8210070229
Download: ML20063N797 (2)


Text

'

Docket Nos. 50-528/529/530

\\

v

~

E..

50.55(o) Report FTi';'O JDD31Zii@ESA IPURYt4t@ EcuardfE@lF2 @@ N 3003 STA.

p.o. sox misse -

PH'oENIX, ARI2oNA 85036 September 15, 1982 ANPP-21834-GHD/BSK U. S. Nuclear Regulatory Commission Region V Creekside Oaks Office Park 1450 Maria Lane - Suite 210 Walnut Creek, California 94596-5368 Attention:

Mr. D. M. Sternberg, Chief Reactor Projects Brant'a 1

Subject:

Time Extension for Report - DER 82-9 A 50.55(e) Potentially Reportable Deficiency Relating to Thermowells In Diesel Generator Lube Oil Systems by Cooper Energy Were Not Procured to ASME Code.

File: 82-019-026 4.33.2

Reference:

(A) Telephone Conversation between T. Bishop and G. Duckworth on March 16, 1982 (B) ANPP-20715, dated April 16,1982 (Interim Report)

(C) ANPP-21183, dated June 15, 1982.(Time Extension)

Dear Sir:

The NRC was notified of a potentially reportable deficiency in Reference (A), an Interim Report was transmitted by Reference (B), and a time extension was requested by Reference (C). At that time, it was estimated that a Final Report would be available by September 16, 1982.

Due to the extensive investigation and evaluation required, it is now expected that this information will be finalized by November 16, 1982, when a complete report will be submitted.

There is no new information or change to the Interim Report at this time.

Very truly yours, T

E.

cuA nut E. E. Van Brunt, Jr.

APS Vice President Nuclear Projects Management ANPP Project Director EEVBJr/GHD:db cc: See Attached Page 2 (F

'8210070229 820915

')

IcPDR ADOCK 05000528 i

OL.

.PDR

o

. p.-

U. S. Nuclear Regulatory Commission September 15, 1982 Attention:

Mr. D. M. Sternberg, Chief ANPP-21834-CHD/BSK Page 2 cc: Richard DeYoung, Director Office of Inspection ar.d Enforcement U. S. Nuclear Regulatory Commission Washington, D. C. 20555 T. G. Woods, Jr.

J. A. Roedel D. B. Fasnacht G. C. Andognini A. C. Rogers B. S. Kaplan W. E. Ide J. Vorees J. A. Brand A. C. Gehr W. J. Stubblefield W. G. Bingham R. L. Patterson R. W. Welcher R. M. Grant D. R. Hawkinson L. E. Vorderbrueggen G. A. Fiorelli Lynne Bernabei, Esq.

Harmon & Weiss 1725 "1" Street, NW Suite 506 Washington, D. C. 20006 i

i R. L. Greenfield I

Assistant Attorney General Bataan Memorial Building Santa Fe,.New Mexico 87503 I

l

- _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ - - _ _ _ _