Informs That All Actions Requested by NRC Bulletin 88-011 Complete,Per Receipt of Final Documentation of CEOG Task 696 on 931202.Stress & Fatigue Analyses Reviewed & Updated to Ensure Compliance W/Applicable Code Requirement
ML20063D654
Person / Time
Site: Calvert Cliffs  Constellation icon.png
Issue date: 01/31/1994
From: Denton R
BALTIMORE GAS & ELECTRIC CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
IEB-88-011, IEB-88-11, TAC-M72119, TAC-M72120, NUDOCS 9402080248
Download: ML20063D654 (3)


Text

'$

BALTIMORE GAS AND i

LECTRIC 1650 cal. VERT CLIFFS PARKWAY. LUSBY, MARYLAND 20657-4702 RODERT E. DENTON vice Pacsiorwt Nuctr Aa carnor January 31,1994 (deu) 760-4465 l

l' U. S. Nuclear Regulatory Commission Washington,DC 20555 ATTENTION:

Document Control Desk

SUBJECT:

Calvert Cliffs Nuclear Power Plant Unit Nos.1 & 2: Docket Nos. 50-317 & 50-318 Final Response to Safety Evaluation For Combustion Engineering Owners Group Report CEN-387-P, Revision 1, " Pressurizer Surge Line Thermal Stratification Evaluation," NRC Bulletin 88-11 (TAC Nos. M72119 -

and M72120)

REFERENCES:

(a)

Pressurizer Surge Line Thermal Stratification (NRC Bulletin 88-11),

dated December 20,1988 (b)

Letter from Mr. D. G. Mcdonald (NRC) to' Mr. G. C. Creel (BG&E), dated July 12,1993, Safety Evaluation For Combustion Engineering Owners Group Report CEN 387 P, Revision 1,

" Pressurizer Surge Line Thermal Stratification Evaluation," (Bulletin 88-11), Calvert Cliffs Nuclear Power Plant, Units 1 & 2 (TAC Nos. 72119; 72120)

(c)

Lete from Mr. R. E. Denton (BG&E) to NRC Document Control Desk, dated September 14,1993, Response to Safety Evaluation For Combustion Engineering Owners Group Report CEN-387-P, Revision 1,

" Pressurizer Surge Line Thermal Stratification Evaluation," NRC Bulletin 88-11 (TAC Nos. M72119; M72120)

Nuclear Regulatory Commission Bulletin 88-11 (Reference a) requested that we establish and implement a program to confirm pressurizer surge line integrity in view of thermal stratification issues. Action 1.d of the bulletin required us to update our stress and fatigue analyses to ensure l

compliance with applicable Code requirements. Reference (b) requested that we "... confirm that all actions requested by the Bulletin 88-11, including the updating of the plant-specific stress and fatigue analyses required by Action 1.d, have been completed." As Reference (c) states,we could not confirm completion of Action 1.d until we received final documentation of Combustion Engineering Owners Group (CEOG) Task 6%," Surge Line Design Report Addenda."

G,% li{f Y*,,$

I '-)

[

1 e c. -

f

/

9402000248 940131 I

PDR ADDCK 05000317 t

D PDR

i Document Control Desk

~ ~

i January 31,1994 Page 2 -

[

We received final documentation of CEOG Task 696 on December 2,1993. We have reviewed and updated our stress and fatigue analyses to ensure compliance with applicable Code requirements. All of the actions requested by Bulletin 88-11 are complete. Attachment (1) lists all documents related to Bulletin 88-11.

Should you have any further questions regarding this matter, we will be pleased to discuss them with you.

Very truly yours,

?

g RED /JMO/ dim l

Attachment:

As Stated cc:

D. A. Brune, Esquire J. E. Silberg, Esquire R. A. Capra, NRC D. G. Mcdonald, Jr., NRC T. T. Martin, NRC P. R. Wilson, NRC R. I. Meixan, DNR J. II. Walter, PSC i

i f

.I I

i r

6 er l

,.I' ATTACIIMENT (1)

LIST OF DOCUMENTS RELATED TO NRC BULLETIN 88-11 (a)

Pressurizer Surge Line Hermal Stratification (NRC Bulletin 88-11), dated December 20,1988 (b)

Letter from Mr. D. G. Mcdonald (NRC) to Mr. G. C. Creel (BG&E), dated July 12,1993, Safety Evaluation For Combustion Engineering Owners Group Report CEN-387-P, Revision 1, " Pressurizer Surge Line Thermal Stratification Evaluation," (Bulletin 88-11),

Calvert Cliffs Nuclear Power Plant, Units 1 & 2 (TAC Nos. 72119; 72120)

(c)

Letter from Mr. R. E. Denton (BG&E) to NRC Document Control Desk, dated September 14,1993, Response to Safety Evaluation For Combustion Engineering Owners Group Report CEN-387-P, Revision 1, " Pressurizer Surge Line Thermal Stratification Evaluation," NRC Bulletin 88-11 (TAC Nos. M72119; M72120) i (d) letter from Mr. G. C. Creel (BG&E) to NRC Document Control Desk, dated March 3,1989, NRC Bulletin 88-11, Pressurizer Surge Line Thermal Stratification (c)

Ixtter from Mr. G. C. Creel (BG&E) to NRC Document Control Desk, dated June 6,1989,

~,

NRC Bulletin 88-11, Pressurizer Surge Line Thermal Stratification (f)

Ixtter from Mr. G. C. Creel (BG&E) to NRC Document Control Desk, dated July 31,1989, f'

NRC Bulletin 88-11, Pressurizer Surge Line Thermal Stratification (g)

Letter from Mr D. G. Mcdonald (NRC) to Mr. G. C. Creel (BG&E), dated July 18,1990, NRC Bulletia 9%11, " Pressurizer Surge Line Thermal Stratification" Evaluation of Combustion

-ineering Owners Group Bounding Analysis Relating to Calvert Cliffs, Units 1 & 2, ('iaC Nos. 72119; 72120) r (i)

Letter from Mr. D. G. Mcdonald (NRC) to Mr. G. C. Creel (BG&E), dated August 14,1991, Pressurizer Surge Line Thermal Stratification,.Bulletin 88-11, Calvert Cliffs t

Nuclear Power Plant, Units 1 & 2 (TAC Nos. 72119;72120)

(j)

Ixtter from Mr. D. G. Mcdonald (NRC) to Mr. G. C. Creel (BG&E), dated September 9,1991, Pressurizer Surge Line Hermal Stratification,Bulletin 88-11, Calvert Cliffs Nuclear Power Plant, Units 1 & 2 (TAC Nos. 72119; 72120)

(k)

Letter from Mr. G. C. Creel (BG&E) to NRC Document Control Desk, dated December 24,1991, Pressurizer Surge Line Thermal Stratification,Bulletin 88-11 Calvert Cliffs Units 1 & 2 (TAC Nos. M72119; M72120)

I