Responds to NRC Re Violations Noted in IE Insp Rept 50-285/81-30.Corrective Actions:Standing Order G-22, Storage of Critical Quality Elements, Revised to Incorporate Tagging Program
ML20062L815
Person / Time
Site: Fort Calhoun 
Issue date: 06/01/1982
From: William Jones
OMAHA PUBLIC POWER DISTRICT
To: Seidle W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
Shared Package
ML20062L769 List:
References
LIC-82-225, NUDOCS 8208190264
Download: ML20062L815 (1)


Text

.

Omaha Public Power District 1623 HARNEY S OMAHA. NEBRASKA 68102 m TELEPHONE 536 4000 AREA CODE 402 June 1, 1982 LIC-82-225 T (@g j\\W!- 7

>,. a 3 m y,

Mr. W. C. Seidle, Chief Reactor Project Branch 3 j

U. S. Nuclear Regulatory Commission Region IV 611 Ryan Plaza Drive, Suite 1000 Arlington, Texas 76011

Reference:

Docket No. 50-285 IE Inspection Report 81-30

Dear Mr. Seidle:

Fort Calhoun Station CQE Material Tagging Program The Omaha Public Power District's letter, dated February 10, 1982, provided the District's response to Violation 2 of the subject Inspection Report. The District stated in this response that a CQE material tag-ging program would be initiated to appropriately identify and control this material from storeroom issuance to installation and that Admini-strative Standing Order (S.O. ) G-25, " Stores Control", would be revised to incorporate this tagging program by June 1, 1982.

The purpose of this letter is te inform the Commission that the District has commenced implementation of the subject tagging program, but that S.0. G-22,

" Storage of Critical Quality Elements", has been revised to address and provide instruction regarding the Fort Calhoun Station tagging program.

S.0. G-22, instead of S.0. G-25, was revised because during the final in-depth review of the implementation objectives of the Fort Calhoun Station tagging program, the District determined that the program instruction would be more appropriate in S.O. G-22.

The District believes the intent of our response has been fulfilled and that neither the objectives nor effectiveness of the Fort Calhoun Station COE material tagging program have been compromised by this deviation.

Sincsrely, I k(L. L ). '

q jj p W. C. Jones Division Manager Production Operations cc:

LeBoeuf, Lamb, Leiby & MacRae 1333 New Hampshire Avenue, N.W.

Washington, D.C.

20036 8208190264 820813 PDR ADOCK 05000285 G