ML20062G471

From kanterella
Jump to navigation Jump to search
Forwards IE Inspec Rept 50-344/78-24 on 781003 & 781101-03 During Which No Items of Noncompliance Were Noted
ML20062G471
Person / Time
Site: Trojan File:Portland General Electric icon.png
Issue date: 11/22/1978
From: Crews J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To: Goodwin C
PORTLAND GENERAL ELECTRIC CO.
Shared Package
ML20062G474 List:
References
NUDOCS 7812280355
Download: ML20062G471 (2)


See also: IR 05000344/1978024

Text

-

.

,,. . - - _ _

-

-.

_

,

.

,

' ' ' ' '

-~~- . -

.

-

-

-

.. _. .

. . . . ,

_ .,

~

, c/

't,

UNITED STATES

.

$

NUCLEAR REGULATORY COMM!sSION

[.d .

f_

REGION V

,

%

'

SUITE 202, W ALNUT CREEK PLAZ A

,

k '%#

o

1990 N. CALIFORNIA BOULEVARD

'

  • +,e*-

WALNUT CREEK, CALIFORNI A 94$$$

NOV 22 378

Q

Docket No. 50-344

i

Portland General Electric Company .

121 S. W. Salmon Street

Portland, Oregon 97204

Attention: Mr. Charles Goodwin, Jr.

,

i

Assistant Vice President

!

i

Gentlemen:

'

l

Subject: NRC Inspection of Trojan Nuclear Plant

This refers to the inspection conducted by Mr. P. J. Morrill and other

'

IE inspectors of this office on October 3, and November 1-3, 1978 of

,

activities authorized by NRC License No. NPF-1, .and to the discussion of.

l

our findings held by Mr. Morrill with Mr. S. Christensen on October 3.

i

4

1978, Mr. F. Lamoureaux on November 3,1978 and other members of your

l

staff at the conclusion of the inspection.

Areas examined during this inspection are described in the enclosed

inspection report. Within these areas, the inspection consisted of

selective examinations of procedures and representative records, inter-

views with personnel, and observations by the inspectors.

No items of noncompliance with NRC requirements were identified within

.

the scope of this inspection.

!

In accordance with Section 2.790 of the NRC's " Rules of Practice,"

i

Part 2, Title 10, Code of Federal Regulations, a copy of this letter and

the enclosed inspection report will be placed in the NRC's Public

'

Document Room.

If this report contains any information that you believe

to be proprietary, it is necessary that you submit a written application

to this office, within 20 days of the date of this letter, requesting

'

that such information be withheld from public disclosure. The applica-

!

tion must include a full statement of the reasons why it is claimed that

the information is proprietary. The application should be prepared so

i

!

l

7812280 355

(p

.

c,

y-

,-v-

-e.yw

ww-ww

w

-1

r

W-----t---r

-

-

= * -

---"i*-'-'"-

F

,

\\

-

.

'

'

NOV 2 2 t]78

,

Portland General Electric Company

-2-

!.

-

i

that any proprietary information identified is contained in an enclosure

'

to the application, since the application without the enclosure will

-

also be placed in the Public Document Room.

If we do not hear from you

,

,

in this regard within the specified period, the report will be placed in

the Public Document Room.

Should you have any questions concerning this inspection, we will be

glad to discuss them with you.

Sincerely,

,

_

"

J. L. Crews, Chief

Reactor Operations and Nuclear

Support Branch

.

-

Enclosure:

)

IE Inspection Report

No. 50-344/78-24

.

a

,

cc w/o enclosure:

B. Withers, PGE

F. C. Gaidos, PGE

1,