Forwards IE Inspec Rept 50-247/78-30 on 780913-14 During Which No Items of Noncompliance Were Noted
ML20062D814
Person / Time
Site: Indian Point Entergy icon.png
Issue date: 10/19/1978
From: Brunner E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: William Cahill
CONSOLIDATED EDISON CO. OF NEW YORK, INC.
Shared Package
ML20062D819 List:
References
NUDOCS 7811300337
Download: ML20062D814 (2)


See also: IR 05000247/1978030

Text

^

.

-

l

  • -

.  :

.__ . . - . _ .

- -

O-2 N [

gf?%

., q #*,

. UNITED STATES

NUCLEAR REGULATORY COMMiss!ON

y ( ) e (, l S REclON I

W s sai PAnx AvcNur

! '/ c;# [e KING OF PRUSSI A. PENNSYL.VANI A iS406

O,%, TAWj

.....

'

Docket No. 50-247 $ 19 OCT 1978

1

Consolidated Edison Company of

New York, Inc.

A~TN: Mr. W. J. Cahill, Jr.

Vice President

4 Irving Place .

New York, New York 10003

Gentlemen:

Subject: Inspection 50-247/78-30

This refers to the inspection conducted by Mr. T. Rebelowski of this

office on September 13 74, 1978 at the Consolidated Edison Company

Corporate Offices, New York City of activities authorized oy NRC

License No. DPR-26 and to the discussions of our findin,ts held by

Mr. Rebelowski with Mr. C. Jackson of your staff at the conclusion of  :

the inspection. '

Areas examined during this inspection are described in the Office of

Inspection and Enforcement Inspection Report which is enclosed with this

letter. Within these areas, the inspection consisted of selective

examinations of procedures and representative records, interviews with  :

personnel, and observations by the inspector. '

Within the scope of this inspection, no items of noncompliance were

observed.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part

2, Title 10, Code of Federal Regulations, a copy of this letter and the

enclosed inspection report will be placed in the NRC's Public Document

Room. If this report contains any information that you (or your con-

tractor) believe to be proprietary, it is necessary that you make a

written application within 20 days to this office to withhold such

information from public disclosure. Any such application must be ,

accompanied by an affidavit executed by the owner of the information,

which identifies the document or part sought to be withheld, and which '

contains a statement of reasons which addresses with specificity the

items which will be considered by the Commission as listed in subpara-

graph (b) (4) of Section 2.790. The information sought to be withheld

shall be incorporated as far as possible into a separate part of the

affidavit. If we do not hear from you in this regard within the speci-  ;

fied period, the report will be placed in the Public Document Room.

i

?S1130tS~

-

_

-

.

,

. - . - . _ - - - .. .. .

. ..

.

Consolidated Edison Company of New York

2 1 S OCT 1978

No reply to this letter is required; however, if you should have any

questions concerning this inspection, we will be pleased to discuss them

with you.

Sincerely,

'

.

Eldon ' . runner, ie-

Reactor Operations an iuclear

Support Branch

Enclosure: Office of Inspection and Enforcement Inspection '

Report Number 50-247/78-30

cc d/ encl:

L. O. Brooks, Project Manager, IP Nuclear

W. Monti, Manager - Nuclear Power Generation Department

T. Law, Plant Manager

J. M. Makepeace, Director, Technical Engineering

J. W. Kilduff, Assistant to Resident Manager

J. D. Block. Esquire, Executive Vice President - Administration