Text
^
.
-
-
.
.__
. . - . _ .
O-2 N [
-
-
gf?%
UNITED STATES
.
NUCLEAR REGULATORY COMMiss!ON
., q
,
y ( ) e (, l S
REclON I
- W
'/ c; [e
s
sai PAnx AvcNur
O,%, TAWj
!
KING OF PRUSSI A. PENNSYL.VANI A iS406
.....
Docket No. 50-247 $
19 OCT 1978
'
1
Consolidated Edison Company of
New York, Inc.
A~TN: Mr. W. J. Cahill, Jr.
Vice President
4 Irving Place
10003
.
Gentlemen:
Subject:
Inspection 50-247/78-30
This refers to the inspection conducted by Mr. T. Rebelowski of this
office on September 13 74, 1978 at the Consolidated Edison Company
Corporate Offices, New York City of activities authorized oy NRC
License No. DPR-26 and to the discussions of our findin,ts held by
Mr. Rebelowski with Mr. C. Jackson of your staff at the conclusion of
'
the inspection.
Areas examined during this inspection are described in the Office of
Inspection and Enforcement Inspection Report which is enclosed with this
letter. Within these areas, the inspection consisted of selective
examinations of procedures and representative records, interviews with
'
personnel, and observations by the inspector.
Within the scope of this inspection, no items of noncompliance were
observed.
In accordance with Section 2.790 of the NRC's " Rules of Practice," Part
2, Title 10, Code of Federal Regulations, a copy of this letter and the
enclosed inspection report will be placed in the NRC's Public Document
Room.
If this report contains any information that you (or your con-
tractor) believe to be proprietary, it is necessary that you make a
written application within 20 days to this office to withhold such
information from public disclosure. Any such application must be
,
accompanied by an affidavit executed by the owner of the information,
which identifies the document or part sought to be withheld, and which
'
contains a statement of reasons which addresses with specificity the
items which will be considered by the Commission as listed in subpara-
graph (b) (4) of Section 2.790. The information sought to be withheld
shall be incorporated as far as possible into a separate part of the
If we do not hear from you in this regard within the speci-
fied period, the report will be placed in the Public Document Room.
i
?S1130tS~
-
_
.
-
,
.
- . - . _ - - -
.. ..
.
.
..
.
Consolidated Edison Company of New York
2
1 S OCT 1978
No reply to this letter is required; however, if you should have any
questions concerning this inspection, we will be pleased to discuss them
with you.
Sincerely,
'
.
Eldon ' .
runner,
ie-
Reactor Operations an iuclear
Support Branch
Enclosure: Office of Inspection and Enforcement Inspection
'
Report Number 50-247/78-30
cc d/ encl:
L. O. Brooks, Project Manager, IP Nuclear
W. Monti, Manager - Nuclear Power Generation Department
T. Law, Plant Manager
J. M. Makepeace, Director, Technical Engineering
J. W. Kilduff, Assistant to Resident Manager
J. D. Block. Esquire, Executive Vice President - Administration
E. J. Sack, Esquire
A. Z. Roisman, Natural Resources Defense Council (Without Report)
.
-
.
l
l
.
_