Forwards IE Inspec Repts 50-341/78-14 on 780907-08 & Notice of Violation
ML20062C427
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 09/20/1978
From: Heishman R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Hines E
DETROIT EDISON CO.
Shared Package
ML20062C428 List:
References
NUDOCS 7811090004
Download: ML20062C427 (2)


See also: IR 05000341/1978014

Text

~

.

.

PDR

,

_

UNITEo STATES

pe nsoug

NUCLEAR REGULATORY COMMISSION

g

,,

[

, REGloN HI

o

799 nod 5EVELT ROAD

7e

'

'

'

4

GLEN ELLYN, ILLINOl5 40337

e

4., .

,-

-

,

..

....

_,;

SEP 2 01978~

Docket No. 50-341

The Detroit Edison Company

ATTN:

Mr. Edward Hines

Assistant Vice President

and Manager Quality

Assurance

2000 Second Avenue

Detroit, MI

48226

Gentlemen:

This refers to the inspektion conducted by Mr. I. T. Yin of this office

(

at the Enrico Fermi 2 site on September 7-8, 1978, of activities

authorized by NRC Construction Permit No. CPPR-87 and to the discussion

of our findings with Mr. T. A. Alessi and others of your staff at

the conclusion of the inspection.

The enclosed copy of our inspection report identifies creas examined

during the inspection. Within these areas, the inspection consisted

of a selective examination of procedures and representative records,

observations, and interviews with personnel.

During this inspection, certain of your activities appeared to be in

noncompliance with NRC requirements, as described in the enclosed

Appendix A.

This notice is sent to you pursuant to the provisions of Section 2.201

l

of the NRC's " Rules of Practice," Part 2, Title 10, Code of Federal

l

Regulations. Section 2.201 requires you to submit to this office

within thirty days of your receipt of this notice a written

statement or explanation in reply, including for each item of non-

I

compliance:

(1) corrective action taken and the results achieved;

(2) corrective action to be taken to avoid further noncompliance; and

(3) the date when full compliance will be achieved.

In accordance with Section 2.790 of the NRC's " Rules of Practice,"

Part 2, Title 10, Code of Federal Regulations, a copy of this letter,

the enclosures, and your response to this letter will be placed in

the NRC's Public Document Room, except as follows.

If the enclosures

78T' 09 oo *N

Q

.

-

'

.

,

,

.

The Detroit Edison

-2-

SEPTOI97f

Company

contain information that you or your contractors believe to be

proprietary, you must apply in writing to this office, within twenty

days of your receipt of this letter, to withhold such information

from public disclosure. The application must include a full statement

of the reasons for which the information is considered proprietary,

and should be prepared so that proprietary information identified in

the application is contained in an enclosure to the application.

We will gladly discuss any questions you have concerning this

inspection.

Sincerely,

(

1B

. F. Beishman, Chief

Reactor Construction and

Engineering Support Branch

Enclosures:

1.

Appendix A, Notice

of Violation

2.

IE Inspection Report

No. 50-341/78-14

cc w/encls:

Central Files

Reproduction Unit NRC 20b

AR

(

Local PDR

NSIC

r

TIC

Ronald Callen, Michigan Public

Service Commission

Eugene B. Thomas, Attorney

I

i

?

l

l

'

__

._

_ _ _ - -

-