y November 9, 1993 4
Docket No. 50-483 DISTRIBUTION Docket File NRC & Local PDRs JRoe PDIII-3 Reading Mr. Donald F. Schnell JZwolinski DMcDonald Senior Vice President - Nuclear JHannon EGreenman, RIII Union Electric Company MRushbrook LRWharton Post Office Box 149 ACRS(10) i St. Louis, Missouri 63166 OGC
Dear Mr. Schnell:
SUBJECT:
CALLAWAY NUCLEAR PLANT - RESPONSE TO NRC BULLETIN 89-01, SUPPLEMENT
- 2. " FAILURE OF WESTINGHOUSE STEAM GENERATOR TUBE MECHANICAL PLUGS" (TAC NO. M81598)
On June 28, 1991, NRC Bulletin 89-01, Supplemer.t 2, was issued to all holders '
I of operating licenses or construction permits for pressurized water reactors (PWRs). The bulletin requested that actions similar to those requested in NRC Bulletin 89-01, " Failure of Westinghouse Steam Generator Tube Mechanical Plugs," be extended to include all Westinghouse mechanical plugs fabricated from thermally treated Inconel 600. These actions were necessary to. ensure i
that these plugs would continue to provide adequate assurance for reactor coolant system (RCS) pressure boundary integrity under normal operating, transient and postulated accident conditions.
By letter dated July 24, 1991, you responded to Bulletin 89-01, Supplement 2, by providing the information addressed in the Actions Requested portion of that document. We have reviewed your response for Callaway and find the information and planned / accomplished actions to be acceptable. Therefore, we are closing out TAC No. M81598.
Sincerely, Original Signed By:
L. Raynard Wharton, Project Manager Project Directorate III-3 Division of Reactor Projects - III/IV/V Office of Nuclear Reactor Regulation cc: See next page
{
OFFICE PD373:lN PD3-3:PH PD3hPb NAME MRuIhbk hRWharton:sw JHannon DATE
\\\\ /9/93 Ni/9 /93
// /h/93 OfflCIAL RECORD
'Dodjment Name: G:\\CALLAWAY\\ CAL 81598.BU 9311180090 931109 Mh PDR ADOCK 05000483 P
ppg fD\\
b
^
a n:
r O
E UNITED STATES 5
NUCLEAR REGULATORY COMMISSION
-1 kg wasuiwoTow, o.c. ossimoo$
Docket No. 50-483 November 9, 1993 Mr. Donald F. Schnell Senior Vice President - Nuclear Union Electric Company Post Office Box 149 St. Louis, Missouri 63166
Dear Mr. Schnell:
SUBJECT:
CALLAWAY NUCLEAR PLANT - RESPONSE TO NRC BULLETIN 89-01, SUPPLEMENT 2, " FAILURE OF WESTINGHOUSE STEAM GENERATOR TUBE MECHANICAL PLUGS" (TAC NO. M81598)
On June 28, 1991, NRC Bulletin 89-01, Supplement 2, was issued to all holders of operating licenses or construction permits for pressurized water reactors (PWRs). The bulletin requested that actions similar to those requested in NRC Bulletin 89-01, " Failure of Westinghouse Steam Generator Tube Mechanical Plugs," be extended to include all Westinghouse mechanical plugs fabricated from thermally treated Inconel 600. These actions were necessary to ensure that these plugs would continue to provide adequate assurance for reactor coolant system (RCS) pressure boundary integrity under normal operating, transient and postulated accident conditions.
By letter dated July 24, 1991, you responded to Bulletin 89-01, Supplement 2, by providing the information addressed in the Actions Requested portion of that document. We have reviewed your response for Callaway and find the information and planned / accomplished actions to be acceptable. Therefore, we are closing out TAC No. M81598.
Sincerely, 92 twas 63 L.Rayn$rdWharton,ProjectManager Project Directorate III-3 Division of Reactor Projects - III/IV/V Office of Nuclear Reactor Regulation cc: See next page
e i
[:
Mr. D. F. Schnell Union Electric Company Callaway Plant Unit No. 1 CC:
Cermark fletcher Associates Mr. Dan I. Bolef, President 18225 Flower Hill Way fA Kay Drey, Representative Gaithersburg, Maryland 20879-5334 Board of Directors Coalition Mr. S. E. Sampson for the Environment Supervising Engineer, 6267 Delmar Bopulevard Site Licensing University City, Missouri 65130 Union Electric Company Post Office Box 620 Fulton, Missouri 65251 U.S. Nuclear Regulatory Commission Resident Inspectors Office RR #1 Steedman, Missouri 65077 Mr. Alan C. Passwater, Manager Licensing and Fuels Union Electric Company Post Office Box 360 Jefferson City, Missouri 65102 1
Regional Administrator U.S. NRC, Region III 799 Roosevelt Road Glen Ellyn, Illinois 60137 t
Mr. Ronald A. Kucera Deputy Director Department of Natural Resources P. O. Box 176 Jefferson City, Missouri 65102 Mr. Bart D. Withers President and Chief Executive Officer Wolf Creek Nuclear Operating Corporation P. O. Box 411 Burlington, Kansas 66B39 1