Text
..-
ga pm reg g
$ +,
UNITED STATES j.) g_;f j
NUCLEAR REGULATORY COMMISSION f
WASHtNGTON, D.C. 205554K01
,%]***
Novenber 18, 1993 Docket No. 50-285 Mr. Terry. L. Patterson Division Manager - Nuclear Operations Omaha Public Power District Fort Calhoun Station FC-2-4 Adm.
[
Post Office Box 399 Hwy. 75 - North of Fort Calhoun Fort Calhoun, Nebraska 68023-0399
Dear Mr. Patterson:
SUBJECT:
EVALUATION OF THE SECOND 10-YEAR INTERVAL INSPECTION REQUEST FOR RELIEF FOR FORT CALHOUN STATION (TAC NO. M84816)
The staff, with technical assistance from its contractor, the Idaho National Engineering Laboratory (INEL), has reviewed and evaluated the information provided by Omaha Public Power District in its letter dated October 16, 1992, related to its alternative to the ASME Boiler and Pressure Yessel Code (the Code),Section XI concerning the regenerative heat exchanger (RHX) nozzle weld inspections for the Fort Calhoun Station inservice inspection (ISI) program.
Based on the information submitted, the staff agrees with the Contractor's conclusions and recommendations presented in the Technical Evaluation Summary enclosed. The staff concludes that pursuant to 10 CFR 50.55a(a)(3)(ii), the licensee's proposed alternative may be used in that it provides an acceptable level of quality and safety and that compliance with the Code would result in hardship without a compensating increase in the level of quality or safety.
This relief is authorized on a one-time basis only, with the conditions that the licensee perform a volumetric examination of these nozzle-to-vessel welds (ISI #10 and #11) during the first refue ing outage of the third 10-year inspection interval and that the licensee perform all additional RHX nozzle weld examinations on a schedule consistent with ASME Section XI.
In addition, for the third 10-year interval the staff will consider granting the licensee's request for relief (if submitted by the licensee) from Code requirement to volumetrically examine the nozzle inner radius sections. The JJag gg gg 24 m a 9312O20558 931118 PDR ADOCK 05000285 i
G PDR hel e
g s
1
.g
..g,
t i
Mr. Terry L. Patterson,
enclosed Safety Evaluation provides the results of the staff's review of the licensee's proposed alternative examination.
If you have any questions, please contact me at 301-504-1313.
Sincerely,
'a
/
27 William D.
ckner, Director Project Directorate IV-1 Division of Reactor Projects - III/IV/V Office of Nuclear Reactor Regulation
Enclosures:
l.
Safety Evaluation 2.
Technical Evaluation Summary cc w/ enclosures:
See next page 6
i b
r P
6 l
L
(
Mr. Terry L. Patterson t enclosed Safety Evaluation provides the results of the staff's review of the I
licensee's proposed alternative examination.
If you have any questions, please contact me at 301-504-1313.
Sincerely, ORIGINAL SIGNED BY:
D. Wigginton for William D. Beckner, Director Project Directorate IV-1 Division of Reactor Projects - III/IV/V Office of Nuclear Reactor Regulation
Enclosures:
1.
Safety Evaluation 2.
Technical Evaluation Summary cc w/ enclosures:
See next page DISTRIBUTION:
Docket.' File NRC & Local PDRs PD4-1 Reading T. Murley/F. Miraglia L. J. Callan E. Rossi J. Lieberman J. Roe E. Adensam W. Beckner P. Noonan S. Bloom T. McLellan i
OGC E. Jordan G. Hill (2)
ACRS (10)
OPA OC/LFDCB J. Mitchell, EDO A. B. Beach, RIV
- See previous concurrence OFC LA:PD4-TV4 PM:PD4-1 OGC
- D:Pkti,f NAME PNoonan)I SBloom:pk EHoller WBeNerM DATE O /l/ /93
/ /93 11/12/93
\\(/lff/93 COPY
?3Y/N0 YES/NO YES/NO YES/NO OFFICIAL RECORD COPY Document Name:
FC84816.REL-
i Mr. Terry L. Patterson Omaha Public Power District Fort Calhoun Station, Unit 1 CC:
Mr. Michael F. McBride, Esq.
LeBoeuf, Lamb, Leiby & MacRae 1875 Connecticut Avenue, NW Washington, D.C.
20009-5728 Mr. Jack Jensen, Chairman Washirigton County Board of Supervisors l
Blair, Nebraska 68008 Mr. Raymond P. Mullikin, Resident Inspector U.S. Nuclear Regulatory Commission Post Office Box 309 Fort Calhoun, Nebraska 68023 Mr. Charles B. Brinkman, Manager Washington Nuclear Operations Combustion Engineering, Inc.
12300 Twinbrook Parkway, Suite 330 Rockville, MD 20852 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 1000 Arlington, Texas 76011 Harold Borchert, Director Division of Radiological Health 5
Nebraska Department of Health 301 Centennial Mall, South Post Office Box 95007 i
Lincoln, Nebraska 68509 Mr. James W. Chase, Manager Fort Calhoun Station Post Office Box 399 Fort Calhoun, Nebraska 68023 i
4
.-