Rev 3 to Monthly Operating Rept for May 1993 for Cpses,Unit 2
ML20057A963
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 05/31/1993
From: Julie Hughes
TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
To:
Shared Package
ML20057A961 List:
References
NUDOCS 9309160289
Download: ML20057A963 (2)


Text

.

~

' Attachment to TXX-93324 Page 10. of 13 COMANCHE PEAK STEAM ELECTRIC STATION, UNIT 2 NRC MONTHLY OPERATING REPORT-REV.3 DOCKET NO:

50 446 UNIT:

CPSES 2 DATE:

September 10,1993 COMPLETED BY:

Janet Hughes TELEPHONE 817-897-5331 OPERATING STATUS 1.

Reporting Period: MAY 1993 Gross hours in reporting period:

ZM 2.

Currently authorized power level (MWt):

3:111 Max. depend. capacity (MWe-Net): 1150

  • Design Electrical Rating (MWe-Net):

1MQ 3.

Power level to which restricted (if any) (MWe-Net):

E 4.

Reasons for restriction (if any):

THIS MONTH YRTO DATE CUMULATIVE 5.

Number of hours reactor was critical 326 834 834 6.

Reactor reserve shutdown hours 418 418 418 7.

Hours generator on line 279 787 U

8.

Unit reserve shutdown hours 0

0 0

9.

Gross thermal energy generated (MWH) 499.853 1,165.087 1,165.087 10.

Gross electrical energy generated (MWH) 152.610 320.680 320.680 11.

Net electrical energy generated (MWH) 129,268 268,787 268,787 12.

Reactor Service factor NA NA NA 13.

Reactor availability factor NA NA NA 14.

Unit service factor NA NA NA 15, Unit availability factor NA NA NA 16.

Unit capacity factor (Using MDC)

NA NA NA 17.

Unit capacity factor (Using Design MWe)

NA NA NA 18.

Unit forced outage rate NA NA NA 19.

Shutdowns scheduled over next 6 months (Type Date, and Duration of each):

20.

If shutdown at end of report period, estimated date of startup:

21.

Units in test status (prior to commercial operation):

FORECAST ACHIEVED Initial Criticality 930320 930324 Initial Electricity 930330 930409 Commercial Operation 930801 Estimated HAY 1993 REVISION 3 9309160289 930913 2

PDR ADOCK 05000445 W

R PDR Q

Attachment to TXX-91324 Page 11 of 13 UNIT SHUTDOWNS AND POWER REDUCTIONS REV.1 DOCKET NO:

2 446 UNIT:

CPSES 2 DATE:

September 10,1993 COAPLETED BY:

Janet Hughes REPORT MONTH MAY 1993 METHODOF TE SHUTTING DOWN Ff0RCED DURATION THEREACTOROR NO.

DATE SSCHEDUI FD (HOURS)

REASON REDUCING POWER CORRECTIVE ACTIONSCOAMENTS 4

930504 F

47.7 A

1 Loss of Feedwater flow to Steam Generator #1.

5 930506 S

27.5 8

1 Remote Shutdown Test.

6 930508 S

109.1 B

1 Loss of Offsite Power Test.

7 930520 F

97.9 A

3 Loss of Coolant Flow to Generator Stator.

8 930524 S

183 A

4 Feedwater isolation Valve slow closure.

Unit 2 was already in MODE 5.

MAY 1993 REVISION 3 1)

REASON

2) METFOD A: EOUiPMENT FAILURE (EXPLAIN)

E. OPERATORTRAINING ANDUCENSEEXAMINATION 1: MANUAL B: MAINTORTEST F: ADMINISTRATIVE 2: MANUALSCRAV.

C: RERJEUNG G: OPERATK)NALERROR(EXPLAIN) 3: AUTOMATIC 6 CRAM D: REGLIATORYRESTRICTKW H: OTHER (EXPLAIN) 4: OTHER {tiXPLAIN)

-