ML20057A173

From kanterella
Jump to navigation Jump to search
Insp Rept 50-255/93-05 on 930614-17 & 29,0701 & 20-21 & 0803-04.No Violations or Deviations Noted.Major Areas Inspected:Isi Activities Including Review of Program, Procedures & Observation of Work Activities
ML20057A173
Person / Time
Site: Palisades Entergy icon.png
Issue date: 09/07/1993
From: Jeffrey Jacobson, Schapker J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML18059A366 List:
References
50-255-93-05, 50-255-93-5, NUDOCS 9309130146
Download: ML20057A173 (5)


See also: IR 05000255/1993005

Text

.

.

.

i

I

,

I

t

!

U. S. NUCLEAR REGULATORY COMMISSION

f

REGION III

i

l

4,

!

Docket No.

50-255

i

'

!

Report No.

50-255/93005(DRS)

License No. DPR-20

I

j

Licensee: Consumers Power Company

212 West Michigan Avenue

Jackson, MI 49201

'

t

Facility Name: Palisades Huclear Plant

l

,

i

Inspection At: Covert, MI

-i

Inspection Dates: June 15-25, 1993 (Region 1)

June 14-17, and 29; July 1, 20-21, and August 3-4, 1993

!

i/7/[3

Inspector:

]

. F. Scha Wer, Reactor Inspector

Date '

'

k1

hgM

9

'? - 1.3

Approved , :[ ' .

j

j

/ Jrg'obson Chief

f

Date

,

j

teriah

i rocesses Section

'

Inspection Summary

l

t

ins.fection on June 14-17. and 29: Jul y 1. 20-21. and August 3-4

1993

!

(Region 111): June 15-25. 1993 (Region 1) (Report No. 50-255/93005(DRS))

Inspection Summary and Conclusions: Routine announced inspection of inservice

{

inspection (ISI) activities including review of program (73051), procedures

j

(73052). observation of work activities (73753), data review and evaluation

(73755), review of corrective action for previous inspection findings (92701),

j

review of erosion / corrosion program (49001), and independent examinations

performed by the NRC Mobile Laboratory of the main steam, containment spray,

i

'

safety injection, shutdown cooling, pressurizer relief, long term cooling,

'

containment air cooling, charging line, pressurizer spray and pressurizer

.

surge piping welds.

f

,

Results: Of the areas inspected, no violations or deviations were identified.

!

'

The NRC did not agree with the licensee's disposition of an indication in weld

PCS-4-PRS-lPl-2. The NRC determined, because of the results obtained by its

I

independent evaluation, that it was more appropriate to treat the indication

as a planar flaw. The licensee subjected this indication, utilizing

conservative dimensions, to analysis in order to determine the component was

!

,

l

acceptable.

In their correspondence dated July 20, 1993, they restated their

evaluation of the indication, a commitment to reevaluate the indication during

i

the next two outages and submitted an engineering evaluation that concludes

!

I

that the flaw will not propagate.

.

l

!

l

1

,

!

!

a

!

9309130146 930907

ADOCK 05000255 n[m

{

DR

1

PDR

_ ,

.

_

9

. .

.

,_.

.

.

- 1

.

-

-.

. -- - - . -

_ - - . ..

.

-

,

f

l

-

l

t

>

1

1

Inspection Summary

2

,

4

The 14RC inspectors noted the following:

,

<

j

The implementation of ISI was improved considerably from the previous

[

l

inspection. Corrective actions were taken to resolve the inspection

i

J

findings previously identified. Observations and examinations performed

this outage showed improvements in procedures and implementation of the

!

ISI program.

d

Steam generator (SG) secondary water chemistry and maintenance appears

l

to be substantially improved since the SGs were replaced. This is

,

i

evident by the secondary side cleanliness (small sludge buildup) and

eddy current examination results.

!

a

t

l

,

!

s

!

.

'

l

-

i

f

!

,

t

5

1

9

d

0

4

e

w

=w

nm---r

--

,-

,.-4

-

- -

--

- -+-

. _ -

- -

-

.

.

-.

-

_.

.

. _ - -

.

.._.

_

1

i

,

d

DETAILS

~

1.

Persons Contacted

Consumers Power Company (CPCo)

i

  • D. Rogers, Safety and Licensing Supervisor
  • C. Hillman, Licensing Engineer
  • B. VanWagner, Predictive Engineering Supervisor

!

  • T. Fouty, Senior Nuclear Operations Analyst

R. Smedley, Staff Licensing Engineer

S. Maclean, Senior Engineer

D. Engle, Senior Engineer

i

D. Morris, Quality Assurance

l

Pacific Sierra Nuclear Corporation (PSN)

W. Lee, Vice President

,

f

U. S. Nuclear Requlatory Commission (NRC)

  • M. Parker, Senior Resident Inspector

,

,

D. Passehl, Resident inspector

l

,

j

  • R. Landsman, Project Engineer

i

'

i

i

  • Denotes those attending the exit interview on August 4, 1993.

-

Other licensee and contractor personnel were contacted during the course

,

of the inspection.

!

'

i

i

2.

L icensee Action on Previous Inspection finding _s_L9270]!

j

s

,

1

l

(Closed) Unresolved item (255/92012-ll(DRS):

Ventilated Concrete Cask

for Dry fuel Storage QA/QC weaknesses.

The licensee's contractor

i

eversight and QA/QC implementation was weak.

Tre NRC inspector

]

icantified weaknesses including: failure to follow procedures,

!

1

msof ficient training of craf t, and inadequate cefinition of QA/QC

i

responsibilities.

Reference NRC inspection report 50-255/92018(DRP), which addressed the

l

NRC inspector's inprocess review of cask fabricetion and the

i

implementation of corrective actions. The NRC inspector reviewed the QA

!

i

Data Package for the dry cask fuel storage vessels, units 1 and 2.

1

fabrication records and test results were acceptable, this item has been

,

J

satisfactorily resolved,

l

l

1

(Closed) Violation 255/92012-10(DRS):

10 CfR Part 50.55(a), requires,

in part, that inservice inspection (151) of plant components be

<

conducted in accordance with the American Society of Mechanical-

Engineers Boiler and Pressure Vessel Code -(Code),Section XI.

The Code

]

requires that longitudinal pipe welds be included in the ISI program and

J

}

.

,

j

--

._

_

.

-

- .

..

. . - -

.-

_ _ _ _ _ _ .

__

_ . _ . __ .. -.._ _ _

._.

.

_ _ _ ,

i

,

-

,

t

i

i

,.

-

inspected at the intersection with circumferential welds.

Upon

I

-

examination of welds MSS-36-MSL-ISI-211, HSS-36-MSL-2SI-212, and MSS-36-

!

3

i

HSC-2SI-219 on the main steam system, it was noted that the intersecting

{

longitudinal welds had not been examined and were not included in the

!

licensee's ISI program.

,

(

j

The licensee examined all the longitudinal welds on the main steam

system that required inspection prior to the plant leaving cold shutdown

j

'

from the 1992 refueling outage. All welds were found to be

!

satisfactory.

In addition, all welds with longitudinal welds required

i

by 10 CFR Part 50.55(a) to be examined were added to the ISI 40 year

!

'

master plan. This violation has been satisfactorily resolved and is

l

considered closed.

s

i

!

.

3.

Steam Generator Eddy Current Examination (73753. 73755)

!

y

i

The licensee replaced steam generators (SGs) during the 1990-1991

outage. This was the third eddy current examination performed since

4

j

installation of the replacement SGs.

The inspection included full

i

length tube examination of 1598 tubes in the "A" SG and 1602 tubes in

j

the"B" SG utilizing a beo' bin coil probe with multifrequency ET (MIZ-18)

i

data acquisition system.

In addition, 201 random motorized rotating

1

i

pancake coil (MRPC) examinations were performed in SG-A and 202 in SG-B.

{

'

The examination results were as follows:

'

!,

SG-A

SG-B

,

i

MEM*

37

71

f

l-19%d*

1

23

!20-29X

6

11

I

,

'

!

30-39%

2

l

40-49X

1

'

t

  • Manuf acturing Burnish Mark (permeability indication due to cold working

{

!

etc.)

i

  • Fercent wall loss due to degracation, wear

,

!

The row 137, column 94 tube in SG- A was found to have a 41% indication

(40-49% reported above) which was plugged in accordance with the

l

e

'

Palisades Technical Specification requirement.

!

,

j

No reportable indications were found as a result of the random MRPC

!

}

inspection. MRPC of bobbin disterted indications (DI's) was also

!

performed with no indications substantiated as defects.

i

Results of the examination and comparison with the baseline ET concluded

!

i

that the replacement SG's show no significant degradation.

l

,

9

l

'

!

!

I

J

t

4

i

i

h

'

I

--,

.,

-

- - -

-

-

-

-

-

- -

-

-

-

.-

.

. . - - .

=

-

. . - ,

_-

- _ _ _

.

i

,

The licensee performed sludge lancing, secondary side cleaning and

'

3

foreign object inspection. Sludge lancing for the last two outages

,

since SG replacement resulted in very small sludge recovery. The small

'

,

sludge production during operations is attributed to excellent water

chemistry control of the secondary side combined with upgrades of

secondary side tubing materials.

i

The NRC inspector observed ET in progres:, verified

calibration / certification of ET equipment and calibration standards,

,

reviewed the examiner / analyst qualification certifications and the ET

'

Data Analyst Guidelines.

l

q

The NRC inspector also observed evaluations of ET data in progress,

4

sludge lancing post cleaning inspection (via remote camera VCR) and

'

.

reviewed the secondary side cleaning and inspection data.

,

]

No violations or deviations were identified, the licensee's SG

I

maintenance program since SG replacement has improved considerably.

'

i

4.

Erosion / Corrosion (E/C) Monitorina Proaram (490011

'

3

Procedure EM-09-08, Revision 3, describes the minimum requirements for

I

the erosion / corrosion program.

The selection of systems, component

.i

selection, ultrasonic inspection, data logging, data evaluation, and

,

engineering evaluations methodology were reviewed. The licensee's E/C

.

program appears to be conservatively implemented and based on good

,

{

engineering principles. Weaknesses which were identified in inspection

report 50-255/92012 are being addressed by the licensee.

The licensee's

l

predictive engineering department has submitted budget requisitions to

i

purchase and implement the EPRI Chet Works E/C program, an enhanced E/C

l

program with capabilities to continually update the computer model with

current plant operations data.

'

l

The licensee inspected 154 components cr subcomponents this outage.

.

]

Four components were replaced due to E/C.

The licensee replacements are

-

'

'

upgraded, using chrome / moly or stainless steel when possible.

t

j

The NRC inspector observed the ultrasonic measurement and data logging,

verified inspector and equipment certifications, and reviewed the data

e

'

and engineering evaluations performed this outage.

l

No violations or deviations were identified.

i

i

,

5.

Exit Interview

i

!

{

The inspectors met with the licensee representatives (denoted in

!

paragraph 1) at the conclusion of the inspection on August 4,1993.

The

inspector summarized the scope and findings of the inspection

i

activities.

The licensee acknowledged the inspection findings.

The

a

'

j

inspector also discussed the likely informational content of the

inspection report with regard to documents or processes reviewed by the

,

i

inspector during the inspection.

The licensee did not identify any such

!

j

document / processes as proprietary.

! !

,

1

1

3

i

.

-.

..

._

.-

-

_.

--

. - -