ML20054E200
| ML20054E200 | |
| Person / Time | |
|---|---|
| Site: | Davis Besse |
| Issue date: | 03/23/1982 |
| From: | Crouse R TOLEDO EDISON CO. |
| To: | Spessard R NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III) |
| Shared Package | |
| ML20054E178 | List: |
| References | |
| 1-255, NUDOCS 8204260248 | |
| Download: ML20054E200 (1) | |
Text
,
MXEDO
% EDISON Docket No.
50-346 Rc uop.cnana Vu Pmused License No. NPF-3 N**-
141912S9 5221 Serial No. 1-255 March 23, 1982 PRINCIPAL STAFF DTR ESIS 7/D PAD A/D
'sto Mr. R. L. Spessard, Director b/' hp4pt Diviaion of Resident and Project Inspection ns&TI United States Nuclear Regulatory Commission sdb..
Region III nt" c.07 File
/
799 Roosevelt Road Glen Ellyn, Illinois 60137
Dear Mr. Spessard:
This letter is written in response to a telephone conversation between Region III and Toledo Edison regarding instrument calibration procedures for the Davis-Besse Nuclear Power Station Unit 1.
In addition to providing an independent review of the Safety Features Actuation Systems (SFAS)
Instrument Calibration Procedures (Serial No. 1-250), Toledo Edison will also provide an independent review of the Reactor Protection System (RPS)
Instrument Calibration Procedures by August 31, 1982, and of the Steam and Feedwater Rupture Control System (SFRCS) Instrument Calibration Procedures by October 31, 1982. The intent of these reviews is to verify RPS and SFRCS instrument string accuracies. This will ensure compliance with the Davis-Besse Technical Specification requirements and the appropriate Safety Analysis.
Very truly yours, ff RPC:RFP:rs cc:
DB-1 NRC Resident Inspector 8204260 24'[{
THE TOLEDO EDISON COMPANY EDISON PLAZA 300 MADISON AVENUE TOLEDO, OHIO 43652 MAR 2 51982