1TREDO
%me EDISON ACHARD P. Caoust vu %t
- man, 14193259 *4 21 Docket No. 50-346 License No. NPF-3 Serial No. 1-250 February 26, 1982 Mr. R. L. Spessard, Director Division of Resident and Project Inspection U. S. Nuclear Regulatory Commission Region III 799 Roosevelt Road Glen Ellyn, Illinois 60137
Dear Mr. Spessard:
This letter is to identify ongoing activity related to your December 15, 1981 letter containing report 50-346/81-18.
This deals with the violation of Appendix A Technical Specification Section 2.2.1 (Table 2.2-1).
In addition to the corrective action taken in our letter of January 14, 1982 (Serial No. 1-239), Toledo Edison is providing an independent review of the Safety Features Actuation Systems (SFAS) ' Instrument Calibration Procedures. The intent of this' review is aimed at verifying SFAS instrument string accuracies. This will assure compliance with the Davis-Besse Technical Specification requirements and the appropriate Safety
- Analysis, i
This review is to be completed by March 31, 1982.
l Very truly yours, ffz 2 __ -
RPC:RFP:rs cc: DB-1 NRC Resident inspector l
l l
8204260 9//Y l
THE TOLEDO EDISON COMPANY EDISON PLAZA 300 MADISON AVENUE TOLEDO, OHIO 43652 MAR 1 ggg
.