Revised Monthly Operating Rept for Feb 1982
ML20053B838
Person / Time
Site: Beaver Valley
Issue date: 03/05/1982
From: Weaver L
DUQUESNE LIGHT CO.
To:
Shared Package
ML20053B826 List:
References
NUDOCS 8206010274
Download: ML20053B838 (1)


Text

~

OPERATING DATA REPORT DOCKET NO. 50-334 DATE 3-5-d2 COMPLETED BY L.

'4 Weaver TELEPHONE.

'+1'

'41-9303, OPERATING STATUS X. Unit Name: Beaver Valley Power Station. Unit til Note *

2. Reporting Period:

Februarv. 1982

3. I le===d Thermal Power (MWt):

?AA0

4. Nameplate Rating (Gross MWe):

923

5. Design Electrical Rating (Net MWe):

852

6. Maximum Dependable Capacity (Gross MWe):

960

7. Maximum Dependable Capacity (Net MWe):

810

8. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report. Give Reasons:
9. Power Level To which Restricted.If Any (Net MWe):

None

10. Reasons For Restrictions.If Any:

N/A This Month YrAo.Dete

'Camulative

!!. Hours !n Reporting Period 672 1,416 51,120

12. Number Of Hours Resctor Was Criticai 0

0 21,059.29

13. Resctor Reserve Shutdown Hours 0

0 4,482.80

14. Hours Gemerator On Line 0

0 20,154.06

15. Unit Reserve Shutdown Hours 0

0 0

16. Gross Thermal Energy Generated (MWH) 0 0

43,628,940.48

17. Gross Electrical Energy Generated (MWH) 0 0

13.650,440

18. Net Electrical Energy Generated (MWH)

-3.013

-8.521 12,515,433

19. Unit Service Factor 0

0 41.2

20. Unit Availability Factor 0

0 41.2

21. Unit Capacity Factor (Using MDC Net 1 0

0 33.6

22. Unit Capacity FactoriUsing DER Net) 0 0

32.0

23. Unit Forced Outsee Rate 0

0 40.2

24. Shutdowns Scheduled Over Next 6 Months tType. Date.and Duration of Each t:

7.#,a14,7 n t,79 17/29/81. 20 weeks u

25. If Shur Down At End Of Report Period Estimated Date of Startup:
  • v 21-1082
26. Units In Test Status iPnor to Comm rcial Operation s:

Forecast Achieved INITIA L CRITICA LITY

"/2 V/A INIT!AL ELECTRICITY N/A N/A COMMERCIAL OPERATION N/A N/A (9/77) 820601 0M

..