Omaha Public Power District 1623 HARNEY 8 OMAHA. NEBRASKA 68102 e TELEPHONE S36 4000 AREA CODE 402 March 18, 1982 LIC-82-115 Mr. John T. Collins, Administrator U. S. Nuclear Regulatory Commission Region IV 611 Ryan Plaza Drive, Suite 1000 Arlington, Texas 76011
Reference:
Docket No. 50-285 Inspection Report 81-35
Dear Mr. Collins:
i The referenced Inspection Report identified four significant findings related to the Emergency Preparedness Appraisal concluded on December 16, 1981. Omaha Public Power District's response to signi-i ficant finding 4 is attached.
Sincerely, llD a
W C. Jpnes Divisio,n Manager Productico Operations WCJ/KJM/TLP/RWS:jmm Attachment cc:
U. S. Nuclear Regulatory Commission l
Office of Inspection and Enforcement Washington, D.C.
20555 LeBoeuf, Lamb, Leiby & MacRae 1333 New Hampshire Avenue, N.W.
~~fM7 h [ ( g */
Washington, D.C.
20036
+?
=\\l
}
bl(bl M 22l982 :l /
L__
p L_ _
a 8205070379 0
05 l
PDR ADOCK 0 ppg l
L
9 OMAHA PUBLIC POWER DISTRICT'S RESPONSE TO IE INSPECTION REPORT 81-35 Emergency Preparedness Appraisal Significant Finding 4 - Respiratory Protection a.
Required Action The licensee shall determine the expected number of onsite emer-gency personnel who may be required to perform essential duties under conditions of significant airborne radioactive contamination and who, therefore, require self-contained breathing apparati in order to safely perform their assigned tasks. The licensee shall make provisions for acquisition of the necessary quantities of appropriate respiratory protection equipment and for locating the equipment in areas safely and quickly accessible to all onsite emergency response personnel.
The licensee shall assure the NRC that all emergency response personnel will maintain their capa-bility to safely and efficiently don appropriate respiratory protective equipment.
b.
Agreed Upon Date of Completion The licensee shall describe to the NRC by April 1,1982, how all essential emergency response personnel including anticipated off-site emergency support personnel are to be provided with appro-priate respiratory equipment, including plans for the acquisition of necessary additional equipment.
Response
a.
Action Omaha Public Power District has completed an evaluation which identified all essential onsite emergency response personnel,
)
including anticipated offsite support personnel, that may require a I
self-contained breathing apparatus (SCBA) for the performance of their duties during an emergency. The following criteria were used for determining which personnel require SCBA's:
(1) normal work location, (2) assigned emergency response facility during emer-gencies, (3) onsite mobility requirements to perform emergency duties, (4) site access and egress travel route, and (5) optimum location of SCBA. Utilizing these criteria, the District segre-gated those positions that require dedicated or individual SCBA's and those positions that could share a respirator. With these considerations, the District determined the optimum number and locations for the SCBA units to ensure all essential personnel would have proper respiratory equipment for all contemplated emergency tasks. The results of the SCBA analysis are provided below:
, Location Quantity of SCBA Required Technical Support Center 10 Control Room /0perations 6
Support Center Emergency Operations Facility 6
Fire Brigade Assembly Area 9
Health Physics Station 8
Security Buildina 1
i Total 40 The District has verified that all applicable personnel, with the exception of five i;RC representatives at the Technical Support Center, maintain the capability to correctly don and operate respiratory equipment in accordance with Ua Fort Calhoun Station Radiation Protection Program.
b.
Date of Completion Presently,18 self-contained breathing apparatus units are main-tained at the Fort Calhoun Station and are available for emergency service. The District will increase the supply to attain the optimum 40 units as identified by the evaluation. The District has.
ordered four additional SCBA units and plans to plac2 them in service by April 1,1982. The remaining 18 SCBA units will be ordered by April 1,1982 and will be placed in service within one month af ter delivery.
1 i
e n
,,