Forwards IE Insp Repts 50-275/82-10 & 50-323/82-06 on 820308-12 & 0329-0402.No Noncompliance Noted
ML20052C181
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 04/20/1982
From: Bishop T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To: Crane P
PACIFIC GAS & ELECTRIC CO.
Shared Package
ML20052C182 List:
References
NUDOCS 8205040471
Download: ML20052C181 (2)


See also: IR 05000275/1982010

Text

_ _ _ _

- . . -

. - . .

.

,,

,,

,

,

-,,

.

, ~ ,

.

,

,.

-

'?

.'

?

j, Y

ay -'

<

APR 2 01982

0, W !&,

Docket Nos. 50-275, 50-323

g

s

rcdca. :~ .;

-

%

el

MAY

31982w [2

Pacific Gas and Electric Company

u na mam maa

"

P. O. Box 7442

"" Ef"

J

l

San Francisco, California 94120

y

(B

P

Attention: Mr. Philip A. Crane, Jr.

m

Assistant General Counsel

Gentlemen:

Subject: NRC Inspection of Diablo Canyon Units 1 and 2

This refers to the inspections conducted by Mr. J. F. Burdoin of this office

on March 8-12 and March 29 - April 2,1982 of activities authorized by IRC

Construction Permit No. CPPR-39 and CPPR-69, and to the discussions of our

findings with Mr. R. D. Etzler and other members of your staff on March

12 and April 2, 1982.

Areas examined during this inspection are described in the enclosed inspection

report. tlithin these areas, the inspection consisted of selective examinations

of procedures and representative records, interviews with personnel, and

observations by the inspector.

No items of noncompliance with NRC requirements were identified within

the scope of these inspections.

In accordance with 10 CFR 2.790(a), a copy of this letter and the enclosure

will be placed in the NRC Public Document Room unless you notify this office,

by telephone, within ten days of the date of this letter and submit written

application to withhold information contained therein within thirty days

of the date of this letter. Such application must be consistent with the

requirements of 2.790(b)(1).

8205040471 820420

/

PDR ADOCK 05000275

OI

G

PDR

g

. . .

_

j

'

' ' ' " ' '

)

B'UR 0

C

"tM

, , , , ,', , , ,'$ H

BI

"" "'

" " "

""

"

- - - - -

su

4

... .. . ......

...... .............

onn)

4/d/82

....../..........

4p/82

,...........

,,,,,, , , , , ' "

' ' ' ' " " ' " '

' ' ' ' " "

4// /82

. .

. . ....

.. . ..... . .

. . . .......... ,,

,, ....,,,. ,,, ,

, ,,, ,,,,,, , ,,

,,,,, ,,, ,, ,

, , , , , , ,,

NRC FORM 318 410'80) NRCM O240

OFFICIAL _EECOR D COPV_ __

e usc.co is.ao--329 824 -

"

-

.

.

d

Pacific Gas and Electric Company

-2-

APR 20 DBZ

Should you have'any questions concerning this inspection, we will be glad

to discuss then with you.

Sincerely,

T. N. Bishop, Chief

Reactor Construction Projects Branch .

Enclosures:

Inspection Report "os.

50-275/82-10

50-323/82-06

cc w/ enclosures:

W. A. Raynond, PGtE

R. C. Thornberry, PG&E (Diablo Canyon)

bcc: DMB/ Document Control Desk (RIDS)

Distributed by RV:

Resident Inspector

Sandra Silver (Report only)

RHE (w/o enc)

i

.