Advises That Only Open Item in SER 3 Is Installation of Smoke Detection in Areas Having safety-related Equipment. Detectors Must Be Fully Operational Prior to Initial Fuel Loading
ML20050D046
Person / Time
Site: Summer 
Issue date: 04/01/1982
From: Youngblood B
Office of Nuclear Reactor Regulation
To: Nichols T
SOUTH CAROLINA ELECTRIC & GAS CO.
References
NUDOCS 8204120005
Download: ML20050D046 (2)


Text

!

~

~

1 DISTRIBUTION:

Docket File, bcc:

TERA LB#1 Rdg.

PDR APR 11982 JYoungblood LPDR MService NSIC Docket No.: 50-395 enhut S (16)

SHanauer RMattson Mr. T. C. Nichols, Jr.

"T o"

Vice President & Group Executive y

r g

Nuclear Operations RHartfield, MPA South Carolina Electric & Gas Company p.C6\\'M 0 ELD C

Post Office Box 764 OIE

{

g7y 7=

Columbia, South Carolina 29218

Dear Mr. Nichols:

%,2

Subject:

Fire Protection System - Virgil C. Summer Nuclear Statio f^[

On January 8,1982, we issued Supplement No. 3 to the Safety Evaluatio r

In that report we concluded that all matters related to fire protection were resolved.

In your letter dated January 18, 1982 you identified certain diff-erences between statements we made on that report and your comitments. We have resolved all but one of those differences.

The remaining issue involves the installation of smoke detectors. On page 9-4 of Supplement No. 3 to the Safety Evaluation Report, we stated that " Fire detection systems will be installed in all areas having safety related equipment."

By letter dated January 18, 1982, you tool: oxccption to this statement, indicating that not all safety-related equipment areas are equipped with smoke detectors.

This deviation from our guidelines has not been justified nor have you identified those areas where fire detectort are not currently installed. We will require that a smoke detection system be installed in each area containing safety related equipment in accordance with our guidelines specified in Position C.S.a of Branch Technical Position 9.6.1, Revision 1.

In accordance with Position C.I.e(2) of Branch Technical Position 9.5.1, Revision 1, this equipment should be fully operational prior to initial fuel loading in the facility. Should you request relief we will require the identification of all additional areas where smoke detectors are to be installed, the schedule for completion, and the compensating actions to be taken in the interim period.

Sincerely, Originsi signed bys B. J. Youngbloodf B. J. Youngblood, Chief Licensing Branch No. 1 Division of Licensing cc: See next page 8204120005 820401

'The reporting and/or recordkeeping PDR ADOCK 05000395 requirements contained in thi letter E

PDR affect fewer thkn ten respondc ntc ;

omet > u y.

....gg -

- theref cre. -0MB :1sarance is nat rewired suame > W

.9.......

D

.lood.VB.enaroya.....

nder.r.L. m st1 ?............

...../. 82.......4/./....32 3 1

.../... }../. 82 4

oon >

une eocu ais on am uncu om OFFIClAL RECORD COPY usaro i,i-m,w

Mr. T. C. Nichols, Jr.

Vice President & Group Executive Nuclear Operations South Carolina Electric & Gas Company Post Office Box 764 Columbia, South Carolina 29218 cc: Mr. Henry. Cyrus Senior Vice President South Carolina'Public Service Authority 223 North Live Oak Drive Moncks Corner, South Carolina 29461 J. B. Knotts, Jr., Esq.

Debevoise & Liberman 1200 17th Street, N. W.

Washington, D. C.

20036 Mr. Mark B. Whitaker, Jr.

Group Manager - Nuclear Engineering & Licensing South Carolina Electric & Gas Company Post Office 764 Columbia, South Carolina 29218 Mr. Brett Allen Bursey Route 1. Box 93C Little Mountain, South Carolina 29076 Resident Inspector / Summer NPS c/o U. S. NRC Route 1, Box 64 Jenkinsville, South Carolina 29065 Mr. James P. O'Reilly U. S. NRC, Region II 101 Marietta Street Suite 3100 Atlanta, Georgia 30303