ML20050B820

From kanterella
Jump to navigation Jump to search
Provides Results of Preliminary Assessment of Relief & Safety Valve Test Program.Addl Info Re Design & Bases for Safety Power Operated Relief Valves Encl
ML20050B820
Person / Time
Site: Fort Calhoun 
Issue date: 04/01/1982
From: William Jones
OMAHA PUBLIC POWER DISTRICT
To: Clark R
Office of Nuclear Reactor Regulation
References
RTR-NUREG-0578, RTR-NUREG-0737, RTR-NUREG-578, RTR-NUREG-737, TASK-2.D.1, TASK-TM LIC-82-138, NUDOCS 8204070450
Download: ML20050B820 (6)


Text

_

Omaha Public Power District 1623 HARNEY 8 O sd A H A. NEGRA9MA 68102 8 TELEPHONE 536-4000 AREA CODE 402 April 1, 1982 LIC-82-138 Mr. Robert A. Clark, Chief U. S. Nuclear Regulatory Commission Office of Nuclear Reactor Regulation 9

Division of Licensing 4

4 Operating Reactors Branch No. 3 Washington, D.C.

20555 S

t.tWCW/m

Reference:

Docket No. 50-285

'4 ppg 0 61982a CV y($gwr% j-Dear Mr. C1 ark.

ifw n

Subject:

Safety and Relief Valve Test Pr pq s

\\

In accordance with the initial recommendations of NUREG-

<h tion 2.1.2, as later clarified by NUREG-0737, Item II.D.1, and the Commis-sion's letter dated September 29, 1981, each pressurized water reactor (PWR) utility on or before April 1,1982 was to submit a preliminary evaluation supported by test results which demonstrates the capability of relief and safety valves to operate under expected operating and accident conditions.

This letter provides the results of Omaha Public Power District's pre-liminary assessment of the relief and safety valve test program as it applies to the Fort Calhoun Station.

The District is a participant in the Generic PWR Safety and Relief Valve Test Program implemented by the Electric Power Research Institute (EPRI) at the request of participating PWR utilities in response to the U. S.

Nuclear Regulatory Commission recommendations for safety and relief valve testing.

The primary objective of the test program was to provide full scale test data confirming the functionability of primary system power operated relief valves and safety valves for expected operating and accident conditions.

The second objective of the program was to obtain sufficient piping thermal hydraulic load data to permit con-firmation of models which may be utilized for plant unique analysis of

/ O'/b safety and relief valve discharge piping systems.

Relief valve tests

/

were completed in August 1981 and safety valve tests were completed in December 1981.

The reports prepared by EPRI documenting the test program results and a summary justification for applicability to the

//

Fort Calhoun Station are listed below.

8204070450 020401 PDR ADOCK 05000285 P

PDR

o.

Mr. Robert A. Clark LIC-82-138 Page Two A.

" Valve Selection /Justificatiot Report" This report documents that the selected test valves represent all participating PWR plant safety and relief valves. The Fort Calhoun Station's pressurizer overpressure protection system consists of two Crosby 3K6 safety valves and two Dresser 31533VX-30 power operated relief valves, operating in parallel.

EPRI tested valves made by the same manufacturers and of the same models; therefore, the valves tested are representative of the Fort Calhoun Station valves.

B.

" Test Condition Justification Report" and the " Combustion Engineer-ing Plant Condition Justification Report" These reports document the basis and justification of the valve test conditions for all participating PWR plants. The fluia inlet conditions for the Fort Calhoun Station's pressurizer safety and relief valves are identified in our NSSS vendor's report (Combustion Engineering report prepared for EPRI, NP-Research Project V102-20 (Phase B), interim report dated March 1982). This report demon-strates that EPRI's test conditions are representative of all feasible conditions which could occur at the Fort Calhoun Station.

C.

" Safety and Relief Valve Test Report" This report provides evidence demonstrating the functionability of the selected test valves under the selected test conditions for all participating PWR plants.

The test data, presented by EPRI, encom-passes the Fort Calhoun Station's valves and valve inlet conditions to the extent that a realistic estimate of actual valve performance during plausible operating excursions can be determined. The District expects to provide additional data available, by July 1, 1982, which will assess valve performance modifications if necessary.

D.

" Applicability of RELAP5/M001 for Calculation of Safety and Relief Valve Discharge Piping Hydrodynamic Loads" This report presents an analytical model benchmarked against test data that may be used for plant unique analysis of safety and relief valve discharge piping systems.

The safety valve and power operated relief valve system discharge piping at the Fort Calhoun Station was previously analyzed for transient and steady state loads under the action of subccoled liquid flow for low temperature overpressurization (LTOP) events with loop seal water followed by steam flow.

This analysis was performed as a result of concerns-for protecting against LTOP by providing a low pressure setpoint on the power-operated relief valves.

Piping modifications were per-formed to ensure that the integrity of the piping would be main-tained consistent with applicable codes. Certain EPRI test data indicate that our previous analysis and results may not be suf-ficiently conservative; therefore, the District will perform a detailed thermal hydraulic analysis, using a code comparable to RELAP 5 to verify the adequacy of the existing discharge piping.

Mr. Robert A. Clark LIC-82-138 Page Three This analysis will be performed after completing the valve test data evaluation which provides the input to the analysis.

However, the modification previously performed provides reasonable assurance that the piping system would perform adequately during any of the feasible events.

All of the documents have been received by the District and transmitted to you by David Hoffman of Consumers Power Company on behalf of the participating PWR utilities as part of our response in meeting the April 1,1982 preliminary submittal requirement. provides additional information related to the design and bases for the Fort Calhoun Station safety valves and power operated relief valves.

In addition to providing the referenced reports, the District has performed a preliminary review of the test program results.

Based on the review, we have concluded that valves tested represent the safety and relief valve designs and that the conditions tested envelop the range of expected operating and accident conditions for the Fort Calhoun Station.

The above mentioned reports also provide the evidence required by NUREG-0737, Item II.D.1.A which will be used to perform the final plant specific evaluations.

The September 29, 1981 Commission letter requested that plant specific final evaluations be submitted by July 1,1982.

In order to meet that date, evaluations have been initiated. Depending on the outcome of the evaluations, it may be necessary to continue the evaluation beyond July 1, 1982.

If a longer evaluation period is required, you will be notified on or before July 1,1982.

Sincerely, j

't I

h y/ hu Y

. C. Jones Divisil/nManager Produc' tion Operations Enclosure cc:

LeBoeuf, Lamb, Leiby & MacRae 1333 New Hampshire Avenue, N.W.

Washington, D.C.

20036

~.

%n

~

,=

m s

r ENCLOSURE f Design' Ehses The baximum pressure f.ransient for the reactor coolant system pressure i

vessel allowed under ASME Code,Section III, is 110% of design pressure.

The maximum pressure transient allcwable in the reactor coolant system piping, valves, and fittings under USAS Section B 31.1 is 120% of design pressure. The established design pressure at the Fort Calhoun Station's reactor coolant system is 2500 psia; therefore, the safety limit for the reactor coolant system is 2750 psia and for piping, valves, and fittinis it is 3000 psis, j

To protect > gainst anticipated pressure transients, two spring loaded safety valves are installed on the Fort Calhoun Station pressurizer.

These valves meet ASME Code requirements and sre designed to. pass sufficient pressurizer steam to limit the reactor coolant system pres-sure_ to 110% of design following a complete loss of load without simul-taneous reactor trip while operating at 1500 MWT.

If during this event no residual heat were removed by any of the~ other means available, the amount of.steamTwhich could be generated at safety valve lift pressure would be less than half the capacity of one safety valve.

To enhance the operation of the plant and to minimize the operation of the's'afety valves, two power operated relief valves (PORV's) were installed at the Fort Calhoun Station. The PORV's are critical quality equipment (CQE) but are not needed to achieve safe shutdown. The PORV's are hnif capacity valves, but their total capacity is sufficient to limit the reactor coolant system pressure to 110% of design for the design basis o'verpressure event.

They are also used to protect the

. reactor coolant' system from low temperature overpressure.

The hydraulic and mechinical properties of the safety and power operated relief valves for the Fort Calhoun Station are listed below.

1.

Safety Valves (RC-141 and RC-142)

The valve inlets are provided with uninsulated loop seals which contain approximately five gallons (each) of water at an estimated 0

temperature of 160 F during normal power operation. The parameters for these valves are given in Table 1.

Table 1 Pressurizer Safety Valve parameters Manufacturer:

Crosby Number:

Two Type:

Safety, balanced bellows-enclosed bonnet, ASME Code Design Pressure:

2500 psia Design Temperature:

7000F Normal Operating Pressure:

2100 psia Normal Operating Temperature: 6430F Fluid:

Saturated steam Capacity Per Valve (Minimum): 200,000 lbm/hr Total Capacity (Minimum):

400,000 lbm/hr i

- i

ENCLOSURE 1 (Continued)

Capacity Per Valve (Maximum): 240,000 lbm/hr Total Capacity (Maximum):

480,000 lbm/hr Set Pressure - RC-141:

2530 psig Set Pressure - RC-142:

2485 psig Back Pressure - Superimposed: 3 to 300 psig range Back Pressure - Built-Up:

500 psig Accumulation:

Maximum 3% of set pressure Blowdown:

4% of set pressure 2

Orifice Area (in ):

1.8904 Body Material:

ASTM-216 Grade UCB or equal Trim Material:

Stainless steel Spring Material:

Alloy steel Connections:

Inlet Outlet Type:

Flanged Flanged Size:

3 inch 6 inch Rating:

2500 lb 300 lb 2.

Power Operated Relief Valves (PCV-102-1 and PCV-102-2)

The valve inlets are provided with uninsulated loop seals which contain approximately 2.3 gallons (each) of water at an estimated temperature of 1000F to 1200F.

A motor operated isolation valve (HCV-150, HCV-151) is provided upstream of each of the relief valves to permit isolating a valve in case of failure or excessive leakage. The parameters for these valves are given in Table 2.

Table 2 Pressurizer Power Operated Relief Valve Parameters Manufacturer:

Dresser Number:

Two Type:

Power operated, internal solenoid i

pilot Design Pressure:

2500 psia Design Temperature:

700 F Normal Operating Pressure:

2100 psia Normal Operating Temperature: 6430F Fluid:

Saturated steam Capacity Per Valve (Minimum): 99,000 lbm/hr Total Capacity (Minimum):

198,000 lbm/hr Capacity Per Valve (Maximum): 117,000 lbm/hr Total Capacity (Maximum):

234,000 lbm/hr Set Pressure (Trip):

240r) psia, when temperatures are above 3000F Low Temperature Overpressure (Trip):

450 psia, when temperatures are below 3000F Back Pressure - Superimposed: 3 to 300 psig range 2

Orifice Area (in ):

,94 Body Material:

A 182 Grade F 316 Trim Material:

Stainless steel

^-

N i

\\\\

ENCLOSURE 1 N

~

' w' s

s -

(Continued) e-

-s Connections:

Inlet Outlet Type:

' Flanged Flanged

~

'e Size:

2 inch 4 inch

\\

Rating:

2500 lb 300 lb i -

7 s

e

,A

% ',s 5

  • g

\\

4 s

\\ ~g

  • \\

7%t g

s 5

i.

Qs t

g j

s i

v~

kk

  • W*

i

(

"N

\\

w

\\

v,.

\\

4 s.

\\

\\

t 6

6.

A

+

,s t

3 I

e 4

a

~

~

=

N, t

$,i '

f

/

f t

+ *.<

(.

t w1 - =

s

,g t,

L y>

u

[

.a_6

. u*

4'

.i n.

.