ML20050A753

From kanterella
Jump to navigation Jump to search
IE Insp Repts 50-352/82-04 & 50-353/82-03 on 820201-28. Noncompliance Noted:Failure to Control Design Changes Adequately
ML20050A753
Person / Time
Site: Limerick  Constellation icon.png
Issue date: 03/04/1982
From: Durr J, Mccabe E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML20050A741 List:
References
50-352-82-04, 50-352-82-4, 50-353-82-03, 50-353-82-3, NUDOCS 8204020234
Download: ML20050A753 (8)


See also: IR 05000352/1982004

Text

'

-

,

.*

,,

U. S. NUCLEAR REGULATORY COMMISSION

.

50-352/82:.04

Report No.

50-353/82-03

50-352

Docket No.

50-353

CPPR-106

License No. CPPR-107

Priority

-

Category

A

Licensee: Philadelphia Electric Company

2301 Market Street

Philadelphia, Pennsylvania 19101

Facility Name: Limerick Generating Station, Unit Nos. 1 & 2

Inspection at: Limerick, Pennsylvania

Inspection cond cted:

February 1 - 28, 1982

.sikJol

J 1

Lt

Inspectors: ]< ,/

ss'

J. P. Durr,~' Senior Resident Inspector-

/ Dite Signed

Date Signed

Date Signed

Approved by:

&bM

sl 4 / 8'Z.

E. C. McCabe, Chief, Reactor

Date Signed

Projects Section 2B

Inspection Summary: Report 50-352/82-04 and 50-353/82-03 perfomed February

i - zu, 1962.

Areas Inspected: A routine, unannounced inspection by the Senior Resident

Inspector of the HVAC subcontractor's quality assurance program , plant tours,

licensee action on previous inspection findings, and 10 CFR 21 reports. The

inspection involved 77.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> at Unit 1 and 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> at Unit 2.

Results:

One violation was identified in the 4 areas inspected, (Failure to

adequately control design changes, para. 3 and 4).

Region I Fonn 12

(Rev. April 77)

8204020234 020315

gDRADOCK 05000352

PDR

.

-

-

. -. .

.

..

'

t

,

.

! 'o

j

DETAILS

,

1.

Persons Contacted

Philadelphia Electric Canpany

J. M. Corcoran, Field QA Branch Head

M.J. McGill, QAE

G. J. Moffitt, Engineer - Construction

P. L. Naugle, Engineer

,

P. K. Pavlides, Manager - QA

Bechtel Power Corporation

i

G. D. Abbey, Subcontrects Engineer (SCE)

T. Altum, Assistant Project Field Engineer (APFE)

A. Arch, APFE

M. J. Baron, Lead Field Welding Engineer

-

G. Cerrix, Instrument Superintendent

B. Dragon, QAE

H. D. Foster, PFQCE

H. F. Greenawalt, QAE

J. Honer, Sr. Lead S/C Engineer

,

G. C. Kelly, QAE

.

E. R. Klossin, PQAE

'

J. L. Martin, QAE

,

!

K. L. Quinter, Assistant PFQCE

D. Smolinsky, Lead Pipe Engineer

D. C. Thompson, Assistant PFQCE

<

'

R. E. Weaver, LSME

"

l

A. G. Weednan, PFE

Schneider, Inc.

-

1

1

T. M. Carroll, Project Manager

i

i

G. A. Heinrichs, QC Manager

The above listed personnel attended exit interviews on February 11 or 25,1982.

Other craftsmen, engineers, quality control technicians, and supervisors were

l

contacted and interviewed as the inspection interfaced with their work.

I

t

,

i

_

._,

--

_

_

<

.

-

.

'

,

3

2.

Licensee's Actions on Previous Inspection Findings

(Closed) Violation (353/78-07-01)

(Closed) Violation

(352/78-11-01) The licensee was discharging

water from construction activities with turbidity levels in excess of

Construction Pemit allowed levels. The licensee analyzed the rate at

discharge and the turbidity level relative to the Schuylkill River fiow

and determined that there was no adverse environmental impact.

In

addition, he eliminated the direct discharge of water to the Schuylkill

River and instructed the responsiMa superintendent in the proper

t

disposal of dewatering operatior.

The subcontractor responsible for this violation has completed his work

at the site and no further dewatering operations will be perfomed by him.

The inspector toured the site on February 17, 1982, and verified that

settling basins are functional and dewatering appears to be controlled.

He also verified that the licensee had performed a follow-up audit, N-142,

and surveillance, C-172, and corrected all violations.

This item

is closed.

(Closed) Violation (352/79-11-08)

(Closed) Violation (352/81-06-02)

Inspection finding (352/79-11-08)

identified improper welding of heating, ventilating, and air conditioning

(HVAC) dampers.

An attempt to close this finding disclosed that inadequate

corrective actions were taken. The limited access to the welds in question

precluded meaningful inspections from being performed. The design remedy

was to provide an alternate weld inside the damper.

A verification

inspection by the NRC revealed that where welds were inaccessible for

inspection, the alternate weld had not been deposited. This resulted k the

finding (352/81-06-02).

To preclude recurrence of incomplete corrective actions, the licensee has

changed his system so that findings will no longer be closed out before

committed actions are completed. This will be verified by the NRC as future

violations are resolved.

In addition, the licensee took the following actions to correct the

damper weld problem:

(1) Reinspected all dampers for weld accessibility.

(2) Welds which were determined to be inaccessible were modified

in accordance with the alternate design.

(3) Retrained the HVAC quality control inspectors regarding procedures

for inaccessible equipment.

.

.

'

i

.

'

!

4

(4) Revised the site inspection procedure, PPM-5.3, to include a re-

'

quirement in the in-process inspection procedure to check for

accessibility.

The NRC inspector verified that the above corrective actions were completed.

These items are closed.

(Closed) Unresolved Item (352/80-02-03)

The practice of welding galvanize-

coated shapes to the containment liner was questioned.

A review of the

February 14, 1980 letter disclosed that the licensee perfonned welding tests

of electro-galvanized and hot-dipped galvanized shapes.

No adverse

reactions were noted because of the coating.

The AWS Welding Handbook, 72.13-

72.21, and the AWS Structural Welding Code, 3.2, discuss welding through

galvanized coatings without detrimental effects on the weld deposit. This

item is closed.

(Closed) Unresolved Item (352/80-02-04)

The inspector was concerned

that licensee Audit Finding Reports, Fonn QAF-8, were not routinely reviewed

for reportability under 10 CFR 50.55(e). A review of the licensee's

Quality Assurance Plan, Appendix Z and Exhibit XXXIII, verified that

procedures have been implemented which assure the review of audit findings

for reportability. The Finding Report is required to be reviewed for

reportability and this review documented in block 21 of the report. This

item is closed.

(Closed) Violation (353/80-08-01)

(Closed) Violation (352/80-09-01)

The licensee failed to prevent the

discharge of raw sewage to the Schuylkill River. The licensee determined

that the spillage was caused by an open vent associated with the main

tank inlet pipe. An abnonnally large

flow of sewage escaped from this

vent. The licensee capped this vent to preclude recurrence. The inspector

verified that the vent was capped and discussed the sewage system operation

with the pollution control engineer and plant operators. This item

is closed.

(Closed) Violation (352/80-17-01)

(Closed) Violation (352/81-04-01)

Violation (352/80-17-01) identified

uncontrolled cutting of reinforcing bars (rebar) in a concrete block wall.

Violation (352/81-04-01) identified uncontrolled issue of rebar cutting

drills and improper documentation of cut rebar. The licensee recalled all

rebar cutting drills, and implemented new procedures to control the cutting

of rebar, and performed an analysis of " worst case" walls to assure

structural soundness.

The inspector reviewed the revised Job Rule, JR-G-28, for the committed

program changes and controls.

He verified that the procedure for control

was implemented by examining selected attributes from the Job Rule.

He

i

1

__

,_

.

.

.

1

,

5

interviewed the personnel responsible for Job Rule implementation and

confimed that they were knowledgeable of their duties and that appro-

priate reccrds were being kept. During previous plant tour inspections,

the inspector examined several Excavation Check Sheets and verified that

rebar drilling was properly authorized. These items are closed.

3.

Plant Tours (Unit Nos.1 & 2)

Periodically during the inspection, tours were made of the Unit Nos. 1

and 2 primary reactor containments, the reactor buildings, the control

structure, and surrounding yards and shops. The inspector examined

cmpleted work, work in-progress, quality control activities, and equipment

storage, handling, and maintenance.

He discussed the technical aspects

of the work with craftsmen, supervisors, and engineers to assure work

was being perfomed in accordance with requirements.

During the tours and over a period of several days, welders complained

to the inspector that they were having difficulty with weld porosity

during the first half inch of weld deposit.

Further inquiries by the

inspector revealed that other welders were also experiencing difficulty

with porosity in the initial weld deposits. This was brought to the

j

attention of the licensee who acknowledged that similar complaints had

been made to him and that some infomal tests had been perfomed in order

to substantiate the complaint. The tests apparently were satisfactory and

the issue closed.

Based on the welders' statements, the inspector requested further steps

be taken to resolve the issue. The licensee believes that the problem

may be limited to welder technique and will provide additional instruction

.

to those encountering difficulty.

This item is unresolved pending

resolution of the problem (352/82-04-03).

'

,

Safety related welds (ASME III, Class II and III) were selected for

document review and observation of welding activities. The document

reviews verified the welder's qualifications, proper welding procedures

j

were e ployed, required nnndestnictive tests specified, appropriate

'

quality control inspection points specified and signed off, and proper

preheat and postweld heat treatments were required. The observation

of welding consists of, where applicable, examination of the cleanliness,

,

fitup, and alignment of the parts; proper welding equipnent; purge and

~

l

cover gas flow rates; electrodes and filler materials; appearance of the

weld deposit; evidence of quality control activities; and proper documen-

tation. The following welds were examined:

l

I

I

l

L

I

.

..

.-

.- .

-

-

._

.

,

6

Weld No.

Class

System

Status

GBB-111-1/6 FW55

II

RHR

Root Pass

Pipe Weld

HBC-182-H901

III

RHR Serv.

Intemediate

water

Weld Passes

In an attempt to close an open item concerning pipe hangers, the inspector

reviewed the Job Rule M-17, " Field Control of Pipe Supports". The Job

Rule, paragraph 5.6.1, pemits the field engineer to deviate from the

hanger detail drawing or the installation specifications during fabrication,

installation, and rework.

In the case of fabrication and installation, the

engineer has 3 days within which to document the change on a Field Change

Request (FCR). For partially installed hangers and hanger rework, he is

not required to document changes u til the completed hanger is submitted

for acceptance to quality control. This practice allows undocumented

design changes to be made and installation to proceed without approved

drawings or procedures. This is contrary to 10 CFR 50, Appendix B,

Criteria III and VI in that:

Criterion III requires the design basis be translated

into drawings and that field changes to these drawings

be controlled.

Criterion VI requires that measures shall assure that changes

to these drawings are reviewed for adequacy, approved for

release, and are distributed to and used at the location

where the activity is perfomed.

The stated and implied requirements are that field design changes must be

documented and controlled before the work proceeds so that the workmen

have clear drawings and instructions to perfom the work with.

This is a violation (352/82-04-04).

The inspector became aware of an excessive rejection rate for pipe hangers

while pursuing the foregoing violation. The licensee is currently exper-

iencing a 50% rejection rate for hangers inspected by quality control.

Discussions with the licensee's staff verified that they were aware of the

problem and taking steps to improve the acceptance rate. The inspector

infomed the licensee that he strongly suspected that the failure to

provide positive controls on the field originated design changes, identifled

above, have contributed to the problem.

The licensee's efforts to improve

the hanger rejection rate will be reviewed in conjunction with the violation.

-

-

- -.

.

.

'r

i

7

4.

Heating, Ventilating, and Air Conditioning (HVAC)

Subcontractor Audit

The NRC SALP Report for the period of October,1979 to September,1980,

identified the subcontractor quality assurance program functional area

as below average.

The HVAC subcontractor's perfomance was the basis for

this finding. Further, the licensee reported a Construction Deficiency

relating to the fabrication and installation of HVAC duct work which

did not meet design drawings.

Based on these findings, an audit of the

HVAC subcontractor's program was perfomed to assess the adequacy of

corrective actions taken by the licensee.

The audit consisted of

selected attributes from the HVAC subcontractor's " Field Nuclear

Quality Assurance Manual" and " Project Procedures Manual".

The audit

verified the implementation of design roviews, organization, welding pro-

cedures, document control, inspection, nonconformance reporting and duct

work installation.

The review of the drawing control process revealed that when design

changes are received from the architect-e: gineer (AE) they are redrawn

in the HVAC subcontractor's fomat. This requires that the redrawn

documents receive another design review by the AE. To expedite the work,

" pick off" sheets are drawn from the design change drawings. The

" pick off" sheets are details of the fabrication which permits work to progress

.'

while the base document is approved.

There are no provisions in the

program to provide review and control of these " pick off" sheets. This

means that equipment is being fabricated, for a period of time, to

unreviewed and uncontrolled documents. This is contrary to 10 CFR 50,

Appendix B, Criterion VI and a violation (352/82-04-01).

The review of the Nonconfomance and Corrective Action control systems

disclosed that 4 Nonconfomance and Dispor1 tion Reports from 1978 were not

closed. Further, the Corrective Action Report (CAR) log shows 11 CAR's

open from November, 1979 to September, 1981.

The quality assurance manual

does not impose any time restraints for initiating follow-up action by

the responsible parties. The licensee stated that the quality assurance

manual was currently being revised and that a time restraint would be

imposed on CAR follow-up.

The quality assurance manual also states that a " Shop Standard Book" is

prepared by the Lead Draftsman.

This has not been done, however, the

'

infomation covered by the Shop Standard is covered by the AE, C-1350

-

drawings. These are in use by the field personnel.

The " Shop Quality

Assurance Manual" has recently deleted the Shop Standard requirement. The

licensee stated that the Field Quality Assurance Manual will be revised

'

to accurately reflect current practice. These items are unresolved pending

revision of the manual (352/82-04-02).

.

!

. . .

_

_

-, , _ . . , _ . . , . . - - . .

..

... --

__

-

-

l

-

.

,

.

-

..

8

5.

IE Circular Review

80-22 Investigation report 352/82-01 identified concerns with the

1"

licensee's personnel qualification verification program.

The need to perform personnel qualification verification was the

-

result of IE Circular 80-22. The inspector verified that the

licensee initiated actions to satisfy the Circular concerns within

PEC0 and its contractors. The licensee, independent of the NRC

investigation, identified problems with a quality control

inspector's credentials and has taken steps to correct the matter.

This item is closed.

.

6.

Closecut of 10 CFR 21 Reports _

The inspector verified that the licensee is aware of the following listed

10 CFR 21 items and has initiated corrective action:

,

Part 21 No.

Subject

AITS No.80-190

American Warming and

H06000527

80-195

Ventilating Actuator Defects80-333

Colt Industries Emergency

H06000539

Diesel Generator

80-215

American Warming and

H06000614

Ventilation Wiring Defects80-259

MCA Scientific Pressure

H06000671

Switches79-159

GE Connector Crimping

H06000500

80-331

PGCC Flexible Conduit

H070003086

Grounding

H070003087

.

Bergen Paterson Snubbers

H06000516

The above items are closed.

7.

Unresolved Items

Unresolved items are matters about which more infonnation is required in

order to ascertain if it is acceptable, a deviation, or a violation.

Unresolved items are discussed in paragraphs 3 and 4.

8.

Exit Interviews

,

Exit Interviews were held on February 11 and 25,1982, with members of the

licensee's staff. The inspector discussed the scope and findings of

the inspection.

a

.

. .

.

-

.