ML20050A420

From kanterella
Jump to navigation Jump to search
Responds to 810609 Request for Quarterly Updates of Projected Const Completion Date.Aug 1983 Fuel Load Date Will Not Be Met.Schedule Reassessment Underway
ML20050A420
Person / Time
Site: Catawba  Duke Energy icon.png
Issue date: 03/26/1982
From: Parker W
DUKE POWER CO.
To: Adensam E, Harold Denton
Office of Nuclear Reactor Regulation
References
NUDOCS 8204010277
Download: ML20050A420 (2)


Text

+

b DUKE PowEn COMPANY Powru Unit.oino 422 Sourn Cuuncu Srazer, Ciuniorre, N. C. 20a4a WI L LI A94 O. PA R et E R, J R.

Vect Passacrwe itLcomo=

s,...e Pnoovctio,. March 26, 1982 4 7 .

2 N 1 Mr. Harold R. Denton, Director 6g'.

Office of Nuclear Reactor Regulation -

l'Sg -

U. S. Nuclear Regulatory Commission ( Ar g?

Q Washington, D. C. 20555 Attention: Ms. E. G. Adensam, Chief -@

Licensing Branch No. 4 g g Re: Catawba Nuclear Station Docket Nos. 50-413 and 50-414

Dear Mr. Denton:

Your June 9, 1981 letter to W. S. Lee requested quarterly updates of the projected construction completion date for Catawba Unit 1. The following provides information for our third quarterly update. Erection rates of various commoditites for the December, January, and February accounting periodas are included.

Catawba Unit 1 is estimated to be 90% complete as of January 31, 1982. This completion figur? is based on the installation of key commodities such as piping, support / restraints, cables, concrete,and instrumentation.

liigh velocity flush and chemical cleaning of the condenser and associated systems began on January 5, 1982. Efforts are now being concentrated on preparing several critical systems for hydro. These include the Chemical and Volume Control (NV) System, the Ice Condenser Refrigeration (NF) System, the Nuclear Service Water (RN) System, and the Upper Head Injection (UHI)

System.

Our total Construction workforce increased from 3,670 on November 23, 1981, to 3,720 on March 14, 1982. In addition, there are 327 contractor personnel onsite. Second shift work and overtime is used where necessary to complete work on critical systems.

The following quantities of listed Unit 1 commodities were erected during the December, January, and February accounting periods (14 weeks).

Quantity Erected Quantity Remaining Commodition During Period To Be Erected Structural Concrete (cy) 1,248 882 8,430 Piping (weighted value) 3,224 574 2,574 300 3

/

Cable Pulls (each)

Cable Terminations (each) 2,362 11,653 Instruments (equivalent loops) 622 2,364 /O Piping Support / Restraints (each) 2,556 15,635 8204010277 820326 PDR ADOCK 05000413 A PDR L__

  1. 1D Mr. Harold R. Denton, Director March 26, 1982 Page 2 The slippage of mechanical systems scheduled for turnover to the Steam Production Department for functional testing and continuing problems in crecting planned numbers of support / restraints have impacted our ability to meet the published Catawba Fuel Load date of August 1983.

We are currently reassessing the Catawba Unit 1 and Unit 2 schedules at the detail level to develop a revised schedule for the project. The Design Engineering, Construction, and St'am Production Departments are reassessing the schedule logic as well as assuaptions regarding productivity, scope growth, etc.

Project milestone dates will be transmitted to the NRC as soon as this process is complete. Until this reassessment is complete, the NRC Caseload Forecast Panel projections may be used to plan licensing activities.

Very truly yours, 4 '

ws LD . .

William O. Parker, J .

ROS/php cc: J. P. O'Reilly W. H. Lovelace P. K. Van Doorn M. R. Culld Palmetto Alliance i