Discusses Plans for Termination of Projects 4 & 5.OL Application Should Be Amended to Delete Project 4 When Acceptance Review of Project 1 Is Completed in mid-Mar
ML20049J408
Person / Time
Site: Satsop, Washington Public Power Supply System
Issue date: 03/02/1982
From: Tedesco R
Office of Nuclear Reactor Regulation
To: Ferguson R
WASHINGTON PUBLIC POWER SUPPLY SYSTEM
References
NUDOCS 8203180131
Download: ML20049J408 (5)


Text

y gn-i-

w s

m a.

A u

4 DISTRIBUTION:

Docket Nos. 50-509/513 MAR 02 igg TERA NRC PDR WDi rkes Docket Nos: 50-509 Local PDR BSnyder and 50-513 HDenton EAdensam ECase RHernan J Kramer MDuncan Mr. Robert L. Ferguson, Managing Director FSchroeder OELD Washington Public Power Supply Systen DEisenhut GErtter (EDO #11454)

P.O. Box 968 RPurple MFudge Richland, Washington 99352 PPAS LStowers SHanuer OI&E (3)

Dear fir. Ferguson:

HThompson SCavanaugh PCheck

Subject:

Termination of Washington Nuclear Projects 4 and 5 RMattson RVollmer In your letter of February 1,1982, to Mr. W. J. Dircks, you discussed the Supply System's intent to maintain the structures and equipment at Washington Nuclear Project (WNP) Nos. 4 and 5 in a licensable condition at least through the period you have terr.ed Phase One and to conply with all existing construction permit conditions and requirements.

Our preliminary assessment of this decision does

, ~ _

not indicate that any additional near-term action other than that taken or planned is necessary at this time on the part of the Supply Systen.

It is our understanding that the Supply System intends to carry out the nanagement plan presented to the Region V Office on December 10, 1981, insofar as naintaining the plant equipaent and records. The NRC Resident Inspectors and Regional Inspec-tors intend to conduct their activities (inspection surveillance, audit) on both units in accordance with this plan until such time as the Supply System announces termination of phase one.

The staff has ceased its review of the operating license (0L) application for WNP-4 as you requested.

We are continuing our acceptance review of the WNP-1 OL applica-tion.

You should arend the pending application for operating licenses for WNP-1 and WNP-4 to reflect the present status of the WNP-4 project.

Because the staff expects to corplete its acceptance review for WNP-1 only by mid-March 1982, it may be advisable for you to await the outcome of that review and amend your application to delete WNP-4 at that tire. We could then docket and notice the application for an operating license for WNP-1 only. Other aspects of the termination of WNP-4 and WNP-5 could also be discussed at that time.

0m Sincerely, q,

m UQ O

t ES RFCMg s

Nginal signed b IrankJ. ugroggg,y.

O E

D OS2A Q

. fobert L. Tedesco, Assistant Director 88 gkQQg '

lA for Licensing rc;

{ Division of Licensing 0

g om

\\

N

  • NATF-RFF DRFVInHR U _

rno engri DDr er i

omc4. QL LB..#.4.

.LA:DL:LB..#4.

..DL :LB#4

. 0 ELD.

wp}.Q.ag

, DL..

  • "" ' ) *Mernan/hmcAMDuncan..

. *FMir.ag1.i a.

  • MYoung-.

.EAdensam...

'i esco-

"I 2l.19l.82

,2./19/.82

... 3/19/82.... 2/2.3/.82......

.2/ M/82.....,. 2/ h82....

NRC FORM 318 410 43OI NRC M O2 4 0 OFFICIAL RECORD COPY uw m-32n23

G.

'6 -

]

1 g'

3

(

y y

s r

a u

m l

DISTRIBUTION:

Docket Nos. 50-509/513 TERA NRC PDR WDi rkes Docket Nos: 50-509 Local PDR BSnyder HDenten EAaensam and 50-513 ECase RHernan JKramer MDuncan FSchroeder OELD Mr. Robert L. Ferguson, Managing Director DEisenhut GErtter (EDO #11454)

Washington Public Power Supply Systen P.O. Box 968 RPurple MFudge P

tw Richland, Washington 99352 3

Dear fir. Ferguson:

HThompson SCa vanaugh PCheck a

Subject:

Termination of Washington Nuclear Projects 4 and 5 er In your letter of February 1,198k to Mr. W. J. Dircks, you discussed the Supply Systen's intent to naintain the stbyctures and equipt.sent at Washington Nuclear Project (WNP) Nos. 4 and 5 in a lichnsable condition at least through the period you have terned Phase One and to codply with all existing construction permit conditions and requirements. Our preliminary assessment of this decision does not indicate that any additional nearhterm action other than that taken or planned is necessary at this time on the part of the Supply System.

It is our understanding that the Supply ystem intends to carry out the management plan presented to the Region V Office on December 10, 1981, insofar as naintaining the plant equipment and records. The NRC hesident Inspectors and Regional Inspec-tors intend to conduct their activities (inhpection surveillance, audit) on both units in accordance with this plan until such time as the Supply System announces termination of phase one.

The staff has ceased its review of the operating icense (OL) application for WNP-4 g

as you requested.

We are continuing our acceptance \\ review of the WNP-1 OL applica-tion and expect to docket the application (for WNP-lynly) in mid-March 1982, if found acceptable. At that time, the staff will discuss with the Supply Systen the steps that should be taken to revise the application, ah the application presently addresses both WNP-1 and WNP-4. We do not feel that a rAgting between the Supply System and the staff regarding the termination of WNP-4 artd WNP-5 is necessary prior to that time.

Sincerely, Robert L. Tedesco, Assistant Director for Licensing Division of Licensing

/

$,f l =" >. DL AB..!4.h.hA;D(;LB,

,,d

,1i a.

..Md.g..-

...EA,densam,,,

,,,RIed esp,,,

,,DL k,,

,,0 E L D.,

QL ;L S.. M,...

. AD,; L/.0L.....

==W..RH,e rn,a n/,hm,MDuncan,,,,

l om>

..../. j.,i..,......... 2/$.../82 '

...(.............

..../.9.../.8 2 2/

2

/82 2

...../...../. 82 2

..../. -../. 8 2.....

2 l unc ronu sia.io,eoinacu o24o OFFICIAL RECORD COPY

" 'n -sa o24

WNP Mr. R. L. Ferguson Managing Director Washington Public Power Supply System P.O. Box 968 3000 George Washington Way Richland, Washington 99352 cc: Mr. V. Mani United Engineers & Constructors, Inc.

30 South 17th Street Philadelphia, Pennsylvania 19101 Nicholas S. Reynolds, Esq.

DeBevoise & Liberman 1200 Seventeenth Street, N.W., Suite 700 Washington, D. C.

20036 Mr. E. G. Ward Senior Project Manager Babcock & Wilcox Conpany P.O. Box 1260 Lynchburg, Virginia 23505 Resident Inspector /WPPSS NPS c/o U.S. Nuclear Regulatory Cocmission P.O. Box 69 Richland, Washington 99352 Mr. R. B. Borsum Nuclear Power Generation Division Babcock & Wilcox 7910 Woodmont Avenue, Suite 220 Bethesda, Maryland 20814 G. E. Craig Doupe, Esq.

Washington Public Power Supply System 3000 George Washington Way P.O. Box 968 Richland, Washington 99352 Robert Engelken, Regional Administrator U.S. Nuclear Regulatory Commission.

l Region V i

1450 Maria Lane, Suite 210 Walnut Creek, California 94596 l

l t

?

I t

COpTROL NO.

N FROM:

ACTION CONTROL DATES COMPL OEADLINE 2[U[CE

/

d aShi o

ublic Power Supply System

^'[g" y,c,"'"'

PREPARE FOR SIGN ATURE l

TO:

f F'"^'"

i n e M~

O CHAIRMAN DirCkS A M^///'A FILE LO9ATI O EXECUTIVE OIRECTOR OT H E R,

DESCRIPTION pLETTER OMEMO O REPORT O OTHER SPECI AL INSTRUCTIONS OR REMARKS Termination of Supply System NM Nuclear Projects 4and5(WNg-4&WNP-5)

Oddl4k dutgk CLASSIFIED DATA j

OOCUMENT/ COPY NO.

CLASSIFIC ATIONl 5

NUMBER OF PAGES CATEGORY POSTAL REGISTRY NO.

O NS O RO O FRO ASSIGNED TO:

DATE INFORMATION ROUTING LEG AL REVIEW D FINAL 0 COPY

^55' "E

T :

ATE N te At B;ECri NS nontnn-NDD f/

7/7,/A9 Cunnin9 am NOTIFY:

h I

APDDnp ACTTnN

  • PDR R-Th n= = an O EOO AOuiN a CORRES eR 4s,o ns,, +

7/7/R?

Case /DentOn 6.

Check ext.

74Wu, 1.

PPAS 3.

Ma :tsOn 7.

Snyd er COMMENTS. NOTIF Y:

\\

1

//b,,1 o. / /4re/I 4.

Vollmer ext.

2.

Hanauer ttusn u m q M;LL N /

JCAE NOTIFICATION RECOMMENDED:

0 YES (O NO NRC FORM 232 p/

EXECUTIVE DIRECTOR FOR OPERATIONS DO NOT REMOVE THIS Cb#Y N

RINCIPAL CORRESPONDENCE CONTROL e

t

+

Washington Public Power Supply System P.O. Box 968 3000GeorgeWashingtonWay Richland, Washington 99352 (509)372-5000 February 1,1982 G0-1-82-0041 Docket Nos:

50-509 50-513 Mr. William J. Dircks Executive Director for Operations U. S. Nuclear Regulatory Comission Washington, D. C.

20555

Dear Mr. Dircks:

Subject:

TERMINATION OF SUPPLY SYSTEM NUCLEAR PROJECTS 4 AND 5 (WNP-4 and WNP-5)

On January 22, 1982, the Washington Public Power Supply System Board of Directors adopted a resolution terminating the Supply System's Nuclear Projects Nos. 4 and 5.

Construction work on these two (2) projects essentially was halted by the Supply System in July 1981, with the intent that an extended construction delay would continue until June 30, 1983. We advised the staff of this construction deferral by letter to Mr. H. R. Denton dated October 26, 1981.

Those projects were under construction pursuant to Construction Permits CPPR-174 and CPPR-155, respectively.

At the time that work was halted, WNP-4 was 24% complete and WNP-5 was 16% complete.

The Supply System has developed a plan for termination of these projects which contemplates two phases.

Phase One involves efforts to sell the plants intact to a new owner. The Supply System will maintain the plant structures and equipment in a licensable condition at least through

?hase One and possibly thereafter, and will comply with the conditions of the Construction Permits and the requirements of NRC regulations. We intend by and during these efforts to retain the Construction Permits.

We are willing to meet with your staff to brief it on details of the efforts contemplated.

Phase Two of the termination plan will commence only after the Supply s

System determines, subject to the rights of the Participants and Pacific Power and Light (10% owner of WNP-5), that it is no longer prudent to expect that the projects can be sold in their entirety within a reasonable time and without unreasonable expense. No definite time period has been set for completion of the first phase 6nd initiation of the second.

vt.

i W. J. Dircks Page 2 February 1,1982 WNP-4/5 Termination 1

t i

In Phase Two, plant equipment and materials will be sold or otherwise disposed of in a prudent manner, in accordance with applicable contractual and legal procedures, i

i With regard to WNP-4, the application for an Operating License for WNP-i 1 and WNP-4, including the FSAR, FER and General Information Document, i

i was submitted to the NRC on November 25, 1981. Because we intended at i

that time to resume construction of WNP-4 following the extended delay, the application addressed both WNP-1 and WNP-4.

Recent events dictate l

that the application address only WNP-1 now and until further notice.

i Very truly yours, i

-w R. L. Ferguton i

Managing Director t

GCS/sm i

cc: HR Denton NRC V Stello NRC EG Adensam NRC A Schwencer NRC RH Engelken NRC Region V NS Reynolds D&L E