Rev 5 to EOP AP-RCC.1, Continuous Control Rod Withdrawal/ Insertion
ML20045F670
Person / Time
Site: Ginna Constellation icon.png
Issue date: 06/03/1993
From: Marlow T
ROCHESTER GAS & ELECTRIC CORP.
To:
Shared Package
ML17250B293 List:
References
AP-RCC.1, NUDOCS 9307080215
Download: ML20045F670 (6)


Text

V E0P ilTLE:

AP-RCC.1 CONTINUOUS CONTROL ROD WITHDRAWAL / INSERTION PAGE 1 of 6 l

ROCHF. STER GAS AND' ELECTRIC CORPORATION GINNA STATION CONTROLLED COPY NUMBER r

l I

TECHNICAL REVIEW t

b'b O

j PORC REVIEW DATE i

~

1L4 d 6(L PLANT SUPERINTENDENT

'b b'h-h)

EFFECTIVE DATE F

t

$ATEGORY 1.0 REVIEWED BY:

.l I

93070B0215 930628 7""24:{

PDR ADOCK 05000244 P

ppg

e Ew:

fi ra.E :

l REV: 5 AP-RCC.1' CONTINUOUS CONTROL ROD WITHDRAWAL / INSERTION l

PAGE'2 of 6 10.

A.

PURPOSE - This procedure provides the steps necessary to mitigate a continuous control rod motion transient.

B.

ENTRY CONDITIONS / SYMPTOMS 1.

SYMPTOMS - The symptoms of CONTINUOUS CONTROL ROD WITHDRAWAL / INSERTION are; a.

Unwarranted Control Rod motion, or b.

Annunciator C-22, ROD WITHDRAWAL BANK D HIGH 95%,

lit, or c.

Any rod insertion limit alarm (panel C).

O 4

a 10P; TITLE:

REV: 5 AP-RCC.1 CONTINUOUS CONTROL ROD WITHDRAWAL / INSERTION PAGE 3 of 6 s

ACTION / EXPECTED RESPONSE RESPONSE NOT OBTAINED STEP CAUTION o IF AT ANY TIME DURING THIS PROCEDURE, A REACTOR TRIP OR SI OCCURS, THEN E-0, REACTOR TRIP OR SAFETY INJECTION, SHALL BE PERFORMED.

o IF ROD INSERTION IS OCCURRING, VERIFY THAT IN MOTION IS NOT REQUIRED BEFORE CONTINUING WITH THIS PROCEDURE.

                                                                              • +*

NOTE:

Step 1 is an IMMEDIATE ACTION step.

Evaluate Rod Control System Operability:

a.

Place Rod Control Bank Selector Switch to MANUAL

b. Verify control rod notion stops
b. Manually trip the reactor and go O

to E-0, REACTOR TRIP or SAFETY INJECTION.

I

!(

' )

top:

111LE:

REV: 5 AP-RCC.1 CONTINUOUS CONTROL ROD WITHDRAWAL / INSERTION PAGE 4 of 6 O

ACTION / EXPECTED RESPONSE RESPONSE NOT OBTAINED STEP CAUTION IF ANY INSTRUMENT CHANNEL FAILURE INDICATED, THEN EVALUATE OTHER INPUTS TO TAVG AND TREF TO DETERMINE REQUIRED ACTIONS.

Verify Tavg - TRENDING TO TREF l Manually operate control rods 2

and/or adjust turbine load as necessary to restore Tavg to normal.

3 Verify Control Rods Operable In Manual:

a. Insert / withdraw control rods to MRPI transition
b. Verify MRPI indicates control
b. Consult Plant Staff and Tech rod motion Spec section 3,10 to determine operability of rod control system and go to Step 4
c. Restore control rods to desired position 4 Check RCS Tavg Channel IE any Tavg channel malfunction is Indications:

indicated. THEN refer to ER-INST.1, REACTOR PROTECTION BISTABLE DEFEAT o All 4 channels indicate AFTER INSTRUMENTATION LOOP FAILURE.

approximately the same value o All 4 channels responding to the power change O

)-

^

E0P:

TITLE:

REV: 5 AP-RCC.1 CONTINUOUS CONTROL ROD WITHDRAWAL / INSERTION PAGE 5 of 6 O

ACTION / EXPECTED RESPONSE RESPONSE NOT OBTAINED STEP 5 Check Turbine 1st Stage H PI-485 malfunction is indicated, Pressure Channel, PI-485 -

THEN refer to ER-INST.1, REACTOR APPROXIMATELY EQUAL TO PI-486 PROTECTION BISTABLE DEFEAT AFTER INSTRUMENTATION LOOP FAILURE.

6 Check NIS PR Indication:

H a NIS PR channel malfunction is indicated, THEN defeat affected o All PR total channel indicators channel (refer to ER-NIS.3, PR

- APPROXIMATELY EQUAL MALFUNCTION).

o All AI indicators -

}

APPROXIMATELY EQUAL 7 Establish Stable Plant Conditions:

a.

Tavg - TRENDING TO TREF a.

Insert control rods or, if O*

necessary, adjust turbine load to match Tavg to Tref.

b. PRZR pressure - TRENDING TO b Verify proper operation of PRZR 2235 PSIG heaters and spray or take manual control of PRZR pressure controller 431R.

E pressure can NOT be centrolled. THEN refer to AP-PRZR.1, ABNORMAL PRESSURIZER PRESSURE.

c. PRZR IcVel - TRENDING TO PROGRAM
c. Verify proper operation of charging pump speed controllers or take manual control of speed controllers to control PRZR level.

I

d. Rod insertion limit alarms -
d. Borate as necessary and withdraw EXTINGUISHED control rods to clear insertion limit alarms (refer to affected rod bank alarm response procedures if necessary),
e. NIS PR AI - WITHIN i 5% OF
e. Borate / dilute to restore AI to TARGET VALUE within limits.

O

m

~>

(OP3 IIILE:

-j REV: 5 AP-RCC.1 CONTINUOUS CONTROL ROD WITHDRAWAL / INSERTION PAGE 6 of 6 i

ACTION / EXPECTED RESPONSE RESPONSE NOT OBTAINED STEP i

NOTE: Refer to Technical Specification 3.10 for control rod operability l

d requirements.

8 Notify Higher Supervision l

9 Return To Procedure Or Guidance In Effect'

[

l

-END-t k