MONTHYEARNPL-99-0569, Monthly Operating Repts for Sept 1999 for Pbnp,Units 1 & 2. with1999-09-30030 September 1999 Monthly Operating Repts for Sept 1999 for Pbnp,Units 1 & 2. with NPL-99-0051, Monthly Operating Repts for Aug 1999 for Pbnp,Units 1 & 2. with1999-08-31031 August 1999 Monthly Operating Repts for Aug 1999 for Pbnp,Units 1 & 2. with NPL-99-0449, Monthly Operating Repts for July 1999 for Pbnp,Units 1 & 2. with1999-07-31031 July 1999 Monthly Operating Repts for July 1999 for Pbnp,Units 1 & 2. with ML20209D2691999-06-30030 June 1999 Monthly Operating Repts for June 1999 for Pbnps,Units 1 & 2 NPL-99-0328, Monthly Operating Repts for May 1999 for Pbnp,Units 1 & 2. with1999-05-31031 May 1999 Monthly Operating Repts for May 1999 for Pbnp,Units 1 & 2. with ML20209D2751999-05-31031 May 1999 Revised MORs for May 1999 for Pbnps,Units 1 & 2 NPL-99-0273, Monthly Operating Repts for Apr 1999 for Point Beach Nuclear Plant,Units 1 & 2.With1999-04-30030 April 1999 Monthly Operating Repts for Apr 1999 for Point Beach Nuclear Plant,Units 1 & 2.With NPL-99-0193, Monthly Operating Repts for Mar 1999 for Pbnp,Units 1 & 2. with1999-03-31031 March 1999 Monthly Operating Repts for Mar 1999 for Pbnp,Units 1 & 2. with NPL-99-0134, Monthly Operating Repts for Feb 1999 for Pbnp,Units 1 & 2. with1999-02-28028 February 1999 Monthly Operating Repts for Feb 1999 for Pbnp,Units 1 & 2. with NPL-99-0008, Monthly Operating Repts for Dec 1998 for Pbnp,Units 1 & 2. with1998-12-31031 December 1998 Monthly Operating Repts for Dec 1998 for Pbnp,Units 1 & 2. with NPL-98-1006, Monthly Operating Repts for Nov 1998 for Point Beach Nuclear Plant,Units 1 & 2.With1998-11-30030 November 1998 Monthly Operating Repts for Nov 1998 for Point Beach Nuclear Plant,Units 1 & 2.With NPL-98-0948, Monthly Operating Repts for Oct 1998 for Point Beach Nuclear Plant,Units 1 & 2.With1998-10-31031 October 1998 Monthly Operating Repts for Oct 1998 for Point Beach Nuclear Plant,Units 1 & 2.With NPL-98-0826, Monthly Operating Repts for Sept 1998 for Point Beach Nuclear Plant,Units 1 & 2.With1998-09-30030 September 1998 Monthly Operating Repts for Sept 1998 for Point Beach Nuclear Plant,Units 1 & 2.With ML20151W3851998-08-31031 August 1998 Monthly Operating Repts for Aug 1998 for Pbnp Units 1 & 2 ML20151W4541998-07-31031 July 1998 Corrected Page to MOR for July 1998 for Pbnp Unit 1 ML20151W4471998-07-31031 July 1998 Corrected Page to MOR for July 1998 for Pbnp Unit 2 NPL-98-0653, Monthly Operating Repts for July 1998 for Point Beach Nuclear Plant,Units 1 & 21998-07-31031 July 1998 Monthly Operating Repts for July 1998 for Point Beach Nuclear Plant,Units 1 & 2 NPL-98-0558, Monthly Operating Repts for June 1998 for Pbnp,Units 1 & 21998-06-30030 June 1998 Monthly Operating Repts for June 1998 for Pbnp,Units 1 & 2 ML20151W4261998-06-30030 June 1998 Corrected Page to MOR for June 1998 for Pbnp Unit 2 ML20151W4221998-05-31031 May 1998 Corrected Page to MOR for May 1998 for Pbnp Unit 2 NPL-98-0481, Monthly Operating Repts for May 1998 for Point Beach Nuclear Plant,Units 1 & 21998-05-31031 May 1998 Monthly Operating Repts for May 1998 for Point Beach Nuclear Plant,Units 1 & 2 ML20151W4011998-04-30030 April 1998 Corrected Page to MOR for April 1998 for Pbnp Unit 2 NPL-98-0356, Monthly Operating Repts for April 1998 for Point Beach Nuclear Plant,Units 1 & 21998-04-30030 April 1998 Monthly Operating Repts for April 1998 for Point Beach Nuclear Plant,Units 1 & 2 ML20216D7071998-03-31031 March 1998 Monthly Operating Repts for Mar 1998 for Point Beach Nuclear Plant,Units 1 & 2 ML20151W3981998-03-31031 March 1998 Corrected Page to MOR for March for Pbnp Unit 2 NPL-98-0159, Monthly Operating Repts for Feb 1998 for Point Beach Nuclear Plant,Units 1 & 21998-02-28028 February 1998 Monthly Operating Repts for Feb 1998 for Point Beach Nuclear Plant,Units 1 & 2 ML20151W3891998-02-28028 February 1998 Corrected Page to MOR for Feb 1998 for Pbnp Unit 2 ML20216D7121998-02-28028 February 1998 Revised Corrected MOR for Feb 1998 for Point Beach Nuclear Plant,Unit 2 NPL-98-0084, Monthly Operating Repts for Jan 1998 for Point Beach Nuclear Plant,Units 1 & 21998-01-31031 January 1998 Monthly Operating Repts for Jan 1998 for Point Beach Nuclear Plant,Units 1 & 2 ML20198M2251997-12-31031 December 1997 Monthly Operating Repts for Dec 1997 for Point Beach Nuclear Plant,Units 1 & 2 ML20198M2331997-11-30030 November 1997 Corrected Monthly Operating Repts for Nov 1997 for Point Beach Nuclear Plant,Units 1 & 2 ML20203F9171997-11-30030 November 1997 Monthly Operating Repts for Nov 1997 for Point Beach Nuclear Plant,Units 1 & 2 NPL-97-0715, Monthly Operating Repts for Oct 1997 for Point Beach Nuclear Plant,Units 1 & 21997-10-31031 October 1997 Monthly Operating Repts for Oct 1997 for Point Beach Nuclear Plant,Units 1 & 2 ML20203F9361997-10-31031 October 1997 Revised Monthly Operating Rept for Oct 1997 for Point Beach Nuclear Plant,Unit 2 NPL-97-0621, Monthly Operating Repts for Sept 1997 for Point Beach Nuclear Plant,Units 1 & 21997-09-30030 September 1997 Monthly Operating Repts for Sept 1997 for Point Beach Nuclear Plant,Units 1 & 2 ML20203F9311997-09-30030 September 1997 Revised Monthly Operating Rept for Sept 1997 for Point Beach Nuclear Plant,Unit 2 NPL-97-0553, Monthly Operating Repts for Aug 1997 for Point Beach Nuclear Plant,Units 1 & 21997-08-31031 August 1997 Monthly Operating Repts for Aug 1997 for Point Beach Nuclear Plant,Units 1 & 2 ML20203F9261997-08-31031 August 1997 Revised Monthly Operating Rept for Aug 1997 for Point Beach Nuclear Plant,Unit 2 ML20210H9531997-07-31031 July 1997 Monthly Operating Repts for Jul 1997 for Point Beach Nuclear Plant,Units 1 & 2 ML20210H9601997-06-30030 June 1997 Revised Monthly Operating Rept for June 1997 for Point Beach Nuclear Plant,Units 1 & 2,which Provides Corrected Forced Outage Rates NPL-97-0318, Monthly Operating Repts for May 1997 for Point Beach Nuclear Plant,Unit 1 & 21997-05-31031 May 1997 Monthly Operating Repts for May 1997 for Point Beach Nuclear Plant,Unit 1 & 2 ML20141C2381997-04-30030 April 1997 Monthly Operating Repts for Apr 1997 for Point Beach Nuclear Plant,Units 1 & 2 ML20141C2461997-03-31031 March 1997 Corrected Operating Data Rept for Mar 1997 for Point Beach Nuclear Plant,Unit 1 ML20137P5781997-03-31031 March 1997 Monthly Operating Repts for March 1997 for Point Beach Nuclear Plant Units 1 & 2 ML20137P5711997-02-28028 February 1997 Corrected MOR for Feb 1997 for Point Beach Nuclear Plant Unit 1 ML20135F2721997-02-28028 February 1997 Monthly Operating Repts for Feb 1997 for Point Beach Nuclear Plant,Units 1 & 2 ML20134J8711997-01-31031 January 1997 Monthly Operating Repts for Jan 1996 for Point Beach Nuclear Plant,Units 1 & 2 ML20135F2771997-01-31031 January 1997 Revised Monthly Operating Rept for Jan 1997 for Point Beach Nuclear Plant,Unit 2 ML20133N0601996-12-31031 December 1996 Revised MOR Rept for Dec 1996 for Point Beach Nuclear Plant, Units 1 & 2 ML20133F6471996-12-31031 December 1996 Monthly Operating Repts for Dec 1996 for Point Beach Nuclear Plant,Unit 1 & 2 1999-09-30
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARNPL-99-0569, Monthly Operating Repts for Sept 1999 for Pbnp,Units 1 & 2. with1999-09-30030 September 1999 Monthly Operating Repts for Sept 1999 for Pbnp,Units 1 & 2. with ML20212D5961999-09-15015 September 1999 Safety Evaluation Supporting Licensee IPEEE Process.Plant Has Met Intent of Suppl 4 to GL 88-20 NPL-99-0051, Monthly Operating Repts for Aug 1999 for Pbnp,Units 1 & 2. with1999-08-31031 August 1999 Monthly Operating Repts for Aug 1999 for Pbnp,Units 1 & 2. with NPL-99-0449, Monthly Operating Repts for July 1999 for Pbnp,Units 1 & 2. with1999-07-31031 July 1999 Monthly Operating Repts for July 1999 for Pbnp,Units 1 & 2. with ML20196J4251999-06-30030 June 1999 Safety Evaluation Authorizing Proposed Alternatives Described in Relief Requests VRR-01,ROJ-16,PRR-01 & VRR-02 ML20209D2691999-06-30030 June 1999 Monthly Operating Repts for June 1999 for Pbnps,Units 1 & 2 ML20196F3341999-06-22022 June 1999 Safety Evaluation for Implementation of 422V+ Fuel Assemblies at Pbnp Units 1 & 2 ML20195F9781999-06-10010 June 1999 Unit 2 Refueling 23 Inservice Insp Summary Rept for Form NIS-1 ML20209D2751999-05-31031 May 1999 Revised MORs for May 1999 for Pbnps,Units 1 & 2 NPL-99-0328, Monthly Operating Repts for May 1999 for Pbnp,Units 1 & 2. with1999-05-31031 May 1999 Monthly Operating Repts for May 1999 for Pbnp,Units 1 & 2. with NPL-99-0273, Monthly Operating Repts for Apr 1999 for Point Beach Nuclear Plant,Units 1 & 2.With1999-04-30030 April 1999 Monthly Operating Repts for Apr 1999 for Point Beach Nuclear Plant,Units 1 & 2.With ML20196F3521999-04-30030 April 1999 Non-proprietary WCAP-14788, W Revised Thermal Design Procedure Instrument Uncertainty Methodology for Wepc Point Beach Units 1 & 2 (Fuel Upgrade & Uprate to 1656 Mwt - NSSS Power) NPL-99-0193, Monthly Operating Repts for Mar 1999 for Pbnp,Units 1 & 2. with1999-03-31031 March 1999 Monthly Operating Repts for Mar 1999 for Pbnp,Units 1 & 2. with NPL-99-0134, Monthly Operating Repts for Feb 1999 for Pbnp,Units 1 & 2. with1999-02-28028 February 1999 Monthly Operating Repts for Feb 1999 for Pbnp,Units 1 & 2. with ML20207D6751999-02-22022 February 1999 Assessment of Design Info on Piping Restraints for Point Beach Nuclear Plant,Units 1 & 2.Staff Concludes That Licensee Unable to Retrieve Original Analyses That May Have Been Performed to Justify Removal of Shim Collars ML20206R9001999-01-13013 January 1999 SER Accepting Nuclear Quality Assurance Program Changes for Point Beach Nuclear Plant,Units 1 & 2 NPL-99-0008, Monthly Operating Repts for Dec 1998 for Pbnp,Units 1 & 2. with1998-12-31031 December 1998 Monthly Operating Repts for Dec 1998 for Pbnp,Units 1 & 2. with NPL-99-0091, 1998 Annual Results & Data Rept for Pbnps,Units 1 & 2. with1998-12-31031 December 1998 1998 Annual Results & Data Rept for Pbnps,Units 1 & 2. with ML20198C7671998-12-10010 December 1998 Safety Evaluation Accepting Licensee Proposed Alternative to ASME BPV Code,1986 Edition,Section XI Requirement IWA-2232, to Use Performance Demonstration Initiative Program During RPV Third 10-yr ISI for Plant,Unit 2 NPL-98-1006, Monthly Operating Repts for Nov 1998 for Point Beach Nuclear Plant,Units 1 & 2.With1998-11-30030 November 1998 Monthly Operating Repts for Nov 1998 for Point Beach Nuclear Plant,Units 1 & 2.With ML20195J5101998-11-16016 November 1998 Proposed Revs to Section 1.3 of FSAR for Pbnp QA Program ML20198J5941998-11-0303 November 1998 1998 Graded Exercise,Conducted on 981103 NPL-98-0948, Monthly Operating Repts for Oct 1998 for Point Beach Nuclear Plant,Units 1 & 2.With1998-10-31031 October 1998 Monthly Operating Repts for Oct 1998 for Point Beach Nuclear Plant,Units 1 & 2.With NPL-98-0880, Special Rept:On 980913,fire Alarm Control Panels Inoperable for More That Fourteen Days.Troubleshooting of D-401 Panel Following Installation of Replacement Batteries Revealed No Apparent Cause for Spurious Alarms.Panel D-401 Restored1998-10-21021 October 1998 Special Rept:On 980913,fire Alarm Control Panels Inoperable for More That Fourteen Days.Troubleshooting of D-401 Panel Following Installation of Replacement Batteries Revealed No Apparent Cause for Spurious Alarms.Panel D-401 Restored ML20154M9121998-10-14014 October 1998 Unit 1 Refueling 24 Repair/Replacement Summary Rept for Form NIS-2 ML20154L6751998-10-14014 October 1998 Unit 1 Refueling 24 ISI Summary Rept for Form NIS-1 NPL-98-0826, Monthly Operating Repts for Sept 1998 for Point Beach Nuclear Plant,Units 1 & 2.With1998-09-30030 September 1998 Monthly Operating Repts for Sept 1998 for Point Beach Nuclear Plant,Units 1 & 2.With ML20151W3851998-08-31031 August 1998 Monthly Operating Repts for Aug 1998 for Pbnp Units 1 & 2 NPL-98-0653, Monthly Operating Repts for July 1998 for Point Beach Nuclear Plant,Units 1 & 21998-07-31031 July 1998 Monthly Operating Repts for July 1998 for Point Beach Nuclear Plant,Units 1 & 2 ML20151W4471998-07-31031 July 1998 Corrected Page to MOR for July 1998 for Pbnp Unit 2 ML20151W4541998-07-31031 July 1998 Corrected Page to MOR for July 1998 for Pbnp Unit 1 ML20236Q3161998-07-10010 July 1998 Safety Evaluation Accepting Licensee Proposed Alternative to ASME Code Requirements PTP-3-01 & PTP-3-02 ML20236L6771998-07-0707 July 1998 Safety Evaluation Approving Wepco Implementation Program to Resolve USI A-46 at Point Beach NPP Units 1 & 2 NPL-98-0558, Monthly Operating Repts for June 1998 for Pbnp,Units 1 & 21998-06-30030 June 1998 Monthly Operating Repts for June 1998 for Pbnp,Units 1 & 2 ML20151W4261998-06-30030 June 1998 Corrected Page to MOR for June 1998 for Pbnp Unit 2 ML20151W4221998-05-31031 May 1998 Corrected Page to MOR for May 1998 for Pbnp Unit 2 NPL-98-0481, Monthly Operating Repts for May 1998 for Point Beach Nuclear Plant,Units 1 & 21998-05-31031 May 1998 Monthly Operating Repts for May 1998 for Point Beach Nuclear Plant,Units 1 & 2 ML20151W4011998-04-30030 April 1998 Corrected Page to MOR for April 1998 for Pbnp Unit 2 NPL-98-0356, Monthly Operating Repts for April 1998 for Point Beach Nuclear Plant,Units 1 & 21998-04-30030 April 1998 Monthly Operating Repts for April 1998 for Point Beach Nuclear Plant,Units 1 & 2 ML20217F3131998-04-17017 April 1998 Safety Evaluation Accepting Proposed Alternative to ASME Code for Surface Exam of Nonstructural Seal Welds,For Plant, Unit 1 ML20216D7071998-03-31031 March 1998 Monthly Operating Repts for Mar 1998 for Point Beach Nuclear Plant,Units 1 & 2 ML20151W3981998-03-31031 March 1998 Corrected Page to MOR for March for Pbnp Unit 2 NPL-98-0209, Special Rept Re Fire Barrier Inoperable for Greater than Seven Days.Compensatory Measures Implemented in Accordance W/Fire Protection Program Requirements During Time That Barriers Were Inoperable1998-03-30030 March 1998 Special Rept Re Fire Barrier Inoperable for Greater than Seven Days.Compensatory Measures Implemented in Accordance W/Fire Protection Program Requirements During Time That Barriers Were Inoperable ML20217A8501998-03-19019 March 1998 SER Accepting Proposed Changes Submitted on 980226 by Wiep to Pbnp Final SAR Section 1.8 Which Will Impact Commitments Made in Pbnp QA Program Description.Changes Concern Approval Authority for Procedures & Interviewing Authority ML20216J0101998-03-17017 March 1998 Safety Evaluation Accepting Third 10-yr Inservice Insp Interval Relief Request RR-1-18 for Plant NPL-98-0159, Monthly Operating Repts for Feb 1998 for Point Beach Nuclear Plant,Units 1 & 21998-02-28028 February 1998 Monthly Operating Repts for Feb 1998 for Point Beach Nuclear Plant,Units 1 & 2 ML20151W3891998-02-28028 February 1998 Corrected Page to MOR for Feb 1998 for Pbnp Unit 2 ML20216D7121998-02-28028 February 1998 Revised Corrected MOR for Feb 1998 for Point Beach Nuclear Plant,Unit 2 NPL-98-0084, Monthly Operating Repts for Jan 1998 for Point Beach Nuclear Plant,Units 1 & 21998-01-31031 January 1998 Monthly Operating Repts for Jan 1998 for Point Beach Nuclear Plant,Units 1 & 2 ML20198L1151998-01-0808 January 1998 SER Accepting Licensee Response to GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves, for Point Beach Nuclear Plant,Units 1 & 2 1999-09-30
[Table view] |
Text
,..
Wisconsin Electnc POWER COMPANY 231 W. M:chgan PC. Box 2046. Mdwoukee. W! 53201 (414)221-2345 VPNPD 0 61 NRC 0 3 6 March 8, 1993 Document Control Desk U.S. NUCLEAR REGULATORY COMMISSION Mail Station F1-137 Washington, D.C. 20555 Centlemen: ,
DOCKETS 50-266 AND 50-301 MONTHLY OPERATING REPORTS POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 Attached are monthly operating reports for Units 1 and 2 of the ,
Point Beach Nuclear Plant for the calendar month of Januar-y 1993.
&b/voftl Sincerely, (f (
/
y t
Bob Link Vice President Nuclear Power MFB/jg cc: L. L. Smith, PSCW NRC Regional Administrator, Region III NRC Resident Inspector
.l i
9303160321 930228 DR ADDCKOSOOg6 ,g .g .
pp-
[ OPERATIWG DATA REPORT DOCKET No. 50-266 -
~
DATE: 03/05/93 COMPLETED BY: Richard F. Arnold TELEPHONE: 755-2321 ext.193 OPERATING STATUS
- 1. UNIT NAME POINT BEACH NUCLEAR PLANT - UNIT 1 . NOTES .
- 2. REPORTING PERIOD: February - 1993 . .
- 3. LICENSED THERMAL POWER (MWT): 1518.5 . .
- 4. NAMEPLATE RATING (GROSS MWE) 523.8 . . .
- 5. DESIGN ELECTRICAL RATING (NET MWE): 497.0 . .
- 6. MAXIMUM DEPENDABLE CAPACITY (GROSS MWE): 509.0 . .
- 7. MAXIMUM DEPENDABLE CAPACITY (NET MWE): 485.0 . . . . . . . . . . . . . . . . . .
- 8. IF CHANGES _ OCCUR IN CAPACITY RATINGS (ITEMS 3 THROUGH 7) SINCE LAST REPORT, GIVE REASONS:
na
- 9. POWER LEVEL TO WHICH RESTRICTED, IF ANY (NET MWE): na
- 10. REASONS FOR RESTRICTIONS, (IF ANY)*
na THIS MONTH YEAR TO DATE CUMULATIVE
- 11. HOURS IN REPORTING PERIOD 672.0 1,416.0 195,624.0
- 12. NUMBER ~OF HOURS REACTOR WAS CRITICAL 672.0 1,416.0 162,299.3 13.. REACTOR RESERVE SHUTDOWN HOURS 0.0 0.0 667.3.
- 14. HOURS GENERATOR ON LINE 672.0 1,416.0 159,255.4
- 15. UNIT RESERVE: SHUTDOWN HOURS 0.0 0.0 846.9
- 16. GROSS THERMAL ENERGY GENERATED (MWH) 1,018,667 2,147,575 223,884,548
- 17. GROSS ELECTRICAL ENERGY GENERATED 344,470 726,170 75,602,570 18.. NET ELECTRICAL ENERGY GENERATED (MWH) 330,301 696,336- 72,048,499
- 19. UNIT SERVICE FACTOR 100.0% 100.0% 81.4%
- 20. UNIT AVAILABILITY FACTOR 100.0% 100.0% 81.8%
- 21. UNIT CAPACITY FACTOR (USING MDC NET) 101.3% 101.4% 75.6%
- 22. UNIT CAPACITY FACTOR (USING DER NET) 98.9% 98.9% 74.1%
23.-UNIT FORCED OUTAGE RATE 0.0% 0.0% 1.7%
- 24. SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS (TYPE, DATE, AND DURATION OF EACH):
Refueling Outage 3/27/93-5/13/93'(47 Days)
~25. IF~ SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP:
na DATA REPORTED AND' FACTORS. CALCULATED AS REQUESTED IN NRC LETTER DATED SEPTEMBER 22, 1977 M
- ,w+
= -- ~ , . . - ~ ~ , , v .w.x
- v-, ~-c i + .-.w - ,- w , .w-- . ~ . - = , .-. -. -- -- 4-- - _ ~ . s_ e
DOCKET NO. 50-266 POINT BEACH NUCLEAR PLANT .
UNIT NAME Point Beach.' Unit 1 AVERAGE DAILY UNIT POWER LEVEL DATE March 5.1993 '
MONTH FEBRUARY - 1993 COMPLETED BY R. F. Amold TELEPHONE 414/755-2321 AVERAGE AVERAGE DAILY AVERAGE DAILY POWER LEVEL DAILY POWER LEVEL - MWe NET ___
POWER LEVEL D
__f0[
MWe NET MWe NET DE DE 21 492 11 492 494 1 490 493 22 t
12 2 493 491 23 492 13
-3 491 24 490 493 14 4 493 491 25 -
493 15 5 491 26 494 16 493 F 6 493 27 492 493 17 7 470~
493 28 18 492 8 494 19 491 9 493 493 20 10 '494 s
PBF.0028e
. . - ~ ~ . -- .. ~ . . = . . - . . . . . . ~ ~ , , --. . . , . . . - , . . . , ,. . .. . . . . . . . . - . . - ...:---_ . - .-. .
POINT BEACH NUCLEAR PLANT Daket No.. 50-266 Unit Name Point Beach. Unit 1 .
~
UNIT SHUTDOWNS AND POWER REDUCTIONS Date March 5.1993 -
Completed By R. F. Amold -
REPORT MONTH FEBRUARY - 1993 Telephone No. 414/755-2321. Ext.193 Method of '
Shuning No. Date Type
- Down Licensee Event System Component Cause and Conective Action 4
2
'F: Forced Reason: ' Method: ' Exhibit G - Instructions S: Scheduled A - Equipment Failure (explain) 1 - Manual for preparation of B - Maintenance or Testing 2 - Manual Scram data entry sheets C - Refueling ' 3 - Automatic Scram LER file (NUREG-0161)
D - Regulatory Restriction 4 '- Continuation of E - Operator Training & Previous Shutdown Licensing Exam 5 - Reduced lead F - Administrative 6 - Other (explain) ' Exhibit I - Same Source G _- Operational Error (explain)
H - Other (explain)
PBFM8b (03-90)
. _ . . . . _- . - . - . . . . . . . , . . . - , . - _ - . - _ . . . _ . - . -. _ . . . ~ . - . . .-_...._. _ __.-..__ .__ _ - - - _ - _ -
DOCKET No. 50-266 ;
UNIT NAME Point Beach Unit 1 -
DATE March 5, 1993 COMPLETED BY R. F.: Arnold '
TELEPHONE 414/755-2321, Ext. 193 i
Unit 1 operated at approximately 492 MWe net throughout the report period with no significant load reductions. ,
i During the annual maintenance overhaul of G01 emergency diesel generator the ethylene glocal in the engine was replaced with treated water containing a rust inhibitor. G01 was rerated to original FSAR values when it was returned to service on February ,
25, 1993.
Licensee Event Report 266/93-001-00 was submitted.
Safety-related maintenance included:
- 1. Repositioned pins on latch check switches of eight 4160 V safeguards breakers. .
- 2. Completed annual maintenance overhaul of the G01 emergency diesel.
t P
1 6
i
\cs _ _
t? h OPERATI2G DATA REPORT DOCKET NO. 50-301 -
DATE: 03/05/93 COMPLETED BY Richard F. Arnold
- TELEPHONE: 755-2321 ext.193 OPERATING STATUS
- 1. UNIT NAME: POINT BEACH NUCLEAR PLANT - UNIT 2 . NOTES .
- 2. REPORTING PERIOD: February - 1993 . -.
- 3. LICENSED THERMAL POWER (MWT): 1518.5 . .
- 4. NAMEPLATE RATING (GROSS MWE): 523.8 . .
- 5. DESIGN ELECTRICAL RATING (NET MWE): 497.0 . .
6.-MAXIMUM DEPENDABLE CAPACITY (GROSS MWE): 509.0 . .
- 7. MAXIMUM DEPENDABLE CAPACITY (NET MWE): 485.0
- 8. IF CHANGES OCCUR IN CAPACITY RATINGS (ITEMS 3 THROUGH 7) SINCE LAST REPORT, GIVE REASONS:
na
- 9. POWER LEVEL TO WHICH RESTRICTED, IF ANY (NET'MWE): na
- 10. REASONS FOR RESTRICTIONS,'(IF ANY): '
na THIS MONTH YEAR TO DATE CUMULATIVE
- 11. HOURS IN REPORTING PERIOD 672.0 1,416.0 180,409.0
- 12. NUMBER OF HOURS REACTOR WAS CRITICAL 672.0 1,416.0 ~157,691.9
- 13. REACTOR RESERVE SHUTDOWN Hobas 0.0 0.0 229.9
- 14. HOURS. GENERATOR ON LINE 672.0 1,416.0 155,398.5 15.. UNIT RESERVE SHUTDOWN HOURS 0.0 0.0 302.2
- 16. GROSS THERMAL ENERGY GENERATED (MWH) 1,003,337 2,120,292 222,766,553
- 17. GROSS ELECTRICAL. ENERGY GENERATED 344,570 728,260 75,728,380
- 18. NET ELECTRICAL ENERGY GENERATED (MWH) 330,155 697,899 72,184,306
- 19. UNIT SERVICE FACTOR 100.0% 100.0% 86.1%
- 20. UNIT AVAILABILITY FACTOR 100.0% 100.0% 86.3%
- 21. UNIT CAPACITY FACTOR (USING MDC NET) 101.3% .101.6% 81.9%
- 22. UNIT CAPACITY FACTOR (USING DER NET) 98.9% 99.2% 80.5%
- 23. UNIT FORCED OUTAGE RATE 0.0% 0.0% 1.0%.
- 24. SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS (TYPE,.DATE, AND DURATION OF EACH):
na 25..IF; SHUTDOWN AT END OF PEPORT PERIOD, ESTIMATED DATE OF STARTUP:
na DATA REPORTED AND FACTORS CALCULATED.AS REQUESTED'IN NRC LETTER DATED SEPTEMBER 22, 1977
~.. ._ . - - . _ . - . . ~ . = _ - . ..- -. _ ...-_ - . - .
POINT BEACII NUCLEAR PLANT DOCKET NO. 50-301 ,
AVERAGE DAILY UNIT POWER LEVEL UNIT NAME Point Beach. Unit 2 MONTH FEBRUARY - 1993 DATE March 5.1993' COMPLETED BY R. F. Arnold TELEPHONE 414/755-2321 AVERAGE AVERAGE AVERAGE DAILY DAILY DAILY POWER LEVEL POWER LEVEL POWER LEVEL -
PR MWe NET _DR MWe NET DE MWe NET 1 496 11 494 21 4%
2 494 12~ 495 22 493 t
3 494 13 494 23 494 4 496 14 495 24 494 5 494 15 495 25 494 6 495 16 499 26 495 7 496 17 495 27 494 8 496 18 490 28 395 9' 495 19 494 10 - 497 20 495 l'
i PBF-0028a (03-90) 1
.- . . _ . , _ , , _. ._. _. . . . . . . . . . . , .._ m . _ . - - . . . . . _ .. . _ . . - . . . . _ . . , . ,, . . . . . . - . . _ ..
POINT BEACH NUCLEAR PLANT Dockct No. 50-301 Unit Name Point Beach. Unit 2 .
UNIT STIUTDOWNS AND POWER REDUCTIO?iS Date l' arch 5.1993 Completed By R. F. Arnold .
REPORT MONTH FEBRUARY - 1993 Telephone No. 414/755-2321. Ext.193 Method of Shutting Duration Down 13censee Event System Cornpones Cause and Corrective Action y No. Dew - Type' - (Hours) Reason' pe g Report No. Code' Code' To Prevent Recunence t 2r28N3 F 0 A 5 IF INSTRU Fai!ure of pressure transmittee which provides an input signal to the feedwater turbine trip c:rcuit. The pressure transmitter was replaced.
I 2
'F: Forced Reason: ' Method:
. S: Scheduled A - Equipment Failure (explain) 1 - Manual for preparation of B - Maintenance or Testing 2 - Manual Scram data entry sheets C_- Refueling 3 - Automatic Scram LER file (NUREG-0161)
D - Regulatory Restriction 4 - Continuation of E - Operator Training & - Previous Shutdown Licensing Exam 5 - Reduced Load F - Administrative 6 - Other (explain) ' Exhibit I - Same Source G - Operational Error (explain)
H - Other (explain) i PBF-00286
. (03-90)
DOCKET NO. 50-301 UNIT NAME Point Beach Unit 2 DATE March 5, 1993 COMPLETED BY R. F. Arnold TELEPHONE 414/755-2321, Ext. 193 Unit 2 operated at approximately 491 Mwe net throughout the report period with one significant load reduction because of the failure of a pressure transmitter which.provides input to the-feedwater turbine trip circuit (AMSAC).
Licensee Event Reports 301/92-006-01 and 301/93-001-00 were submitted.
Safety-related maintenance included:
- 1. Repositioned pins on latch check switches of four 4160 V safeguards breakers.
- 2. Replaced Loop "A" reactor coolant flow low bistable.
<