Forwards Request for Addl Info Re Containment Liner Weld Channels for Plant,Per 871227 Response to Insp Rept 50-302/87-38.Response Requested within 60 Days of Ltr Date
ML20043G230
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 06/13/1990
From: Silver H
Office of Nuclear Reactor Regulation
To: Beard P
FLORIDA POWER CORP.
References
TAC-76464, NUDOCS 9006200072
Download: ML20043G230 (3)


See also: IR 05000302/1987038

Text

"

June 13, 1990

.

Docket No. 50 302

DISTRIBUTION

SPChan 7/H/15

Docket File-

'

NRC & LPDRs

PD22 Rdg File

Mr. Percy M. Beard, Jr.

SVarga 14/E/4

Senior Vice President,

Glainas 14/H/3

Nuclear Operations

HBerkow

Florida Power Corporation

DMiller

ATTN: Manager, Nuclear Operations

GWunder

Licensing

HSilver

P. O. Box 219-NA-21

OGC

Crystal River, Florida 32629

EJordan MNBB-3302

ACRS(10)

Dear Mr. Beard:

MSinkule RII

SUBJECT: CRYSTAL RIVER UNIT 3 . CONTAINMENT LINER WELD CHANNEL (TAC NO. 76464)

By letter dated December 27, 1987, you responded to our Inspection Report 87 38

by submitting the requested assessment concerning reactor building liner weld

channels. As a result of your assessment, you determined that containment

integrity would be maintained during the design basis loss of coolant accident

with the channels either vented or unvented.

We are currently reviewing your submittal and have determined that there is not

sufficient data to demonstrate that the leak chase channel system can be

qualified as an integral part of the containment liner plate. Therefore, we

request that you provide additional information listed in the enclosure within

60 days of the date of this letter.

The reporting, and/or recordkeeping requirements contained in this letter

affect fewer than 10 respondents; therefore, OMB clearance is not required

pursuant to P.L.96-511.

Sincerely,

Original signed by

Harley Silver, Project Manager

Project Directorate II-2

Division of Reactor Projects . I/II

Office of Nuclear Reactor Regulation

Enclosure:

As stated

cc w/ enclosure:

See next page

OFC

L

II-2

PE:PDII-2

/ :PM:PDII.

D:PDII.2

.......:.........v...:.........._:...h...)....:..............:....__.......

'

......:

.

NAME

le

GWuiide'dkd
HS v
HBe

l

- . . . . . . : . . . .I.. . _ _ . . . . . . : . e _3

........: ___... ,.....:.__...........:..............:...__..__....

DATE :(,,/

/90

d6

7/90

h/l

90

6 / D /90

' 0FIICIAL RECORD COPY

Document Name: PINK TICKET CR3 TAC 76464

9006200072 900613

PDR

ADOCK 05000302

i

P

PDC

l\\

-_-

_ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ .

_ _ - _ _ _ _

.

.-

a

s

.,

.

..

'

-

..

'

Mr. Percy M. Beard, Jr.

Crystal River Unit No. 3 Nuclear

Florida Power Corporation

Generating Plant

cc:

Mr. A. H. Stephens

State Planning and Development

General Counsel

Clearinghouse

Florida Power Corporation

Office of Planning and Budget

MAC - A5D

Executive Office of the Governor

P. O. Box 14042

The Capitol Building

St. Petersburg, Florida 33733

Tallahassee, Florida 32301

Mr. P. F. McKee, Director

Chairman

Nuclear Plant Operations

Board of County Comissioners

Florida Power Corporation

Citrus County

P. O. Box 219-NA-20

110 North Apopka Avenue

Crystal River, Florida 32629

Inverness, Florida 32650

Mr. Robert B. Borsum

Mr. Rolf C. Widell, Director

Babcock & Wilcox

Nuclear Operations Site Support

Nuclear Power Generation Division

Florida Power Corporation

1700 Rockville Pike, Suite 525

P.O. Box 219-NA-21

Rockville, Maryland 20852

Crystal River, Florida 32629

-Senior Resident Inspector

Mr. Gary L. Boldt

Crystal River Unit 3

Vice President, Nuclear Production

U.S. Nuclear Regulatory Comission

Florida Power Corporation

15760 West Powerline Street

P. O. Box 219-SA-2C

Crystal River, Florida 32629

Crystal River, Florida 32629

Regional Administrator, Region II

U.S. Nuclear Regulatory Comission

101 Marietta Street'N.W., Suite 2900

Atlanta, Georgia 30323

Mr. Jacob Daniel Nash

Office of Radiation Control

Department of Pealth and

o

Rehabilitative Services

1317 Winewood Blvd.

Tallahassee, Florida 32399-0700

Administrator

.

.

Department of Environmental Regulation

Power Plant Siting Section

State of Florida

2600 Blair Stone Road

-Tallahassee, Florida 32301

Attorney General

Department of Legal Affairs

The Capitol

Tallahassee, Florida 32304

l

l

1

{

l

.,

.-

.-.

-

-. --

-

-. -

-.-

-

-.

-

-.-

.

.,.

  • f, J ' ,

ENCLOSURE

REQUEST FOR ADDITIONAL INFORMATION REGARDING

CONTAINMENT LINER WELD CHANNELS

CRYSTAL RIVER UNIT 3

l

1.

Provide supporting analyses and stress calculations for at least one

typical liner weld channel to show that the containment liner weld

channel system meets the following requirements:

a.

The material strength and quality of weld attaching the channel to

i

the liner plate should be equal to or better than that of the

original liner joints and should meet the applicable requirements of

either ASME Boiler and Pressure Vessel Code,Section III, Division

2, Subsections CC-2000, 3000 and 4000 (Code of Concrete Reactor

Vessels and Containments,1983), or whatever comparable code that

was used in design and construction.

b.-

Since the liner weld channels now become part of the containment

l

wall and are therefore considered a structural element, the strength

l

of the channel box and its welds should be able to resist all load

I

combinations involving the tested loads and the loads of a

l-

postulated accident, including seismic loads. The design of the

'

liner weld channel should meet the applicable requirements of steel

<

!-

containments; i.e., either ASME Boiler and Pressure Vessel Code,

,

Section III, Division 1, Subsections NE-2000, 3000 and 4000 for

Class MC Components (1983) and American Institute of Steel

Construction Specification for the Design, Fabrication and Erection

!

of Structural Steel for Buildings (1978), or whatever comparable

code that was used in design and construction.

2.

Complete documentation of installation records, including leak test

procedures and results of the liner seam welds and the welds attaching

the channel to the liner, should be available on site. Please sumarize

and provide examples of available records.

If no records or only partial

records are available, provide whatever additional information/ assurance

that is available regarding procedures, materials, welds, inspection

records, etc.

L

l

3.

The staff needs a comitment that you will perform a visual inspection of

the accessible interior and exterior surfaces of the containment

'

structure and components, including a visual inspection of accessible

channel plugs,.as required by 10 CFR Part 50, Appendix J, and to fix all

l

cracking and corrosion problems prior to any Type A test.

.

-

-

.

--.

-.