Advises That Limit Switches Will Be Utilized to Comply w/NUREG-0737,Item II.D.3 Requirements for Positive Pressurizer Safety Valve Indication,In Response to SER Suppl 3,Confirmatory Issue 1.7.21,Item 3
ML20041D902
Person / Time
Site: Summer South Carolina Electric & Gas Company icon.png
Issue date: 02/26/1982
From: Nichols T
SOUTH CAROLINA ELECTRIC & GAS CO.
To: Harold Denton
Office of Nuclear Reactor Regulation
References
RTR-NUREG-0737, RTR-NUREG-737, TASK-2.D.3, TASK-TM NUDOCS 8203090502
Download: ML20041D902 (2)


Text

f

-A =.

south CAROLINA ELECTRIC a gas COMPANY POST OF FIC E box 764 CotuMe:A, south CAROLINA 29218 k

i c. nicuots.sa.

mbruary 26, 1982 vict Patsint.1 a o Gaov. OccuYwt h

RECENED

-.. on..

.s Mr. Harold R. Denton magg asung Office of Nuclear Reactor Regulation Asg 8

U. S. Nuclear Regulatory Comu.ssion Washington, D. C.

20555 0

g

Subject:

Virgil C. Suniner Nuclear Station Docket No. 50/395 Seismic Qualification Review Team SER Confirmatory Issue 1.7.21

Dear Mr. Denton:

In response to SER, Supplement No. 3, Confirmatory Issue 1.7.21, Item 3, South Carolina Electric and Gas Cmpany (SG&G) acting for itself and as agent for the South Carolina Public Service Authority, has decided to utilize limit switches to cmply with NUR93 0737, Item II.D.3 requirenents for positive pressurizer safety valve indication.

Previously, SG&G had proposed the use of a Westinghouse Acoustic Leak Detection System to perform this safety grade function.

However, contractual and scheduling problms associated with the se.ismic and environmental qualification of this equipnent has resulted in the decision to utilize a different means of cmplying with NRC criteria in NUREG 0737.

In addition, this decision will allow SG&G to install qualified switches prior to full p]wer operation.

As previously discussed during a conference call on mbruary 12, 1982 with Mr. Kane and Mr. Ice of the NRC staff, the limit switches SCE&G will use are manufactured by Crosby, the same cmpany which supplie:1 the safety valves. These switches are designed to mount on top of the valves and are considered to be an excellent choice because of their specifically designed application for these safety valves. It is SCE&G's understanding that other utilities have j

oniered these limit switches to cmply with NURIE 0737 requirements.

Environmental and seismic testing of these switches is presently underway by Crosby with m known problems at this time. SCE&G has reviewed the design and test plan for these switches and is awaiting final test empletion, when testing is emplete (presently schedulal to be cmplete 4/82) SCE&G will review the test results. It is mt anticipated that any problems will develop frm testing that would preclude their eventual use at the Virgil C. SunTner Nuclear Station.

go l o

6s 6 8203090502 820226 i

PDR ADOCK 0S000395 E

PDR 1

I Wo Mr. Harold R. Denton Page Two Ebbruary 26, 1982 Future qualification testing of Acoustic Ieak Detection equipnent will be suspended as a result of this change. Ilowever, the Westinghouse equipnent will renain installed and operational.

If you have any further questions, please let us know.

Very truly yours,

/

/

T. C. Nichol 1, Jr.

AP:'ICN:LKB cc:

V. C. Sumner T. C. Nichols, Jr.

G. II. Fischer II. N. Cyrus II. T. Babb D. A. Nauman M. B. M1itaker, Jr.

W. A. Williams, Jr.

J. P. O'Reilly O. S. Bradham R. B. Clary M. N. Browne A. R. Koon G. J. Braddick l

J. L. Skolds l

J. B. Knotts, Jr.

B. A. Bursey C. L. Ligon (NSRC) i J. C. Ruoff II. Donnelly NICF File l