.8' Omaha Public Power District 1623 HARNEY a OMAHA. NEBRASMA 68102 m TELEPHONE S36-4000 AREA CODE 402 February 26, 1982 LIC-82-05)
,.)*$U%
al,y'
't Mr. Robert A. Clark, Chief M
, r. : '
D' l "Ul? s 8
U. S. Nuclear Regulatory Commission 999& ~
Office of Nuclear Reactor Regulation Division of Licensing i
- 2. "%
~
Operating Reactors Branch No. 3
'\\
YO Washington, D.C.
20555 Qf9; Y'y/
Reference:
Docket No. 50-285
Dear Mr. Clark:
The Commission's letter dated November 10, 1981 requested Omaha Public Power District provide additional information regarding the proposed storage of uranium hexaflouride (UF ) at the Fort Calhoun Station. The 6
District's response is attached.
Please note the attached response references storage areas #1 and #2.
The District plans to store the UF6 in one of these two areas and is presently evaluating the soil load bearing capacity of each. The District will determine which of the two areas is more appropriate and will inform the Commission by April 1,1982.
The District believes the Commission should note that the Model 48X storage cylinders have been used for many years.
These canisters have been storing the UF6 material for the past eight to ten years without incident and the storage conditions at the Fort Calhoun Station-are similar to the conditions at the Kerr McGee facility in Gore, Oklahoma.
Union Carbide, the manufacturer of the cylinders, has strenuously tested prototypes o/ the cylinders for strength and durability. The final design incorporated all improvements which were considered necessary with respect to enhanced structural integrity and shipping consider-ations. The onsite storage of UF6 in the solid form will not pose any hazard to the environment or to plant operations, since UF6 is con-sidered very stable.
The ERDA (DOE) approved canisters are designed to safeguard against significant hazards by employing limits on U23b enrich-ment, mass, volume, geometry, and spacing. Procedures incorporating these safety considerations have been developed and evaluated at the ERDA (D0E) facilities during the past 25 years.
s H.' C.i nes j
j Divisjon Manager Production Operations WCJ/KJM/TLP/RWS:Jmm Attachment 8203050286 820226 cc: LeBoeuf, Lamb, Leiby & MacRae
[ 20m 05000 g
r A.
Storage Area A.1 Provide a facility plot plan showing the proposed storage location and its relationship to ventilation intakes and prevailing winds at the Fort Calhoun Station.
Response
The facility map showing the proposed storage locations is provided in Figure A-1.
Storage area #1 is in the northwest corner of the onsite substation. The approximate locations of the control room and the technical support center ventilation intakes are shown in Figure A-1 with the approxi-mate distances, from the storage area, of 1700 feet and 1600 feet, respec-tively.
The wind directional persistency data for July 1, 1977 through June 30, 1981 is presented in Table A-1.
The prevailing winds are from the north-west and north-northwest sectors with wind frequencies of 12.33% and 10.64%,
respectively. Storage area #1 will be in the west-southwest wind sector with a wind frequency of 3.31%.
Storage area #2 is approximately 200 feet north of the station storeroom and 150 feet east of the railroad spur. Approximate distances between this area and the control room and technical support center ventilation intakes are 600 feet and 500 feet respectively. This location is in the west wind sector with a wind frequency of 4.24%.
l l
FC76/d i
l i
. ADDITIONAL EXCLUSION AREA MISSOURI RIVER
- 7
- 1. REACTOR COMTAINMENT
- - - --- _ w
~
- ~ ~
i
,,[
- 2. AUXILIARY SUILDING 7
- 3. TURalNE ROOM & SERVICE BUILDING A" IN 4.
INTAKE STRUCTURE g
RE
,,.y/.
- 5. V/AREHOUSE STRUCTURES p
L.,
- 7. CONTROL ROOM VENTILATION
-I IHTAKE
- 8. PROPOSED STORAGE AREA #1 1
- 9. PROPOSED STORAGE AREA #2 SVllTCHYARD AREA JACCESS c
FENCE ROAD RAILv
~
SPUR
) (
)
L CHICAGO a NORTHWESTERN RAILWAY TRACKS f
U.S. HIGHWAY No. 73 FEET 0
250 500 1000 SCALE Figure A-1 OMAHA PU3LIC POP!ER DISTRICT FT. CALHOUN STATION UNIT No.1 SITE PLAN
TABLE A-1 FORT CAL 110UN STATION UNIT NO. 1 JOINT FREQUENCY DISTRIBUTION DATA PERIOD JULY 1, 1977 THROUGH JUNE 30, 1981 Wind Frequency Per Year Sector *
~
(Percent)
NNE 3.35 NE 2.58 ENE 2.23 E
3.14 ESE 5.60 SE 9.29 SSE 9.18 S
9.70 SSW 7.02 SW 4.08 WSW 3.31 W
4.24 WNW 7.93 NW 12.33 NNW 10.64 N
5.26
- Sector is Wind Direction
t A.2. Describe the cylinder storage conditions (e.g. existing ground with or without cylinder cradles, concrete or asphalt pad with or without cylinder I
cradles, hold-down straps, inside or outside storage, security fences, stacking cyclinders, cylinder valve protection, fire protection).
J
Response
Storage area #1 is in the northwest corner of the Substation enclosure and will be enclosed by a separate fence that will be appropriately marked.
The Substation is a 700' x 950' rectangular area enclosed by chainlink fence seven feet tall and topped with three strands of barbed wire for a security fence eight feet tall. There are three gates in the fence, each twelve feet wide, that are kept locked except for entry by authorized OPPD personnel.
The surface of the Substation is graded from an elevation of '1003 feet ms1 at the eastern and western fence lines to an elevation of 1006 feet asl at the center, thus providing for drainage away from the transmission and distribution components located at the center of the enclosure. The elevation of storage area #1 is an average of 1003 feet ms1 with a slight incline from east to west, a 1 foot drop in a traverse of 60 feet, to pro-vide for drainage. The surface of storage area #1 is covered with_ crushed t
limestone and no addit,ional paving, e.g.-concrete or asphalt, is planned.
Storage area #2 is approximately 200 feet north of the onsite' storeroom and 150 feet east of the railroad spur indicated on Figure A-1.
Storage condi-tions for this area would include fence and surface' condition comparable 5-to area #1. Entry would be limited to authorized OPPD personnel.
l Thel ufo cylinders will be stored with the long axis of the cylinder parallel to, and elevated from, the crushed limestone covered ground on railroad tie i
-e
>-w~
cradles. The cradles will be made by attaching wedges to the railroad ties at locations to provide maximum cylinder stability without the use of tie-down devices. Tie-down devices are not considered necessary during storage because of the large weight of each individual cylinder (23,530 puunds nominal gross weight) and the low probability of movement by natural forces (see response to Item D); also the cylinders will not be stacked. Stacking would require tie-down devices to prevent the bottom row from rolling out from under the top row.
Cylinder valve protection, as designed for the Model 48X Cylinder is now in place at Kerr-McGee, and will' remain so throughout shipping and the storage period.
The proposed storage locations will be maintained free of combustible materials.
In addition, the cylinders are made of steel, and the UFs and hydrolized pro-ducts are not combustible; therefore, no fire protection systems are planned.
Ilowever, CO2 fire extinguishers, available in the Interim Emergency Operations Facility and/or the storeroom for spot cooling of a cylinder if a leak should develop, will ensure that fire protecticn is adequate.
I I
B.
Inspection Program B.1 Describe your inspection program for receipt and prior to transfer.
In-clude your criteria for rejecting the cylinder (s) and planned actions you will take to make the cylinder (s) acceptable for receipt or transfer.
Response
All cylinders will be inspected by a Kerr-McGee qualified inspector prior to transfer from Gore, Oklahoma per DOE inspection procedure, A-1.1, de-tailed in ORO-671, Volume 1.
Inspection results will be recorded on a " ufo Cylinder Inspection Data Sheet," (Figure B-1) and copies will accompany the shipment to Fort Calhoun Station. All DOT and NRC regulations applicable to the transportation of UFc will be observed during shipping to the Fort Calhoun Station.
4 Prior to storage, an OPPD qualified inspector will check the Kerr-McGee -
inspection sheets and conduct an inspection of the cylinders per DOE i
l inspection procedure, A-1.1.
Inspection results will be recorded on a
" ufo Cylinder Inspection Data Sheet" (Figure B-1).
Damage to cylinders discovered during either pre-shipping or pre-storage inspections is classified as acceptable or unacceptable based on the cri-teria defined in ORO-671, Volume 1.
A cylinder shall be deemed unacceptable for receipt if any " Unacceptable" block is checked on the "UFs Cylinder 1
Inspection Data Sheet" (Figure B-1) for that cylinder during the OPPD pre-storage inspection.
A comparison between Kerr-McGee pre-shipping inspection sheets and-0 PPD pre-storage inspection sheets will be made, and any discrepancies will be resolved through discussion with Kerr-McGee and the carrier. Damage will lue repaired as necessary,. prior to acceptance for storage of any pylinder deemed unacceptable. Minor damage, e.g., bent, broken, or mispositioned valves, 7
1
--s c...<
a UFs CYLINDER INSPECTION DATA SHEET CYtmota auveta edi.ota moo L a o i,,
Cru ota etina O xA **=i O.aA o*'
O 0'.aa O 8** '"' O "' " '= -= n
O P. m m. m
,,,,,,,,,,n,,,,,,,,,,,,,,,
c.=en cvunota sv A rus O An.
an O r."
O t.cr.
P~ a..
.. C aa..ia. O a.'*a O P.
= 8..'s ' a Au.
. O a ' auai.=.
e..
C,i
.. C su v..
O a.
C v===. C a'~. **. 5.' * '
- O T..
a.
C,im e i. S hH.s h
s.
O O v.......
A.u
..r..t o.
-*- + -.
A. v&Lvt:
- a. r., c= 0,
- 2. Tw..e t.s.
A v C.. P n Pim.
!'YLINDER B. vALvt PORT:
C VALVE'
""'""'*"'8 VAI/<E 8C""********'**"'""*""'***"*'***
PORT C. PtuCt 1 ** ***' C ="
AND
- 2. Tw'as r a.-
ptyc5 O v& Lyt PRQTECTOR.PRistui Amo PROPERLv PQ5aT10Nt0 C. SEAL 0.u.
.e Omn i.e
,r A. CIRCUMPEAtNTIAL mtAD $the stLD. VALv& E90 3 CJRCUuPERENTIAL ntA0 $taa..tLO. PLUG END C. LonCITV0 mat Stau.tLn Ono.
.r 0. s.e
,e A. $s.tLL
- 8. MEA 0.vALvtth0 C. MEAD.PLUC END g
MD h"'******'"'"
HEADS A. vAtvt eno IV,
- s. Ct= Tan STIFFENING C. PLus t=n RIN G5 c..u.v
.e 0.. i.s
,e A. v&Lvten0 y
5bRT3 0..u i
.e 0
.o i.e
,e OAIL AMD IWE IMSPLCit0 amiPtCIED SY TMs3 IsCTsOn TQ af Co.PL<o er a waureto enut C rom eroa camace orignato ro rwe em3Pggreow ogPra 3ECT10N A
cAlt QUAU Fit o im1PECTom T...
.w.i.. O an===. O u...
FMdf IECTeo.s 70 et CO.PLETfD.cffN TME DamACf IMOfCA FfD A OVE #5 fM5PECTfD A O A*PAprEO SF OTMgm TMAN sNIPfCT.
- 0m ofPT Pfe50NNEL in.
.., nn a
.w.ui.e s ui....e
,e SECTION B
OAMAGE APPRovtp sy TITLE DAtt
.. un L u s sa v nts GnsiTium LEGEND A e a.
D.es t..e.u. ruun u. u
.o
.. s A.. C w
Se. o -
-A.....
Figure B-1 TYPICAL CYLINDER INSPECTION DATA SHEET
- ~..
I
. plugs or valve protectors, discovered during the OPPD pre-storage inspec-tion will be repaired by OPPD personnel. More extensive damage, e.g.
6trt or stiffener ring torn from the shell, broken stiffener ring or other damage requiring welding for repair, discovered during the pre-storage inspection will be referred to Kerr-McGee. Before repair work requiring welding can be performed, the damaged cylinder must be emptied due to density differences between solid and liquid UFs.
Liquid UFs occupies a
^
24% larger volume _than: solid UFs, therefore, localized heating of a storage cylinder must be avoided. The above mentioned repair work will be referred
' /- O to Kerr-McGee because OPPD does not have the necessary facilities for emptying or filling the~cylindersi
- ~
~
~
~~
m.
~~ '
.z.,
a a
i L
E
==m A
F I
e 4
e =
}
s 3
t a
')
1 a
"t B.2 Describe your inspection program for long-term storage.
Include your criteria for determining if a cylinder is no longer acceptable for storage and planned actions you will take to make the cylinder acceptable for con-
- ~
J
tinued storage.
Response
The inspection program for long-term storage of UFs cylinders will consist of the pre-storage inspection, as described in the response to Item B.1 above, a bi-ennial inspection and a pre-shipping inspection of the cylinders utilizing the same DOE procedure A-1.1.
The results of the bi-ennial inspection will be evaluated to determine if a cylinder is acc?ptable for continued storage service. A cylinder will be removed from storage service if any damage to the cylinder is discovered during the bi-ennial inspection that fits the criteria described in ORO-671, Volume 1.
4 In the unlikely event a cylinder is deemed unacceptable for continued storage service, the District would repair the defect or ship the cylinder for repair or replacement in accordance with industrial and app: aved practices for UFs storage cylinders.
Further, the following security measures will be taken:
1.
The storage area gates 'will be kept locked except for entry by authorized OPPD personnel.
s 4
4
.n
.wp
. M F*
i :'
,r r.
e 4
N" sw-
Y
)
l l
l 2.
Personnel authorized for entry to storage area #1 will be on business pertaining to maintenance of the transmission and distribution components or receipt / shipping / inspection of UFs cylinders.
Personnel authorized for entry to storage area #2 will be on business pertaining to receipt /
shipping / inspection of the storage cylinders.
3.
The Fort Calhoun Station Security Force conducts routine patrols, mini-mum of once per 8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> shift, of the site boundaries and areas not under continuous surveillance by closed-circuit television cameras.
4.
Any abnormal situation or appearance would be reported by the Security Force and an individual would be dispatched for further investigation.
The occurrence of any physical damage to a cylinder that would meet the criteria of " Unacceptable Damage" of OR0-671, Vol.
1, Figure 2 is extremely unlikely based upon the security precautions and storage location described I'
above, and the low probability of occurence of natural disaster described in the response to Item D.
f w
I f
C.
Industrial Accidents C.
Provide a discussion and assessment of the following industrial accidents to include (1) preventive measures, (2) health, safety and environmental impact to cylinder storage area, other station areas (e.g., containment building, turbine building), and beyond the site boundaries if the accident should occur, and (3) your personnel, procedures, equipment and facilities for dealing with these accidents if they should occur.
C.1 Failure of a cylinder either during on-site handling or storage when the cylinder contains only solid UFs.
Response
The Model 48X ten-ton shipping and storage cylinder is designed and con-structed as a high integrity containment vessel for Uranium Hexafluoride (UFs) with a maximum enrichment of 4.5%.
Design, coastruction and testing have been conducted in accordance with the following standards and regula-tions: ANSI N-14.1-1971; ASME Boiler & Pressure Vessel Code,Section VIII, Division 1; 10 CFR Part 71.
See Table C-1 for structural design criteria per 10 CFR Part 71.
Due ta the design, construction _and testing criteria specified by ANSI, ASME, NRC and ERDA (DOE), catastrophic failure of the Model 48X Cylinder during shipping or storage ig considered highly unlikely (See Allied General Nuclear Services Safety Analysis Report for Model 48X UFs Packaging).
At any time during on-site handling or storage, the cylinder contents will be solid with a low concentration of UFs gas occupying the space above the solid.
In the event solid UFs is released to the atmosphere, it will react with the moisture in the air (hydrolize) forming UO F, a white powder which 2 2 i
?
TABLE C-1 STRUCTURAL DESIGN CRITERIA APPLICABLE PARAGRAPl!
PROM 10CFR71 SUBJECT COMPONENT CRITERIA COMMENTS 71.31 Lifting devices Cylinder lifting lugs +
Support at least - 3 times the weight of the loaded package without generating stresses in the packaging exceeding yield.
Tie-down devices cylinder lif' ting logs 2g vertical, 5g transverse, 10g longitudinal transport loading.
Auxiliary lifting holes in skirt, Stiffening rings, cylinder wall.
Lifting & Tie-down All above Failure of device (s) due to Excessive load is devices excessive load will not
".?
defined as that loac impair the containment which will result it' integrity of the cylinder.
a structural failu-(.
in the packaging.
71.32 Load resistance cylinder wall Support at least 5 times the weight of the loaded package as a simple beam without generating stresses in the packaging exceeding yield.
a.
.~
- ::~ '
^-
TABLE C-1 (Con t'd. )
APPLICABLE PARACP.APli rn0M 10CFR71 SUBJECT COMPONENT CRITERIA COPMENTS 0
71.32 (Co n t ' d. ) External pressure cylinder wall & heads containment vessel integrity Determined for -40 F maintained when a 25 psig condition to maximize external pressure is applied.
pressure differential.
0 212 F steam chest
- 71. 3 5 (a) (1)
Internal pressure cylinder wall, heads No yielding 130 F ambient and stiffening rings results in greater 0
- 71. 3 5 (a) (2) '
Full insolation temperature and pressure.
-40 F ambient in cylinder wall, heads, No brittle fracture, no Low vapor pressure of 0
- 71. 35 (a) (2) contributes to yielding UF6 still air and stiffening rings, and shade.
tie-down/ lifting devices.
pressure differential.
External pressure Cylinder wall, heads, No yielding in the packaging Less severe than and stiffening rings.
for a reduction in atmos-pressure differential pheric pressure to 0.5 atm.
resulting from 1300F ambient.
s Vibration Packaging Natural frequency exceeds No failures in more 20 Itz.
than 1*0 years of use in road and rail transport.
1-foot free drop Skirts, stiffening rings, No reduction in packaging Paducah test results cylinder, wall, heads.
effectiveness (containment).
cited.
Penetration Valve No reduction in packaging Paducah test results effectiveness (containment).
cited.
Compression cylinder wall Uniform compressive load of 50,000 pounds applied to top
& bottom of Cylinder in normal position of transport.
tends to settle on surfaces, and HF, a colorless vapor.
The solid UFs will and HF.
A visible plume also sublime to UFs gas and then hydrolize to UO F2 2
of the white UO F2 Powder and HF vapor will result and will be easily trace-2 able. The plume will disperse at a rate governed by wind speed and other meteorological conditions. UO F2 and HF concentrations in the plume will be 2
governed by the amount of UFs exposed and the amount of water vapor in the atmosphere.
Health, safety, and environment impact beyond the site boundaries will be a toxic chemical, rather than a radiological hazard and is dependent upon the wind speed, wind direction and other meteorological conditions effecting plume dispersal. A release of UFs of the magnitude postulated would be placed in an appropriate emergency classification as described in Section D of the Fort Calhoun Station Radiological Emergency Response Plan. Notifi-cation of State and Local authorities would be made consistent with the emergency classification declared.
The following discussion illustrates that the radiological hazard from a UF release is insignificant when compared to the chemical hazard 6
of the Uranium released in the form of UO F -
2 2 The expected quantities of radioisotopes in the UFs product (and thus the UO F ) were calculated for natural enrichment uranium on the basis of decon-2 2 tamination factors for the UFs conversion process.
Of the fission product impurities in the uranyl nitrate product from the BNFP Separations Facility, only traces of ruthenium-rhodium (Ru-Rh) will be carried over into the UFs (UO F ) Product. The Zr-Nb impurities, which form non-volatile fluorides, 2 2 will remain in the UFs facility's fluorinator bed.
Thus, the only gamma-emitting fission product in the UFs (UO F ) product will be trace quantities 2 2 of Ru-Rh isotopes, and Ru-106 is the only element of concern from a radio-logical hazard standpoint.
The isotope U-237 will be present in the UFs (UO F ) in the Cylinder. At 2 2 the time of shipment, the radiation source contribution from this isotope is approximately the same as that from the U-235 isotope. The Ru-Rh isotopes, primarily Ru-106 emit the most penetrating of the radiation sources used in the shielding analysis.
The UFs (UO F ) Product has been stored until the U-237 isotope has decayed 2 2 to within shipping specifications. The concentration of gamma-emitting isotopes is expected to be no more than 0.032 Ci/MTU of Ru-Rh and 0.13 Ci/MTU of U-237.
In addition, the concentration of the U-235 in the product UFs (UO F ) will be no more than 0.0214 Ci/MTU.
2 2 For radiological considerations it is assumed that the Ru-Rh isotopes are released in the particulate form and only Ru-106 is assumed to be the source term with a total activity of 0.32 Curies (0.032 Curie /MTU X 10 tons). All of the activity is conservatively assumed to be released to the environment following a cylinder rupture. The two-hour whole body dose to a child at the site boundary will be approximately 1.0E-05 Rem (based on a DCF of 1.09E-06 mrem /pCi, X/Q of 4.4E-04 sec/m3 and a 3
breathing rate of 6.9E-05 m /sec) which is 4.2E-05 percent of the limits specified in 10 CFR Part 100.
There are no significant neutron sources.
Direct contact with the plume should be avoided, as the HF is a mild but very penetrating acid when in contact with skin or other tissue such as the linings of the throat or lungs. Rubber or plastic protective clothing should be worn to prevent skin contact with the HF and respiratory equipment should be worn to prevent inhalation of the UO F 2 2 and HF.
The inhalation of fumes from very large releases for more than a few breaths may result in temporary lung impairment quite soon after the exposure and in some instances mild but repairable kidney damage within a few days. UO F 2 2 is a water soluable heavy metal compound that is toxic to the kidneys when inhaled or ingested in large quantities.
Impact on the operation of Fort Calhoun Station would oe very small consider-ing the storage location in relation to prevailing winds and the station venti-lation system intakes. As stated in the response to Item A.1 above, the wind direction necessary to carry a UO F /HF plume over the station ventilation 2 2 system intakes will be west-southwest with a frequency of 3.31% for storage area #1, or west with a frequency of 4.2% for storage area #2.
The station ventilation systems can be isolated so that no outside air will be brought in if a release occurs with the wind blowing from the above defined direction.
In the event of a significant release, evacuation of the plant, which would potentially expose many people to the plume, would be unnecessary.
Health, safety and environmental impact to either of the storage areas would be small because 1) the storage areas are in a remote sector of the plant site, 2) UO F2 and HF will have no adverse effects on any equipment 2
located near either of the storage areas, and 3) there is no significant vegetation in either of the storage areas or in the direction of the prevailing winds.
Response personnel, procedures, equipment and facilities are described in the response to Item E, below.
Accident prevention will be provided by the location of the storage area and by cautious handling by a crane operator experienced in the handling of large loads. The proposed storage location inside the Substation enclosure, storage area #1, is a minimum of 200 feet from transmission and distribution components and is enclosed by a separate fence. Storage area #2 is 200 feet north of the storeroom, 150 feet east of the RR spur and 100 feet west of the construction road. These are very low vehicle and personnel traffic areas.
The only traffic in or near either of the storage areas will be pertaining to shipment or receipt of cylinders.
Movement of cylinders will be by a 15 ton or greater capacity, truck mounted crane. The truck will be capable of lting raised on four hydraulically operated legs to increase stability when the crane is loaded; therefore the lifting equipment is immobile.
In the unlikely event of lifting cable failure, a free drop from up to a 10-foot height onto the surface of the storage area is not expected to result in cylinder failure based on the following discussion.
Structural integrity of the Model 48X Cylinder was evaluated on the basis of " Free Drop" tests as required by 10 CFR Part 71, Appendix A.
Drop tests conducted by AGNS at Paducah, Kentucky exceeded the 10 CFR Part 71, Appendix A requirements for fully loaded cylinders.
No cylinder failures are reported for drops of up to thirty feet onto a flat, unyielding surface, although significant deformation was observed. A four-foot drop of a fully loaded (simulated UFc,) cylinder is reported.
In this test the cylinder was dropped 1
l onto its " top" skirt (valve end). The cylinder remained upright and undamaged
I after the drop. A 30-foot drop of a fully loaded (simulated UFs) cylinder is also reported. ~The 25,540 pound cylinder was dropped onto the plug end at an angle of 20* from vertical. Maximum deformation to the cylinder body was approximately three (3) inches where the skirt crimped in on the cylinder head.
A slight leak occurred at the plug nearest the point of impact. Twenty-foot and forty-inch drop tests from a horizontal attitude onto a flat surface and a six-inch diameter piston, respectively, resulted in cylinder shell deforma-J tion but no leakage. A second forty inch drop onto a six-inch diameter piston was conducted. The point of impact was the center of the cylinder head. Head deformation was three inches, but no leakage'was observed.
Therefore, significant leakage or cylinder failure from a drop onto a crushed limestone covered surface is considered highly unlikely.
1 1
I i
l 4
1 1,
5
C.2 Failure of a cylinder either during on-site handling or storage when the cylinder contains gaseous UFs.
Response
1 As discussed in the response to Item C-1, the cylinders contain solid UFs with a volume of gas in the space above the solid. Due to internal pressure of the cylinder, the concentration of the gas will be low.
A high concen-i tration of UFs gas occupying the volume above the solid is considered highly unlikely due to the chemical characteristics of UFs and normal weather conditions at Fort Calhoun Station as discussed in the response to Item C.3, below.
In the event of a small leak, the escaping UFs gas would hydrolize, as discussed in the response to Item C.1 above, and the product would plug the leak. Environmental impact from a large leak would be the same as for a release of solid material as discussed in the response to Item C.1, above.
C.3 Failure of a cylinder either during on-site handling or storage when the cylinder contains liquid UFs.
This is unnecessary if it can be shown that such a condition is incredible.
Response
This. condition is considered incredible due to the chemical characteristics of UFs, the weather conditions at Fort Calhoun Station and Nuclear Industry practice relating to shipping and storage of UFs.
Industry practice allows for UFs shipping only in solid form with a vapor pressure of less than 14.5 psia.
(See OR0-651, Section 6.1).
This condition will be maintained during on-site storage. The chemical characteristics of UFs provide for a solid material at a temperature and pressure of less than 147.3 F and 22 psia, respectisely.
l
~,
1 Cylinders in storage subjected to summer solstice insolation on a 130 F day would have a temperature of 178 F (see the AGNS SAR for Model 48X Cylinders). This. temperature, 178 F,-is for a cylinder oriented with its axis parallel to an east-west vector in still air. These ideal conditions 4
are extemely rare in Nebraska. Maximum daytime summer temperatures are on the order of 100 F and wind is generally blowing at 5 mph or more, therefore, liquification of UFs due to daytime peak temperatures during the summer months is considered incredible.
4 4
i
'l 1
f i
y
D.-
Natural Phenomena D.
Provide a discussion and assessment of the following natural phenomena to include (1) health, safety and environmental impacts to cylinder storage area, other station areas (e.g. containment building, turbine building) and beyond the site boundaries and dealing with these if they should occur.
D.1 Earthquakes
{
Response
From the discussion on Seismicity in the Fort Calhoun Station FSAR Section 2.4, the following sections are reproduced:
2.4.3 Seismic Design Criteria Although on the basis of the history of the region no significant earthquake ground motion is expected at the site, occasional shocks along the Missouri River and continuation of shocks in the belt extending northward from the Abilene Arch to the Sioux Uplift could be postulated. For conservation in the determination of appropriate seismic criteria the proximity of a fault to the site is consiaered. On this basis, and in accordance with the recommenda-tions of the U.S. Coast and Geodetic Survey (USC&GS), seismic criteria have been established as follows:
a.
Design earthquake: maximum horizontal ground acceleration equal to eight percent of gravity; b.
Maximum hypothetical earthquake: maximum horizontal ground acceleration equal to seventeen percent of gravity.
l 2.4.4 Conclusion l
(
The site is subject to infrequent slight ground motion from regional shocks.
' Conservatively, and in line with USC&GS recommendations, the plant is designed for earthquake intensities postulated on the basis of a fault system in the vicinity of the site. The plant is designed for elastic response to ground motion accelerations as high as eight percent of gravity and for a safe shut-down of the reactor for accelerations as high as seventeen percent of gravity.
The model 48X Cylinders were designed per ANSI N14.1 as high integrity vessel primarily used for the shipping of UF. Structural design criteria from 10 6
CFR Part 71, presented in Table C-1, require the cylinder tie-down devices, i.e. wall, stiffening rings, auxiliary lifting holes in the skirts and lifting lugs, to be capable of withstanding the following transport loads:
- 1) 2g(51,060 pounds) vertical, 2) 5g(127,650 pounds) transverse, and 3) 20g(255,300 pounds) longitudinal. The least of the aforementioned criteria, 2g(51,060 lbs), is a factor of 11.76 greater than the maximum expected earth-l quake induced loads at the plant site. Therefore, it is considered highly unlikely that cylinder failure will occur from earthquake induced loads.
Health, safety and environmental impact to the cylinder storage area, other station areas and beyond the site bondaries from UFs releases is dis-cussed in the response to Item C, above.
Personnel, procedures, equipment and facilities for response to UFs releases are described in the response to Item E, below:
0.2 Flooding Response-The proposed storage area #1 is approximately 1800 feet west of the Missouri River at an elevation of 1003 feet msl. Proposed storage area #2 is approxi-mately 900 feet west of the river at approximately the same elevation. The Fort Calhoun Station'FSAR, Section 2.7.1.2 states the plant design flood peak r
stage is 1004.2 feet ms1. The design flood peak stage is slightly greater than the 0.1% probability flood, when the probability curve is extrapolated.
Therefore the 1004.2 ft. ms1 stage is conservative and proper for use. Addi-tionally, the ground rises to an elevation of 1006 feet msl between the river and storage area #1.
Storage area #2 will be graded to a suitable elevation prior to placement of cylinders for long-term storage.
The peak flood stage during the 1952 flood is documented as 1008.5 feet ms1 by the Army Corps of Engineers. A flood of this ragnitude has a probability of occurance of less than 0.1% due to five (5) flood control dams constructed upstream of Fort Calhoun since 1952.
Design and construction of the Model 48X Cylinder is such that catastrophic cylinder failure due to flooding is considered incredible.
Load resistance of the Model 48X Cylinders is discussed in the response to Item C, above.
D.3 Tornados
Response
The low profile, diameter of four feet and length of ten feet, and large weight, 25,530 pounds, significantly reduces the probability of cylinder movement as a result of a tornado on site.
Cylinder rupture as a result of a tornado induced pressure drop is considered incredible based upon calculations presented in the AGNS SAR for Model 48X Cylinders. AGNS postulated an external pressure of 7.4 psia and calculated the resulting effect on the internal pressure. The decrease of 7.4 psi ex-ternal pressure has the same effect as an internal pressure increase of approximately the same amount. Considering the internal operating pressure of 100 psia, the hydrostatic test pressure of 415 psia and a tornado induced pressure drop of up to 10 psi, the resulting internal pressure of approxi-mately 110 psia is a factor e ^ 1.77 below the hydrostatic test pressure.
4 t
Tornado carried debris impacting a cylinder perpendicular to its surface could result in shell fracture and UFs release.
The probability of such an impact is very low because of the cylinder diameter, however in the event of such an occurance the health, safety, and environmental impact to the storage area, on and off-site, areas and operation of the plant would be the same as for UFs releases discussed in the response to Item C.1, above.
Response actions, personnel, procedures, equipment and facilities are dis-cussed in the response to Item E, " Emergency Plans".
1 3
1 4
.t f
2 4
1 l
i 6
4 e
1 ye-
--- ~ -. _. -,
E.
Include a specific proposed section in the Fort Calhoun Station Emergency Plan to address potential accidents of the proposed storage of UFs.
It is suggested that this be done as a separate addendum to the Emergency Plan, i.e., a UFs Accident Contingency Plan.
Response
The Fort Calhoun Station Radiological Emergency Response Plan provides comprehensive action required by NUREG-0654/ FEMA-REP-1, Rev. 1.
Basic identification, notification, organization, assessment, protective response and exposure control mechanisms are integral features of the Plan.
Potential accident effects to the public resulting from the storage of Uranium Hexafluoride (UFs) are fully reduced within the scope of the existing Emergency Plan.
Specific instruction addressing potential accidents from the storage of ufo can be provided to (1) the ' Accident Consideration' section of the Radiological Emergency Response Plan and (2) a separate Emergency Procedure, Uranium Hexafluoride Incident, to the Fort Calhoun Station Operating Manual as proposed below.
1.
Radiological Emergency Response Plan, Section Accident Consideration.
8.0 Uranium hexafluoride accidents Uranium hexafluoride (UFe) cylinders are stored on-site and will be eventually shipped off-site for fuel processing.
The cylinders are constructed of steel and designed in accor-dance with applicable ANSI and ASME standards.
The UFs and
J-its hydrolized products are neither combustible nor a radiological hazard. The health consequence which may result from handling of the bulk material is tissue irritation by inhalation and direct contact.
Exposure to UFs and its decom-position products ould result only from the opening of a cylinder or a loss of container integrity.
If a surveillance observation indicates UFs is lost from a cylinder, Emergency Operating Procedure Uranium Hexafluroide Incident provides effective response actions to control and minimize the release of the chemical.
t 2.
Emergency Procedure Uranium Hexafluoride Incident A.
Purpose To describe the actions to be taken in the event that uranium hexafluoride is released from a storage cylinder.
B.
Symptoms Any one or more of the following indications may be present:
1.
White crystals at a failed valve or cylinder crack.
2.
Irritant, corrosive fumes in the atmosphere.
3.
White particles in the air.
C.
Immediate Action 1.
Notify the Shif t Supervisor of an apparent release of uranium hexafluoride and that a detailed examination is to be made for verification purposes.
2.
Don self-contained breathing apparatus, gloves and head covering and re-enter area.
3.
Inspect storage area closely. Verify crystals are not cylinder corrosion deposits and fumes are not another irritant vapor, such as chlorine or ammonia.
4.
Secure cylinde. valve if it is the source of the leak.
5.
Report inspection observations to Shift Supervisor immediately.
D.
Follow-Up Action 1.
Apply actions consistent with " Notification of Unusual Event" emergency classification.
2.
Control storage area with barricade and labeling.
a F.
UFn Cylinder Materials l
F.
Clarify the materials of construction for the Type 48X cylinders you
. plan to utilize.
4 i
Response
i The Model 48X Cylinders shnll and heads are fabricated from ASME SA-516 l
carbon steel plate, 5/8" thick. Stated tensile strength is 55.0-65.0 ksi with a yield point of 30 ksi.
All other structural components are ASME SA-36 (ASTM A-36) structural steel with a stated tensile strength i
of 58.0-80.0 ksi, yield point of 36.0 ksi and coefficient of Linear Thermal Expansion 6.7E-06 in/in/*F.
Design, construction and testing of each cylinder is per ANSI N-14.1 -
1971Property "ANSI code" (as page type) with input value "ANSI N-14.1 -</br></br>1971" contains invalid characters or is incomplete and therefore can cause unexpected results during a query or annotation process., ASME Boiler and Pressure Vessel Code,Section VIII, Division 1 and 10 CFR Part 71.
The Model 48X Cylinder'has a one-inch fill valve.
The body, packing nut, packing ring, and packing follower are an Aluminum-Silicon-Bronze alloy and the stem is Monel.
J 4
6
)
l 4
7