ML20040G363

From kanterella
Jump to navigation Jump to search
Advises That Reg Guide 1.68.3 Re Preoperational Testing of Instrument & Control Air Sys Is Approved Subj to Clarification of Applicability & Implementation.Guide Should Apply to post-OL Plants When Mods/Repairs Degrade Sys
ML20040G363
Person / Time
Issue date: 02/08/1982
From: Dircks W
NRC OFFICE OF THE EXECUTIVE DIRECTOR FOR OPERATIONS (EDO)
To: Minogue R
NRC OFFICE OF NUCLEAR REGULATORY RESEARCH (RES)
Shared Package
ML20040G347 List:
References
RTR-REGGD-01.068.03, RTR-REGGD-1.068.03 NUDOCS 8202120213
Download: ML20040G363 (1)


Text

Y

+I

![p3 flfCg

    • -Io UNITED STATES g

NUCLEAR REGULATORY COMMISSION n

(5 WASHINGTON, D. C. 20555 N.'..../

FEB 0 81982 MEMORANDUM FOR: Robert B. Minogue, Director Office of Nuclear Regulatory Research FROM:

William J. Dircks Executive Director for Operations

SUBJECT:

PREOPERATIONAL TESTING 0F INSTRUMENT AND CONTROL AIR SYSTEMS - REGULATORY GUIDE 1.68.3 On Thursday, January 21, 1982, the CRGR was briefed by RES (Ed Wenzinger) on the subject Regulatory Guide. The Committee agreed that the potential for common mode failure, combined with the observed frequency of air service-related events, indicates that additional attention to air system testing is warranted.

The staff advised the CRGR that an interoffice task group had been established with the objective of reviewing the need for design changes to imprave air system reliability entirely separate from the RG 1.68.3 issuance.

It was noted that the subject RG had the potential for limited improvement in reliability of air systems through improved testing procedures.

Accordingly, the subject guide is approved subject to clarifying the guide's applicability and implementation. The Committee believed, and I agree, that the guide should be applicable to (1) the testing of air systems after major modifications or repairs are performed for post-OL plants when such modifications or repairs have the potential for degrading system performance and (2) the initial preoperational testing for pre-0L plants except in those cases where approved test plans and procedures exist and testing is scheduled or in progress.

Further, it is requested that the final wording of the implementation section receive specific ELD review and concurrence especially with regard to mechanisms for implementing this Reg. Guide for plants that are no longer under specific licensing review.

/

l' f

Willia J. Dircks Executive Director for Operations 8202120213 820204 PDR REVGP NRCCRGR PDR