Responds to NRC 811112 Ltr Re Violations Noted in IE Insp Rept 50-370/81-16.Corrective Actions:Blue Cables Have Been Repulled & Cover Placed Over Cable Tray Until Completion of Const
ML20040C426
Person / Time
Site: Mcguire
Issue date: 12/15/1981
From: Parker W
DUKE POWER CO.
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
Shared Package
ML20040C421 List:
References
811211-03, 811211-3, NUDOCS 8201270627
Download: ML20040C426 (2)


Text

'

o ,o .' '

l. 8 D

, D' 'If K h ,."'O

    • I cr $.;prI tQFllIt,;C031PANY

..t ,

POWER UUILLING 422 Sourn Councu STREET, CHAntDTTE, N. C 28212

'llnrc17 +

05 WI LLI AM O. PA R M E R, J R.

w p r..or,,, December 11, 1981 retc~o~c:^aca 7o4 set. e ooxv o., 2 7 3-4 c s 3 Mr. James P. O'Reilly, Director U. S. Nuclear Regulatory Commission Region II 101 Marietta Street, Suite 3100 Atlanta, Georgia 30303

Subject:

McGuire Nuclear Station Docket No. 50-370

Reference:

RII:TDG 50-370/81-16

Dear Mr. O'Reilly:

Please find attached a response to violation 50-370/81-16-01 which was identified in the above referenced inspection report. Duke Power Company does not consider any information contained in this report to be proprietary.

I declare under penalty of perjury that the statements set forth herein are true and correct to the best of my knowledge.

Ve [ truly yours, ,

a_ a _ d. Oh William O. Parker, Jr.

PBN/j fw Attachment 8201270627 811229 PDR ADOCK 05000370 G PDR t

u McGUIRE NUCLEAR STATION Response to I.E. Inspection Report 50-370/81-16 Violation 50-370/81-16-01, Severity Level V:

10 CFR 50, Appendix B, Criterion XIII, as implemented by Duke Power Company QA Topical Report, Section 17.1.13, requires measures shall be established to '

control ... preservation of material and equipment in accordance with work and inspections to prevent damage or deterioration.

Contrary to the above, measures shall be established to prevent damage to installed cables at cable tray node point 12453 two Class IE blue cables were crushed flat by employees walking in the tray. This tray section is being used as a walkway. There is no procedure issued to control the use of cable tray as a walkway.

Response

1. Duke Power Company agrees that the violation occurred as stated.
2. The cable tray was installed in a unique way which made it susceptible to '

physical damage by traffic and the movement of equipment across the tray.

3. The two blue cables identified in the inspection report along with two other blue cables have been repulled, and a cover placed over the cable tray until completion of the construction effort.
4. All craft personnel and contractors have been instructed both verbally and by memo that cable trays are not te be used as a storage place for materials, as a container for refuse, or used as a walkway.
5. The station is presently in full compliance with the QA Topical Report in this area.