ML20039E988

From kanterella
Jump to navigation Jump to search
IE Insp Repts 50-456/81-14 & 50-456/81-14 on 811118-20. Noncompliance Noted:Failure to Ensure That Const Procedures Change W/Specs Changes & to Issue Timely Tendon Insp Instruction
ML20039E988
Person / Time
Site: Braidwood  Constellation icon.png
Issue date: 12/28/1981
From: Gardner R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML20039E980 List:
References
50-456-81-14, 50-457-81-14, NUDOCS 8201110693
Download: ML20039E988 (11)


See also: IR 05000456/1981014

Text

r

U.S. NUCLEAR REGULATORY COMMISSION

REGION III

Reports No. 50-456/81-14; 50-457/81-14

Docket Nos. 50-456; 50-457

Licenses No. CPPR-132; CPPR-133

Licensee: Commonwealth Edison Company

Post Office Box 767

Chicago, IL 60690

Facility Name: Braidwood Station, Units 1 and 2

Inspection At:

Braidwood Site, Braidwood, IL

Inspection Conducted: November 18-20, 1981

Inspectors: II. N Gardner

ll/$l6/

l

s

s

R.

. Land a

' /2.- 2 r- r/

-

' i

'Mit'

R.

Sut h

1,

/1 - 2 6 - 4 /

h

M

y

ins, Acting Chief

A /L&f&l

Approved By: F .i

aw

.

Plant Systems Section

I

I

Inspection Summary,

Inspection on November 18-20, 1981 (Reports No. 50-456/81-14; 50-457/81-14)

Areas Inspected: Observation of electrical cable termination activities,

observation of installed electrical equipment, observation of post-tension-

ing work and review of records, and observation of quality assurance program

performance. The inspection involved a total of 57 inspector-hours onsite

by three NRC inspectors.

Results: Of the three areas inspected, four items af noncompliance were

identified (failure to ensure that revision to specifications are trans-

lated into construction procedures; failure of manufacturer to install

required separation barriers in main control board panel; failure to take

adequate corrective action for post-tensioning noncompliances; and failure

,

to issue inspection instruction for tendon inspection after 90 days).

sre--

.

O

O

~.

.

.

4

DETAILS

!

Persons Contacted

, Commonwealth Edison Company (CECO)

i

  • R. Cosaro, Site Construction Superintendent

j

  • T. R. Sommerfield, Site QA Superintendent
  • C. D. Gray, Project Structural Supervisor
  • S. C. Hansader, QA Supervisor
  • W. D. Bruns, QA Inspector
  • C. Mennecke, Lead Electrical Engineer
  • D. A Broca, QA Supervisor
  • L. J. Tapella, Project Construction Engineer
  • R. C. Schleiter, Administrative Assistant

Napoleon Steel Contractors Incorporated (NSCI)

  • C. Zavada, QC Manager

!

  • T. M. Perala, Project Manager

I

  • V. Sawyer, Superintendent
  • D. Rayka, Project Engineer

L. K. Comstock and Company (LKC)

3

  • R. A. Brown, Sr., QC Manager

'

  • L. Facchina, Project Manager

<

  • J.

A. Hii, Project Engineer

}

  • Denotes those present at the exit meeting on November 20, 1981.

i

!

i

e

4

1

4

i

l

1

i

-2-

.

- - - -

,

- - , - - , ,

-

,

. , .

,. ,

1

.

Section I

Prepared by R. N. Gardner

Reviewed by F. C. Hawkins, Acting Chief

Plant Systems Section

l

1.

Observation of Electrical Cable Termination Activities

The Region III inspector observed the terminations for the

a.

following Class IE electrical cables in the Unit 1 main control

room:

Cable

,

i

1 AP 312

1 AP 083

!

1 AP 051

1 AP 050 (3 conductors were inspected)

The inspector verified that the cables were terminated in

accordance with Sargent and Lundy (S&L) wiring diagram 1-4044N,

Revision J.

The cables were observed to be trained into the

equipment without violation of minimum bend radius or separa-

tion criteria.

b.

The Region III inspector determined that the licensee had

purchased two types of electrical terminal lugs, for conductor

sizes smaller than No. 8 AWG, to be used on Class IE cable

terminations. The licensee had purchased " amp terminal" lugs

for use in non-high radiation areas and " amp nuclear terminal"

lugs for use in high radiation areas. Representatives of the

licensee's electrical centractor, L. K. Comstock, stated that

the contractor's electricians were being instructed to use only

the " amp nuclear terminal" lugs in high radiation areas. The

inspector verified that these actions were in accordance with

the latest revision of L. K. Comstock " Cable Termination In-

sta11ation" Procedure No. 4.3.9.

During subsequent discussions with the licensee and S&L repre-

sentatives, the inspector was informed that S&L " Electrical

Installation" Specification 2790A had previously been revised

to incorporate ECN 1359 which deleted the use of " Amp nuclear

terminal" lugs.

L. K. Comstock Procedure No. 4.3.9 had not

been revised to implement this revision to Specification 2790A.

As a result, unapproved terminal lugs were stored in Class IE

,

storage facilities and L. K. Comstock electricians were being

'

instructed to use these unapproved lugs on Class IE terminations.

This failure to control changes to specifications and procedures

to ensure the use of such changes at the location where the pre-

i

'

scribed activity is being performed is considered an item of non-

,

-3-

-.

-

-

.

.

!

.

.

t

l

l

compliance with 10 CFR 50, Appendix B, Criterion VI as described

in Appendix A of the report transmittal letter.

(456/81-14-01;

457/81-14-01)

During the NRC exit meeting on November 20, 1981, the licensee

stated that the following actions had been initiated with regard

to this matter:

(1)

L. K. Comstock Procedure No. 4.3.9 was being revised to

!

reflect the terminal lug requirements of S&L Specifica-

!

tion 2790A.

l

(2)

L. K. Comstock procedures were being reviewed to assure

implementation of current S&L specification requirements.

(3) All unapproved terminal lugs were removed from Class IE

storage to ensure that they will not be used on Class IE

cables.

(4)

L. K. Comstock electricians "ere being instructed in the

identification of approved terminal lugs to be installed

on Class IE cables.

The licensee stated that no unapproved terminal lugs have been

installed on Class 1E cables.

The RIII inspector verified that approved terminal lugs were

installed on all Class IE terminations observed during this

inspection.

During a review of the manufacturer's literature pertaining

c.

to the " amp terminal" lugs now specified for use in all areas

of the plant, the inspector was unable to determine the

acceptability of the lugs for use in hostile environments

i

l

(e.g., high radiation, high temperature). The literature

l

indicated that the lug insulating material was composed of

vinyl or plastic.

The Region III inspector contacted NRC Region IV Equipment

Qualification Section personnel on November 23, 1981, concern-

ing the acceptability of the subject lugs for use in hostile

environments. During a conversation on December 7, 1981, the

Region III inspector was informed that the consensus of opinion

within the Region IV Equipment Qualification Section was that

the subject lugs were acceptable. The Region III inspector

has no further questions concerning this matter at this time.

2.

Observation of Installed Electrical Equipment - Main Control Boards

During observation of the internal components and equipment pertaining

to the Units 1 and 2 main control boards, the inspector determined the

I

!

following:

!

1

-4-

l

- _ _ _

-

-

~

!

i

l

.

-

l

5

Paragraph 4.1.5 of Westinghouse Specification 952538, Revision 1,

a.

states that, " Barriers shall be installed between PAM-1 and

PAM-2 indicators to provide separation."

The inspector observed the following examples of the manufac-

turer's failure to install the required separation barriers

between adjacent indicators located on the Westinghouse supplied

main control board panel 1 PM 04J.

'

ADJACENT INDICATORS

PARAMETER MONITORED

IPI-524A (PAM-1)

Steam Generator Steam Pressure

IPI-525A (PAM-2)

Steam Generator Steam Pressure

IPI-526A (PAM-1)

Steam Generator Steam Pressure

IPI-534A (PAM-1)

Steam Generator Steam Pressure

1PI-535A (PAM-2)

Steam Generator Steam Pressure

1PI-536A (PAM-1)

Steam Generator Steam Pressure

The subject indicators are identified as being part of the

Post-Accident Monitoring (PAM) system on S&L drawings

20E-1-4049A, Revision E and 20E-1-4049B, Revision E.

Additionally, the inspector cbserved that barriers were not

installed between the corresponding Unit 2 indicators located

on Unit 2 main control board panel 2 PM 04J.

This failure to assure that purchased equipment conforms to

procurement specifications is considered an item of noncom-

pliance with 10 CFR 50, Appendix B, Criterion VII as described

in Appendix A of the report transmitcal letter (456/81-14-02;

457/81-14-02)

b.

Westinghouse Specification 952538, Revision 1, identified four

categories of main control board internal " critical wiring."

The inspector observed that the method developed for identify-

ing the different categories of internal wiring involves the

use of color coded markers which are installed within the main

control board panels. The inspector observed that the separa-

tion of internal wiring within the panels was less than one

inch at some locations. However, the correlation between the

installed color coded markers and the assignment of cables

to " critical wiring" categories was not clear. Westinghouse

Specification 952538 indicates that the internal wiring

separation criteria is dependent upon the assigned " critical

~

wiring" category.

This matter is unresolved pending further review by the

inspector of the Westinghouse specifications and drawings

pertaining to internal wiring separation requirements.

(456/81-14-03; 457/81-14-03)

-5-

9

e

l

'

'

,

-

.-

- _ . -

_-

.-__

-

.

.

Section II

Prepared by R. B. Landsman

Reviewed by F. C. Hawkins, Acting Chief

Plant System Section

.

i

1.

Observation of Work _ Activities

Stressing of horizontal tendon No. 35 CB by Napoleon Steel Con-

tractors, Inc., (NSCI) was observed. The inspector verified that

the work was being accomplished in accordance with site procedures.

!

All pertinent work and data was being verified by the QC Inspector.

2.

Review of Quality Records

!

The following reviews of post-tensioning records were performed to

j

verify their completeness and compliance with licensee specifications,

procedures and commitments:

It was determined from a review of gauge records that two

a.

gauges were found to be out of calibration on November 16,

1981.

NSCI corrective action was to send the gauges back to

Inryco for recalibration. However, corrective action was not

taken to identify and cortect any potential deficiency caused

by the use of the gauges. This failure to take proper correc-

tive action with regard to the nonconforming gauges is contrary

to Criterion XVI of 10 CFR 50, Appendix B.

(456/81-14-04) (A)

b.

NCR's were also reviewed to assure that the specified resolutions

-

addressed the cause of the nonconforming conditions and that

appropriate corrective actions were taken. During this review,

it was determined that the resolution of NSCI NCR No. 137 was

incomplete.

NCR 137 addressed the fact that dome tendons were not being

stressed according to stressing sequence number 25.

The

specified disposition noted on the NCR was to remove and

.

replace a defective tendon. The disposicion did not address

the fact that the stressing sequence was violated. The Region

III inspector determined that this failure to follow the

designated sequence was an isolated case.

This is considered a further example of noncompliance as cited

previously in Section 2., Paragraph 2.a. of this report.

(456/81-14-04) (B)

Through the review of tendon installation records, the inspectors

c.

determined that seventeen tendons had been in place over 180

days without being greased. Tendon installation Specification

L-2722 requires that tendons be greased with in 180 days after

.

insertion. Discussions with NSCI personnel indicated that they

misinterpreted the specification requirements.

-6-

.

,

i

This failure to promptly identify and correct nonconforming

conditions is considered a further example of noncompliance

as cited previously in Section 2. , Paragraph 2.a. and 2.b.

of this report.

(456/81-14-04) (C)

As a result of this finding, the NSCI QC Manager issued NCR

No. 167 to identify this nonconforming condition.

,

d.

Records of grease shipments were reviewed.

The records con-

tained appropriate documentation verifying that all physical

and chemical requirements were met.

The inspector also re-

viewed the purchaser's onsite test results, as required by

Specification 2721, and determined that they were being pro-

perly performed.

-

-7-

Section III

Prepared by R. N. Sutphin

Reviewed by J. M. Peschel, Acting Chief

Management Programs Section

1.

Observations of the Quality Assurance Program Performance Relative

to Drawings and Specifications

In the inspection areas covered by Sections 1 and 2 of this report

the inspector found that field drawings and specifications were

maintained under appropriate revision control and were readily

available for reference and use during the work activity. Revision

Control Logs and Records were maintained and up to date. Documents

in the hands of site contractors and sub-contractors were maintained

in an equally acceptable manner. The inspector observed that there

were differing responses from personnel at the site working on con-

tainment post-tensioning as to which document was to be used to control

the work in progress. Letters, drawings, design specifications, and

procurement specifications were identified as controlling documents

by supervisory personnel but they could not assure the inspector that

these were controlled documents traceable to the controlled contain-

ment specifications. This apparent uncertainity as to the identity

and traceability of documents governing containment post tensioning

is considered an Unresolved Item subject to future detailed review.

(456/81-14-05; 457/81-14-04)

2.

Observations of the Quality Assurance Program Performance Relative

to Field Inspections, Measurements and Workmanship

.

The inspector witnessed the tensioning of tendon number 35 CB of

the Unit I containment post-tensioning system and the wiring

activity on Units 1 and 2 control boards in the control room, to

i

discern if the equipment or systems were being installed / erected

as described by drawings and specifications and that inspections,

measurements and workmanship were receiving appropriate considera-

tion, per quality program requirements. Observations of the work

in process indicated that the work was being accomplished in a

satisfactory manner except for those items identified in Sections

I and 2 of this report, and the inspection of tendons in place

after 90 days without greasing.

S&L Specification L-2722, Revision 14 " Injection of Corresion

Preventive Grease," Section 13-508.2, states in part, "In addition,

each tendon which is not stressed within 90 days after it is in-

stalled in it's sheating, shall be greased within that 90 day

period." ... " Time from initial placement of the tendons to greasing

'

may be increased to 180 days, provided a random sample of 10% of

i

the tendons are withdrawn monthly between the 90 and 180 day period

and inspected for corrosion. Tendons which show signs of corrosion

during the 90 to 180 day period shall be rejected."

l

-8-

.

.

A review of nonconformance reports and records indicated that this

requirement was known and that some inspections relative to the

potential problem of tendon corrosion were attempted, but with

results that are generally inconclusive and unresponsive to the

requirements.

l

l

The inspector found that over 150 tendons had been installed for 90

days or more without greasing, that an inspection instruction or

procedure had not been written to address the requirements in the

specification for the corrosion inspections, that key aspects of

the requirement had not been defined or documented (i.e., random

sample; 10% of the tendons; withdrawn; monthly; acceptance criteria;

,

signs of corrosion; etc.) and that the information provided from

the effort that was undertaken failed to satisfy the inspection

requirement. This is a violation of the inspection criteria of

<

10 CFR 50, Appendix B, Criterion X.

(456/81-14-06)

3.

Observations on Field Engineering Activity

The inspector determined that engineering personnel were assigned

'

to the site by the licensee and the contractors, independently

of the quality assurance organization, providing direction and

assistance in control of the work.

4.

Observations of Quality Control / Inspection Activities

The inspector reviewed the Quality Control and Inspection Activities

of a contractor at the site, NSCI, and determined that these functions

were being performed in an independent and effective manner with some

overview audits and inspections by licensee personnel. However, find-

ings by the NRC inspectors in the area of corrosion inspection of

tendons, indicates that more information is needed to allow the in-

spector to determine if increased attention to specification and

procedural detailed requirements by the Quality Assurance overview

personnel may be necessary to assure that timely and proper Q.C.

Program Action is accomplished. This is an Unresolved Item subject

to further revies. (456/81-14-07; 457/81-14-05)

5.

Observation of Nonconformance Reports and Corrective Action Activity

The inspector reviewed records and reports relative to nonconformance

reporting and the specified dispositions and corrective actions. The

inspector found that the reporting of nonconforming conditions by

'

contractors was acceptable end in an effective and timely manner.

,

Conversely, actions taken to address the repair or disposition of

the identified problems and the appropriate corrective actions do

not appear to be as effective, as indicated below:

During a review of NCR's prepared by LKC for the period of time

from August 5, 1981 to October 15, 1981 (NCR's 252 thru 381), it

was determined that one third (33.8%) of the recommended disposi-

tions for similar conduit installation problems was:

"use-as-is,"

i

-9-

.

-

- -

-

-

_

-

-

.

.

"will not (or does not) affect structural integrity," and (FCR)

.

Field Change Request documents were written to refer the problems

'

for design review and approvals, etc.

In addition to the above, NCR No. 252 was processed two times.

It

was written on August 5, 1981 and processed the first time on

'

August 27, 1981 with concurrence signatures on August 28, 1981, and

the second time on September 18, 1981 with concurrence signatures

on September 22, 1981 with essentially the same use-as-is disposi-

tion. Both copies are on file.

The inspector questions whether the "use-as-is" concept, with an

,

installation prior to a design review, is consistent with established

Quality Program objectives and considers this an Unresolved Item

subject to further review (456/81-14-08; 457/81-14-06).

6.

Observations on Materials and Equipment Receiving, Inspection and

Use at Site

The inspector briefly reviewed, with various site supervision and

management personnel participating, the general policies and pro-

cedures relating to the procurement, receipt, inspection, control

and use of items at the site.

.

,

The inspector observed that QC, QA, Site Supervision and Management

Personnel frequently suggested or recommended changing specifica-

tions or requirements when conflicts or problems were identified,

as a means of potential resolution of the problems. The inspector

considers the prevailing attitude to change specifications and

,~

requirements as somewhat adverse to compliance with established

Quality Program objectives and considers this an Unresolved Icem

subject to further review (456/81-14-09; 457/81-14-07).

7.

Observations of Audit Programs

The inspector reviewed the audit program schedules and determined

that audits had been scheduled in April 1981 and October 1981, for

NSIC, the contractor responsible for containment post-tensiening

activities. The April 1981 audit was scheduled to cover QA Manual

Sections 1 through 5 - the entire QA Manual. The October 1981 audit

was scheduled to cover Applicable Procedures for Post-Tensioning

Activities.

1

The April 1981 audit report was on file as No. QA-20-81-18, 2722-B.

22A. The October 1981 audit report was on file as No. QA-20-81-31,

2722-B.22A.

'

The audit plan covered several areas of the post-tensioning activi-

ties in sufficient detail to be considered an acceptable plan.

/

- 10 -

-

j

1

.

.

Additionally, Item 21 of the October 1981 audit plan specified:

" Verify that stressed tendons are greased within one week of com-

pletion of stressing," (i.e., seven days). The audit found the

4

following:

Tendon

Days to Greasing

D3-1

20

D1-12

1

'

1

V-118

23

V-120

9

V-121

23

Someone added a note, in pencil, to the audit report copy:

"one

week or 28 days - Spec." and referenced Specification L-2722, Section

13-508.2.

The original copy of the audit plan had not been changed

'

for Item 21.

The added pencil note was not dated or signed and

appears to be contrary to the auditing requirements of ANSI N45.2-1977.

The inspector is concerned about the apparent flexibility in penciled

changes to the audit plan. This is considered an Unresolved Item

subject to further review (456/81-14-10; 457/81-14-08).

Unresolved Items

Unresolved Items are items about which more information is required in

order to ascertain whether they are acceptable items, items of noncom-

pliance or deviations. Unresolved items disclosed during this inspection

are discussed in Section 1, Paragraph 2.b, and Section 3, Parta 1, 4, 5,

,

'

6, and 7.

.

Exit Interview

The inspectors met with licensee representatives (denoted in the Persons

Contacted paragraph) at the conclusion of the inspection on November 20,

3

.

1981. The inspectors summarized the scope and findings of the inspection.

The licensee acknowledged the information.

.

O

4

- 11 -

a