ML20039C092

From kanterella
Jump to navigation Jump to search
IE Insp Rept 50-483/81-25 on 811110-13.Noncompliance Noted: Failure to Perform Adequate Insp
ML20039C092
Person / Time
Site: Callaway Ameren icon.png
Issue date: 12/14/1981
From: Hawkins F, Love R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML20039C081 List:
References
50-483-81-25, NUDOCS 8112280395
Download: ML20039C092 (5)


See also: IR 05000483/1981025

Text

..

. .

.

.

.

..

.

. _ _ _ _ _ _ _ _ - _ _ - _ _ - _ _ _ _ _ _

__ -

.

U.S. NUCLEAR REGULATORY COMMISSION

REGION III

Report No. 50-483/81-25

Docket No. 50-483'

License No. CPPR-139

Licensee: The Union Electric Company-

Post Office Box 149

St. Louis, MO 63166

Facility Name: Callaway, Unit 1

Inspection At: Callaway Site, Callaway County, MO

l

. Inspection Conducted: November 10-13, 1981

-r

is

l~L,fl4./8 {-

Inspector:

e

.

.

,,

~

Approved By: FI C. Hawkins, Acting Chief

1Z./ lS{/6l

'

f

Plant Systems Section

Inspection Summary

Inspection on November 10-13, 1981 (Report No. 50-483/81-25)

Areas Inspected: Observation of electrical cable installation and termina-

tion activities; review of cable installation and termination records and

procedures; and review of related quality records. This inspection in-

volved a total of 30 inspection-hours on site by one NRC inspector.

Results: Of the areas inspected, one apparent item of noncompliance was

identified.

(Criterion X - failure to perform adequate inspections --

Paragraph B.2.).

8112280395 811215'N

gDRADOCK 05000483!

PDRj.

_

.

.

.

..

,

DETAILS

Persons Contacted

Union Electric Company

  • W. H. Weber, Manager - Nuclear Construction

R. L. Powers, Superintendent - Site QA

  • J. McGraw, Supervising Engineer

J. V. Laux, Supervising Engineer - QA Construction

  • S. M. Hogan, Assistant Engineer - QA Construction
  • W. H. Stahl, Test Program Coordinator
  • W. M. Dossett, QA Consultant

R. Veatch, Assistant Engineer - QA Construction

Daniel International

A. D. Arnold, Project Quality Manager

F. M. Warblow, Services Manager

D. E. Stites, Project Quality Control Manager

Delcon

  • J. J. Mullen, Project Electrical Engineer

J. Weaver, Project Electrical Manager

The inspector also contacted and interviewed other licensee and contractor

personnel during this reporting period.

  • Denotes those present at the exit interview.

Licensee Action on Previously Reported Items

(Closed) Unresolved Item (50-483/80-15-01): Based on reports thit some

Rockbestos electrical cable had been spliced, the licensen was requested

to determine if splices might also exist in cable that had been purchap'd

and installed at Callaway.

Bechtel Power Corporation letter BLSE-8489, dated .'uly 10, 1980, states in

part, "Rockbestos has stated that no cable butt splices are made on the

SNUPPS orders.

Inspection of Rockbestos cable at the Woli Creek jobsite

and of sample reels at Rockbestos have found no evidence of butt splices."

(Closed) Open Item (50-483/81-20-03): During a previous inspection, minor

errors were noted in procedures WP-303 and QCP-303 that the licensee agreed

to correct. The errors in the subject procedures have been corrected.

(Closed) Unresolved Item (50-483/81-20-02): Daniel Procedures WP-303,

Revision 8, and QCP-303, Revision 7, did not address how the licensee

was going to verify that the cable pulling tension had not been exceeded

when small electric cables and/or instrument cables were pulled. This

-2-

d

'

.

item is upgraced to an item of noncompliance, see paragraph B.2 of this

report.

-

'

(Closed) 10 CFR 50.55(e) Report (50-483/79-03): Defective type SB-12

auxiliary switches on GE metalclad switchgear. The inspector reviewed

Union Electric's final report to Region III (ULNRC-322, dated August 10,

1979) with attached report and nonconformance report (NCR) number

2SN-0822-E which was prepared to track this item. Action to replace the

15 defective SB-12 switches has been completed and the subject NCR was

closed on March 12, 1981.

Functional or Program Areas Inspected

A.

Observation of Electrical Work Activities

1.

The Region III inspector observed five Class IE cables in the

main control room that lacked proper support. A similar condi-

tion was previously reported in IE Report 81-14.

Although

there was no evidence of damage to the subject cables, the

potential for damage was present.

In response to the inspector's

concern, the licensee took immediate action to have the cables

properly supported. The inspector has no further questions

regarding this matter at this time.

2.

During inspection of installed equipment, the Region III in-

spector observed that corrosion was present on cable lugs in

MCC NG04D. The licensee prepared Deficiency Report (DR) No.

2SD-4835 to properly identify and disposition this item. The

equipment has been turned over to Union Electric.

3.

The RIII inspector observed various electrical panels, cabinets,

and switchgears for proper terminations, cable support, cable

bend radius and cable separation. All items observed were in

accordance with applicable instructions, procedures and drawings.

4.

During a review of electrical cable installation activities,

the Region III inspector observed that SKV cable was being

separated by one cable diameter in accordance with the project

drawings. Three tray sections were also inspected to verify

that all installed cables were properly identified as Class 1E

(i.e. , red, white, blue or yellow).

5.

During a review of electrical cable tray installation activities,

the Region III inspector observed that:

a.

In the reactor building at elevation 2030', cable trays

4U2A08 and 4U2A09 were only separated by 26" from trays

6J2B08 and 6J2B09. Further investigation indicated that

l

barriers would be installed in accordance with drawing

E-0R2411(Q), Revision 9 in order to meet separation re-

quirements.

--3

-

,

1

i

-

..

b.

"In the control building at elevation 2000', an unidentified

insulated 8" pipe was identified within twelve inches of

cable tray 4J1C63'and within twenty-four inches of trays

4U1C62, 4GIC62 and 4B1H62.

It was also observed that 8"

pipe, number 2-EF-07-S-015 and 017, was within twelve

inches of cable trays 4U1C56 and 60 4U1C56 and 60 and

4G1C45 and 60.

'

Pending a review of the seismic design analysis for the pipe

supports, this item is unresolved (50-483/81-25-01).

B.

Observation of Electrical Procedures and Records

1.

The Region III inspector observed that Daniel Procedures WP-230,

" Field Fabrication and Installation of Instrumentation" and

QCP-230, " Inspection of Fabrication and Installation of Instru-

mentation" do not address the identification of instrument sens-

ing lines.

In a position letter regarding this subject, the NRC

states that instrument sensing lines shall be identified in

accordance with IEEE 279, paragraph 4.22.

The NRC position was

discussed at length with licensee representatives who acknowledged

the requirements. Presently, the installation of instrument sens-

ing lines is less than 5% complete at the Callaway site. This

item is open pending review of procedure revisions and the imple-

mentation thereof (50-483/81-25-02).

.

2.

During a review of the cable pull records for the NG System,

the Region III inspector observed that the Cable Installation

Checklist was marked "NA" or " Hand Pull" under the checkpoint,

" Maximum pull tension applied to cable during pull".

This

condition was evident for'all Cable Code CO2 and JIP pull records

reviewed. Appendix B to Bechtel drawing No. E-01013(Q), Revision

5, lists the maximum pulling tension for Cable Code J1P as 32

pounds and 65 pounds for Cable Code CO2.

The following cable pull records were reviewed:

a.

INGB10AA, length - 90', pull started September 2, 1980

and completed December 17, 1980, Csble Code - CO2.

b.

INGG01DB, length - 190', pull started July 15, 1980 and

completed November 13, 1980, Cable Code - J1P.

c.

INGG015E, length - 210', pull started July 15, 1980 and

completed November 13, 1980, Cabte Code J1P.

-

d.

INGG02AD, length - 210', pull started October 27, 1980

and completed November 7, 1980, Cable Code - J1P.

e.

INGR01AB, length - 264', pull started August 13, 1980 and

completed December 3, 1980, Cable Code - J1P.

-4-

-

=

W

-

..

,,

In each instance, items a. thru e. above, the licensee failed

to verify that the maximum allowable cable pulling tension and

sidewall pressure, as specified by Appendix B to Bechtel drawing

No. E-01013(Q), had not been exceeded.

The Region III inspector informed the licensee that tnis failure

to execute an inspection program to verify conformance with the

documented instructions, procedures.and drawings is considered

an item of noncompliance with 10 CFR 50, Appendix B, Criterion

X as described in Appendix A of the report transmittal letter.

(50-483/81-25-03)

-

Unresolved Items

Unresolved items are matters about which more information is required in

order to ascertain whether they are acceptable items or items of noncom-

pliance. Unresolved items disclosed during this inspection are discussed

in paragraph A.5.b.

y

Open Items

Open items are matters, not otherwise. categorized in the report, that need

to be followed up on in future inspections. Open' items disclosed during

this inspection are discussed in paragraph B.I.

-Exit Meeting

The inspector met with licensee representatives (denoted under Persons

Contacted) on November 13, 1981. The inspector summarized the scope and

findings of the inspection. The licensee representatives acknowledged

the findings reported in previous paragraphs.

,

s

-5-

_

,_

-

-

,

. _ _

,

_

_,