ML20039B513

From kanterella
Jump to navigation Jump to search
IE Insp Repts 50-443/81-12 & 50-444/81-10 on 811005-1106. Noncompliance Noted:Failure to Erect Instrumentation Supports in Accordance W/Controlling Design Document
ML20039B513
Person / Time
Site: Seabrook  NextEra Energy icon.png
Issue date: 11/25/1981
From: Cerne A, Gallo R, Reynolds S, Schulz R, Varela A
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML20039B508 List:
References
50-443-81-12, 50-444-81-10, NUDOCS 8112230174
Download: ML20039B513 (15)


See also: IR 05000443/1981012

Text

.

.

.

U.S. NUCLEAR REGULATORY COMMISSION

OFFICE OF INSPECTION AND ENFORCEMENT

Region I

50-443/81-12

Report No.

50-444/81-10

50-443

Docket No. 50-444

CPPR-135

License No.

CPPR-136

Priority

Category

A

--

Licensee: Public Service Company of New Hampshire

1000 Elm Street

Manchester, New Hampshire 03105

Facility Name: Seabrook Station, Units 1 and 2

Inspection at: Seabrook, New Hampshire

Inspection conduc ed: October 5-November 16,1981

Inspectors:

H')

i

A. C. Cerne, Sr. Resident Inspector

date signed

,0 O '

OL

l'

8l

'

5'. D. R'eynol ds , / Reactor Inspector

date signed

OL L

nlmlet

fa R. D. Schulz, Reactor Inspector

date signed

/v' . .sh

//

2Il

7

A. A. Vaktla, Reactor Inspector

d~te signed

a

Approved by:

N

(

ll 2 d9 l

R. M. Gallo, Chief, Projects Section 1A,

date signed

Division of Resident and Project Inspection

Inspection Sumary:

Unit 1 Inspection on October 5-November 16,1981 (Report No. 50-443/81-12)

Areas Inspected: Routine inspection by the resident inspector and regional. based inspectors

of work activities relative to the piping QA program, pipe installation, welding, and

supports; concrete placement preparation, cadweld splicing, site civil testing, and con-

tainment liner and concrete interfacing; component installation; instrumentation supports;

and structural connections to include design control over the structural impact of combined

loadings. The inspectors also reviewed licensee action on previously identified items and

perfonned plant inspection-tours. The inspection involved 96 inspector-hours including five

off-shift hours, by four NRC inspectors.

Results: Of the five areas inspected, one item of noncompliance was identified in one area--

failure to erect instrumentation supports in accordance with the controlling design

document (paragraph 8

).

Unit 2 Inspection on October 5-November 16,1981 (Report No. 50-4 4/81-10)

Areas Inspected: Routine inspection by the resident inspector and two regional based in-

~

spectors of work activities relative to'the piping QA program, concrete and cadwell installa-

tion, and plant inspection-tours. The inspection involved 17 inspector-hours by +nree NRC

inspectors

Results: No items of noncompliance were identified.

g 2 h p o!00

G

PDR

- .

- -

- -

- - -

-

.

.

DETAILi

1. Persons Contacted

Yankee Atomic Electric Company (YAEC)

F. W. Bean, Lead Electrical QA Engineer

F. X. Bellini, Site Geolocist (PSNH)

D. L. Covill, Lead Civil QA Engineer

J. H. Herrin, Site Manager (PSNH)

D. A. Maidrand, Project Engineer (Framingham)

G. F. Mcdonald, Jr., QA Manager (Framingham)

J. F. Nay, Jr., Lead Mechanical QA Engineer

J. W. Singleton, Field QA Manager

R. Tucker, Engineer (Framingham)

United Engineers and Constructors (UE&C)

R. G. Blair, Civil Superintendent

G. Burriello, Welding Engineer (Philadelphia)

M. A. Edgar, Resident Construction Engineer

J. A. Grusetskie, Assistant Liaison Engineer

A. J. Hulshizer, Supervisory Structural Engineer (Philadelphia)

R. A. Kountz, Welding Superintendent

D. C. Lambert, Field Superintendent of QA

D. E. McGarrigan, Project QA Manager (Philadelphia)

R. A. Rebel, Resident Construction Manager

G. Shaw, Structural Steel Superintendent

R. D. Tancibok, QA Supervisor

Johnson Controls, Inc. (JCI)

A. O. Kennedy, QC Manager

R. G. Walter, Project Engineer

Perini Power Constructors (PPC)

S. M. Bednar, Chief Cadweld Inspector

K. B. Grandmont, Cadweld Superintendent

G. E. Myers, Assistant Site QA Manager

R. W. Narva, Supervising QA Engineer

PittsburghTestingLaboratory(PTL)

H. Ruffner, Site Manager

Pullman-Higgins (Pullman)

R. G. Davis, Field QA Manager

R. R. Donald, Field QA Supervisor

D. R. Geske, QC Supervisor

D. B. Hunt, QA Records Supervisor

C. Scannell, Chief Field Engineer

Royal Insurance

J. C. Anzivir.o, Authorized Nuclear Inspector

G. Voishnis, Authorized Nuclear Inspector

Westinghouse

J. Ellis, Welding Engineer

R. Powell, Project Manager

C. E. Walker, Liaison Engineer

.

.- .

- -

.w

.

.

3

2.

Plant Inspection-Tours (Units 1 and 2)

The inspectors observed work activities in-progress, completed work and plant

status in several areas of the plant during general inspections of the plant.

The inspectors examined work for any obvious defects or noncompliance with

regulatory requirements or license conditions. Particular note was taken of

the presence of quality control inspectors and quality control evidence such

as inspection records, material identification, nonconforming material

identification, housekeeping and equipment _ preservation. The inspectors

interviewed craft personnel, supervision, and quality inspection personnel as

such personnel were available in the work areas.

-

Specifically, the inspectors examined the control and accountability of

cadweld tensile testing with regard to the USNRC regulatory position of

Regulatory Guide (RG) 1.10.

Reinforcing steel delivery and installation and

-

cadwelding operations were witnessed in Units 1 and 2 containment building

areas, as were welding activities on the Unit 2 eleventh containment liner

ring. .

The temporary installation and support of the Unit 1 main steam and feedwater

piping inside containment was observed. An inspector witnessed fabrication

.

activities for the Unit 1 pipe whip restraint installation and spot-checked

.estraint schedules and drawings for adequate control of material, location,

and assembly details. An embedded' plate in the primary shield wall which

was designed for interface support of restraint PW-201-2 was visually checked

for correct size, orientation and location and ultrasonically examined for

proper thickness, with reference to UE&C drawings F104036, Revision 2, and

F104075, Revision 5.

4

Also, a regional inspector accompanied licensee and NRR geologist personnel

on a tour of the two nonsafety-related cooling water tunnels on October 19,1981.

,

Bed rock features on portions of the completed machine-bored tunnels, currently

being lined with formed concrete, were observed.

No items of noncompliance were identified.

3.

Licensee Action on Previous Inspection Findings

,

a.

(Closed) Unresolved item (443/80-12-01): Justification for multiple

cadweld splices in series - NRC inspection report #443/81-07 continued

,

this item unresolved pending the following:

1.

Licensee concurrence in UE&C technical evaluation and conclusion that

the effect of multiple splices in series in Unit I containment shell

is insignificant.

2.

NRC technical review of the potential effect that multiple cadwelds, as

located, have upon the containment shell concrete.

The Licensee concurred in the UE&C evaluation of the significance of

multiple cadwelds on containment concrete shell crack control. Also,

the NRC has reviewed the UE&C technical evaluation and recommends that

one of the areas with multiple splices be selected to perform crack-

mapping during the containment structural integrity test (SIT). At-

this inspection the licensee committed to identify one of the areas with

multiple splices as one of the five areas to be mapped according to

-

-.

.

.

Regulatory Guide 1.18.

The inspector was informed by the licensee that

this will be entered into YAEC's computer program of long term verification

items to assure that the aforementioned test and evaluation of that area

is performed. Since any future potential safety concerns would be

identified by the SIT and its data analysis, the inspector considers

this item currently closed.

b.

(Closed) Noncompliance (443/80-13-03): Fiald initiated design changes /

controls for rebar cadweld splice stagger. The inspector reviewed UE&C

Engineering Change Authorization (ECA) 01/2127A and noted that it had

been incorporated by interim procedure change into the affected Pe'ini

QC procedure, QAP 10.3, Revision 5.

The corrective actions don'meited

in the licensee response to the NRC Notice of Violation were conlmed.

This item is closed.

c.

(Closed) Noncompliance (443/81-01-02): Lack of skewed fillet weld

acceptance criteria. The inspector reviewed ECA 25/0327A, Pullman Field

Instruction FI 103 (Revision 1) and Pullman Procedure JS-1X-6

(Revision 2) to substantiate procedural controls over the handling of

ASME Section III skewed fillet welds. Various random field inspections

of ASME NF support installation confirmed that welders were installing

welds and that QC inspection was being accomplished in accordance with

the newly established criteria. The inspector verified the conduct of

training in this area. This item is closed.

d.

(Closed) Noncompliance (443/81-03-02): Unspecified pipe support weld

lengths - Also reported as a potential significant deficiency under

10CFR50.55(e). The inspector examined ECA 25/0559A and notec the issuance

of revised pipe support details for approximately 24 hangers, to include

minimum weld length criteria. Discussions with Pullman engineering and

QA personnel confinned that official Requests For Information to the A/E

would be initiated for any welds for which weld lengths were undefined

and could not be determined dimensionally. The licensee investigation

of this design deficiency uncovered no actual cases of installed supports

with inadequate weld lengths.

Ned upon Oe scope of licensee corrective action, evidence that previous

hanger instaliations are adequate, and revisions to the contractor

procedure (Ptilman JS-1X-6) controlling the welding of safety-related

pipe support: , all aspects of this issue, both as a noncompliance and a

potential sitnificant deficiency are considered closed,

e.

(Closed) Unrtsolved item (443/81-05-03): Regenerative Heat Exchanger

bolting and torquing to ASME and design considerations. The inspector

reviewed the following documents which confirmed that the regenerative

heat exchanger and any other potentially affected ASME Section III

items which are supported by noncode anchor bolts, have been consicared

with regard to design torque and NF bolting requirements and installed

accordingly.

-- UE&C Memo S/L CE-1491 (10/8/81)

-- ECA's 01/1875D, 01/24618, 01/2737A, and 08/1166A

Since the A/E has confirmed code applicability to the component / bolt

-

-

- -

.

.

.

5

interface and specified design torque requirements for all previously

questioned components, to include the regenerative heat exchanger, this

item is considered resolved.

f.

(Closed) Unresolved item (443/81-07-02): NRC concerns o. u the lamellar

tearing potential on the RCPB crossover leg support welding. Both the

resident inspector and a regional based specialist observed the conduct

of the crossover leg support welding and discussed the in-process

controls to prevent the occurrence of lamellar tears with welding,

engineering, and QC personnel. Details of the inspection of this area

are presented in paragraph 12:.

Both the governing procedures and the

conduct of welding to date appear to have adequately addressed the specified

NRC concerns. This item is resolved.

4.

Concrete Construction and Inspection Activities (Units 1 and 2)

a.

Cadweld Splicing of and Installation of Reinforcing Steel in Unit 1

Containment Wall

Inspections were performed of Perini work and QC activities in cadwelding

  1. 18 reinforcing bars for the Unit I t.ontainment exterior wall. The NRC

inspector evaluated these activities for conformance to criteria identified

in the following:

- Seabrook Station PSAR Section 3.8 and its referenced Standards

and Chapter 17

- P.P.C. Quality Control Procedure 10.2, Reinforcing Steel Placement

Inspection

- P.P.C. Quality Control Procedure 10.3 (Revision 5) with IPC 4,

Cadwelding Inspection

- UE&C Field Civil Construction Procedure FCCP-7, Mechanical

Splicing of Reinforcing Bars

- ERICO Publication RB-10M-974

The fabrication of horizontal #18 reinforcing hoop splices was observed

for adequacy and QC control during off-stand rebar preparation, cadweld

splice equipment fit-up, powder and starter placement and firing. Post-

fire inspection and documentation by QC were observed. Cadweld operators

and QC inspectors appeared qualified and thoroughly knowledgeable of

their respective procedures. The inspector also witnessed installation

of interior hoop splices at elevation 105' and discussed with the PPC

cadweld foreman, field engineers and supervisory QC personnel the occurrence

of a below strength sister-splice tensile test (Sleeve #244-905-368/

splice #3010), and resulting PPC nonconformance report (NCR) 2220 and

Stop-Work Directive (SWD) 7.

The disposition of the NCR and lifting of

the SWD were observed to conform with the ASME III, Division 2 requirements

in section CC-4300.

No items of noncompliance were identified.

b.

Concrete Placement in Unit #1 Containment Exterior Wall and Common

Circulating Water Pump House

Inspections were performed of Perini work and QC activities in preparation

-

-

.

.

6

for and during concrete placement and post-placement curing of the

following pours:

(1) Personnel air lock portion of containment #1 exterior wall, pour

  1. PAL-1-CS-IT-2

(2) Circulating water / pump house walls, pour #S-CWTH-BF, at elevation

-15' to

-7'.

The NRC inspector evaluated these activities for

confonnance to criteria identified in the following:

-- Seabrook Station PSAR Chapter 17 and Section 3.8 and its

referenced codes and standards

-- Job Specification 13-1- Safety related concrete work, other

than containment

-- Job Specification 13-2, Containment Concrete Work

-- Job Specification 5-1, Civil Testing Facility and Services

-

-- PPC Quality Control Procedures:

- QAP 10.4, Concrete Batching, Delivery

- QAP 10.5, Concrete Pre-placement and Post-placement Inspection

- QAP 2.0, Qttalification and Certification of QA Personnel

- QAP 10.0, Qualification and Certification of Concrete

Production Facilities

-- PPC Field Civil Construction Procedure - FCCP 2, Formwork and

Handling, Placing, Curing, Finishing and Repair of Concrete

-- PTL Quality Control Procedure QC-FSTC-1, Field Sampling and

Testing of Concrete, and PQ-2, Qualifications for Inspection

and Testing Personnel.

The inspector observed both work performance and quality control activities

and verified the scope and adequacy of the following licensee / contractor

actions:

-- Verification of rebar_ adequately installed; cadweld splices

inspected and tested.

-- Formwork: clean, with required rebar clearance and securely

braced.

-- Construction Joints:

treatment for both vertical and horizontal

joints was identified by a UE&C field engineer and found

confonning to requirements of ACI 318 Section 11.7.9.

-- Preplacement Preparation and Inspection Report:

check-out

card signed off by craft supervisors; field engineer check-out

and signature; incomplete items on clean-up are closed; iden-

tification of specific items inspected; QC inspector sign-off;

release of pour by area engineer and QC supervisor; approval

by UE&C field engineer and resident engineer for the placement.

-- Delivery and Placement: proper mix specified, batched and

transported to pump locations; tested prior to discharge into

pump for slump and air and in-process tested for record purpose

at end of pump discharge by qualified inspection personnel.

-- Placing Crew and Equipment:

adequate craft personnel and

equipment, as required by special procedure, were coordinated by

field engineers and craft supervision.

-- Placement Practice and Consolidation:

the advance of concrete

and placement of successive lifts was accomplished while co crete

was still plastic and coordinated to prevent segregation and rock

1

.

.

7'

pockets; limitation of horizontal movement, control of free fall

through top layers of steel, and consolidation with calibrated-

high speed vibrators were all observed to prevent honevcomb

voids.

-- Testing at Placement Location: qualified test personnel using

calibrated test equipment wereiobserved to meet frequency

requirements and ASTM standards for sampling and testing concrete

for temperature, air, slump, . unit weight and casting of cylinders

on concrete discharged from pump lines.

-- Adequate finishing, curing and green cutting were observed

No items of noncompliance were identified.

5.

Review of UE&C Surveillance Reports on PTL Laboratory Activities

The inspector performed a documentary record review of UE&C Surveillance of

PTL test laboratory activities during the-current year. UE&C's Level 2

program for surveillance of each subcontractor's approved level 1 program

covering the containment structure and other safety-related civil / structural

activities, includes coverage of concrete manufacture and placement, soil

compaction, reinforcing steel installation, structural steel erection: and

the testing laboratory. Quality control procedure 10-1, revision 4,

dated January 30,1981 establishes requirements for-UE&C level 2 surveillance.

The inspector observed that sixteen surveillance reports were generated

-

in 1981 up to October 16,1981. Each report covers different generic types

of QA activities. These following PTL activities were surveilled by

UE&C in 1981:

1. Qualifications for inspection, examination and testing personnel

2. Control and reporting of nonconformances

3. General housekeeping

4. Tool, gauge and instrument control-

5. Procurement document control and receiving inspection

In addition to the inspector's verification of UE&C surveillance activities,

he spot-checked some PTL Laboratory and field activities to include cali-

bration of test equipment, service water pipe backfill compaction and nuclear

gauge testing of backfill.

No items of. noncompliance were identified.

6.

Review of Requirements and Records-Relating to Interface Between Containment

Liner Plate and Exterior Concrete Wall Construction Tolerances

The requirements for the containment liner plate fabrication and erection

in UE&C specification 15-1 were reviewed by the NRC inspector. The requirements

of ASME code,Section III, Division 2, CC-4500 are involved. He verified

that the specification states the method of measurement and documentation

of data for the as-erected liner, which includes the containment vessel

,

cylinder, spherical dome roof, penetrations and attachments and that

established bench marks and a centerline are utilized. The liner plate

contractor (PDM) implemented these programmatic requirements and the post-

weld erection tolerances are contained in-field survey procedure FSP-01.

-

- -

- -

~

.-

.

8

The UE&C specification 15-1 requires that PDM's survey infomation shall

be submitted to the Construction Manager for approval prior to placing

containment shell concrete. Utilizing the liner plate as the pemanent

inside fom for the containment exterior conc'ete wall, PPC is required

by UE&C specification 13-2 to make allowancer for his exterior form work

design for the containment shell concrete tc accommodate tolerances con-

forming to' ACI 301, ACI 347 and ASME Code, S ection III, Division 2.

PPC

incorporated all specification requirements into their Field Civil Construction

Procedure FCCP-121, Monitoring of the Containment Shell Wall Liner During

Concrete Placements. The inspector's record review found that revision #1

(August 3,1981) to this procedure eliminated checking by PPC of liner

plumbness and diameter. Approval of this revision by UE&C is based on

UE&C's acceptance of the liner for both diameter and plumbness.

In accor-

dance with the liner specification, PPC is required now only to perfom a

check on the penetrations pre-and post- pour and to monitor the liner during

concrete placements according to prescribed details. The final survey data

reviewed by PPC's QA is then fowarded to the UE&C Resident Construction

Engineer and the Authorized Nuclear Inspector prior to the next placement.

Approval by UE&C of PDM's as-erected liner data and approval also by UE&C

of PPC liner monitoring during placement of the exterior wall concrete

appears to assure adequate control and confomance to code requirements.

No items of noncompliance were identified.

7.

Programmatic QA Inspection of Piping

The inspector conducted a Quality Assurance review of Pullman-Higgins to

ascertain that site work is being performed in accordance with regulatory

requirements and procedural comitments. The following areas were inspected:

procurement, storage, receipt inspection, welding process checklists, qua-

lification of personnel, audits, nonconformances, corrective action, and

drawing adherence. The Seabrook Station PSAR, QA Section 17.2, and the

Pullman Power Products QA Manual (5/8/81) were reviewed for procedural control

and specification of QA criteria relevant to the piping program.

During a review of field purchase orders the inspector noted that statements

referencing 10CFR21, concerning reporting of defects and noncompliances,

were omitted from welding material purchase crders. The following UE&C

purchase orders were lacking the regulatory statement required by 10CFR21.31:

-- Arcos - P.O.#9763-011-16514, dated 7/16/81

-- Sandvik - P.O.#9763-011-17727, dated 5/1/80

-- Chemetron - P.O.#9763-011-18643, dated 8/7/80

-- Arcos - P.O.#9763-011-16520, dated 7/15/81

Material is procured by UE&C, but requisitioned by Pullman. All of the above

orders procured welding material to the ASME B & PV Code, Section NB,

which is material unique to the nuclear industry. The inspectors discussed

this apparent discrepancy with licensee and A/E personnel and were told that

a statement of Part 21 applicability would be added to the fomat of all

nuclear field purchase orders (P.O.).

This comitment was later verified for

implementation by an inspector review of a UE&C Speed' Letter to the Purchasing-

Supervisor and examination of a recently issued field P.O.

__

.

.

9

The inspector reviewed the audit program of Pullman-Higgins, noting that the

entire program, including all eighteen criteria of IbCFR50, Appendix B,

is routinely scheduled for audit oy theiPullman corporate office during four

-day periods, twice a year. The inspector questioned the scope of this audit

program with regard to Criteria XVIII of 10CFR50, Appendix B, which requires

a " comprehensive" system of planned and periodic audits.

Eight days of

formalized auditing can only marginally provide reasonable assurance that

activities are in compliance with all aspects of the Quality Assurance Program.

However, the Pullman site QA organization is presently institutingia site

audit / surveillance program under the direction of the Field 0A Manager.

In addition, YAEC QA is in the process of expanding their. addit coverage.

With licensee commitment to this broader audit coverage of the piping QA

program, the inspector indicated no further question of this audit issue,

but stated that the program would be routinely evaluated for the timeliness

and effectiveness of the new program direction.

8.

Instrument Line Supports (Unit 1)

The only safety-related instrumentation installation to date was accomplished

with the attachment of the Combustible Gas Control-(CGC) tubing lines to pipe

supports on the Unit 1 containment liner dome prior to the lifting and erection

of the liner dome into position onto the standing portion of the containment

liner. The inspector spot-checked the installation prior to the lift,

reviewed QC inspection and engineering documents, ard discussed the work

with licensee and contractor personnel. The Johnson Controls, Inc. (JCI)

support installation packages for supports (SG-2802-1 thru 2802-18) and

(SG-2806-1 thru 2806-18) were examined for the following control and

inspection documents:

.

-- I/F (Installation / Fabrication) Planners

-- Weld Data Reports and Weld Material Requisitions

-- Weld Visual' Inspection Reports

-- Hanger / Support Installation Inspection Reports

The use of applicable inspection attributes, the sign-off of hold points,

and the traceability of weld rod were all verified. Both the installation

and records were evaluated with regard to criteria specified in the following

documents:

-- ASME B & PV Code,Section III, Subsection NF

(W77 Addenda) and Appendix XVII

-- UE&C Specifications 46-1B (Revision 4) and 248-8 (Revision 4)

-- JCI QA Procedures QAS-1101-SS (Revision 1) and QAS-1001-SS

-- JCI QA Manual w/ addenda

-- ITT Grinnell standard component catalog (PH81)

!

-- UE&C drawings F805169 (Revision 2) and M805169S

-- UE&C ECAs 08/1197A and 25/0608A

The inspector noted that UE&C sketch SK-5/14/81-AF nrovided details for the

installed supports per the above referenced ECAs. This sketch illustrated

that each support would use a standard ITT Grinnell pipe clamp with two

each SA-325, " diameter bolts. However, while JCI material requisitions

indi.cated that the proper bolts had been ordered thru UE&C, an error in

coor'dination between UE&C and ITT Grinnell resulted in standard, non high-

-

-

10

strength bolts being supplied with the clamps. These incorrect bolts passed

the UE&C site receiving inspection and were installed, inspected and accepted

by JCI. Subsequent to the inspector's inquiry into the adequacy of the

installed bolts, a nonconfomance report was issued to document this supply,

erection, and' inspection error.

Since both the UE&C and JCI program had failed to preclude the subject

installation of over 30 CGC tubing supports with improper bolts, the inspector

informed the licensee Field QA Manager and Site Manager during an exit

interview on November 13,1981 that this failure represented a noncompliance

with regard to 10CFR50, Appendix B, Criterion V (443/81-12-01). The

inspector later learned that planned corrective actions will include replace-

ment of the subject bolts.

9.

Structural Connections and Design Interfaces (Unit 1)

a.

The inspector examined the combination welded / bolted connections utilized

to support the containment recirculation pump screen steel off a concrete

building structure wall. Material dimensions, weld sizes, and piece

fit-up tolerances were all checked, as was the engineering control over

design changes to the members' method of attachment. While these

particular connections could not be classified as Framed Beam Connections

under the general design criteria of Table III of the AISC Manual,

'

documentary evidence existed that their design as special connections

had been originally approved (Cives drawing sheet E1001, Revision 1,

Section 10-10) and modified (UE&C ECAs 01/2705 A and B) to provide

structurally adequate supports.

The inspector also checked the interfacing concrete embed for type,

size, and thickness against the-drawing requirements and discussed the

handling of any potentially adverse field conditions with QA personnel.

No items of noncompliance were identified.

,

b.

The inspector reviewed several UE&C Specifications (eg: 12-2, 45-9,

46-1, and 48-2) covering various- disciplines, such. as instrumentation and

HVAC, whose support design must interface with the-structural building

steel throughout the plant. Specific issues such. as the allowance of

transverse welding across the tension flange of structural beams are

addressed differently in the various specifications. Addit'onally, the

inspector identified several cases of approved design or design changes

for attachment to building steel without any apparent structural discipline

review of the impact on beam load allowances or flange stresses. Some

examples follow:

-- HVAC: Supports FN5822 and FN6A105 have a total of five transverse

weld' connections to the same structural beam with UE&C

approval of this design without any apparent structural

discipline review.

-- Piping: The disposition of Pullman nonconformance reports (NCR)

571 and 930 allows additional transverse welding beyond

project requirements (reference: UE&C'memoMM5195A)

without a structural review.

/-

.

.

11

-- Electrical: UE&C ECA 25/0714A allows the relocation of two

vertical support members off the neutral axis of

the building steel without specific structural

discipline sign-off.

-- Instrumentation: UE&C Specification 46-1 (Revision 4) provides

authority for the contractor to install transverse

welds up to one-half the flange width without

further UE&C approval and apparently without

consideration of the existing flange fiber stresses

relative to the allowable tensile stress.

Also an examination of ECAs 25/0714A and 25/0746A revealed that design

changes were made to safety-related pipe supports with the resulting

attachment welds to the structural members being undersized relative to

the code requirements of the AISC Manual of Steel Construction for

" Minimum Size of Fillet Welds".

While discussion of this general issue of control over the design

interfaces to building steel has heretofore resulted in the A/E position

that loadings and conditions on the structural members will be verified

in their as-built state at some future time, the above mentioned cases

of apparent specification differences, undersized welds, and transverse

weld loadings have caused the licensee to specifically request frcm

the A/E justification and an explanation of how the structural review

process is or will be accomplished. Pending the presentation of the

licensee position on this issue and a review for the adequacy of controls

on this process by the NRC, this item is unresolved (443/81-12-02).

10.

Safety-Related Components (Unit 1)

a.

Boron Injection Tank (BIT)

The inspector examined the present state of installation of the Boron

Injection Tank (1-SI-TK-6) in place on its anchor bolts and pad in the

Primary Auxiliary Building (PAB). Material, configuration, sizes, and

welds were all spot-checked for the tank and its supports including the

concrete anchor bolts.

Preventive maintenance records were examined and

the existence of the required nitrogen inerting atmosphere was verified.

The QA records package for the fabrication of the tank by Southwest

Fabricating and Welding was reviewed and the BIT was compared to its

as-built drawing details.

The above items were evaluated with regard to the design requirements

specified in the following documents:

-- Westinghouse Equipment Specification, 679065 (Revision 3)

with Interim Change No. 1

-- Westinghouse NSD NSSS Component Receiving and Storage Criteria

-- Westinghouse Drawing 1219E77 (Sheets 1 & 2)

-- UE&C Drawings F805062 (Revision 9); F101526 (Revision 7); and

F101697 (Revision 10)

-

-

- -

.

.

.

12

No items of noncompliance were identified.

b.

CS Charging Pumps (Chemical and Volume Control System)

The inspector examined the in-place, grouted condition of the CS charging

pumps with particular note of the field modification of the base plate

anchorage to the concrete anchor bolts for one of the pumps.

Control

and inspection of the modification process as provided by the disposition

to Pullman NCR 216, the appropriate Pullman Field Process Sheets, and

-

Westinghouse Field Deficiency Report.(FDR) NAH-M-10008, as well as

1

participation in the redesign details by the pump manufacturer (Pacific

Pumps), were verified.

The rework-was inspected to the requirements of ASME Appendix XVII,

Westinghouse E Spec. 952470 (Revision 2) with Interim Change No. 1,

Westinghouse drawing 300-E49746 (Revision 4), and UE&C Procedure PTG-1

(Revision 1). Anchor bolt material, size and spacing were evaluated with

regard to the design requirements of UE&C drawing F101526 (Revision 7)

and the Westinghouse E Spec.

No items of noncompliance were identified.

11. Safety-Related Piping (Unit 1)

1

a.

Welding

The inspector observed joint preparation, in-process welding on completed

welds, on the following pipe spools being installed in the field:

-- 1-RH-180-01, Field Welds F0101 and F0103

-- 1-CC-752-02, Flow Element joint prep repair

-- 1-RH-155-03, Shop Weld (pipe to elbow)

-- 1-RH-158-07, Field Weld F0701

Pullman Field Process Sheets, Weld Rod Store Requisitions, and Welding

Procedure Specifications, or Dravo fabrication sketches, as applicable,

were checked to verify identification, documentation, and inspection of

criteria procedurally required for quality welding. -QC inspection

,

^

verification of hold point items on the weld process sheets was noted.

The inspector also spot-checked offset and reinforcement conditions to

the requirements of ASME Section III and reviewed the record packages

for the RH--180-01 welds, to include verification of the proper NDE on

the original and any repair welds'and use of the proper.penetrameter in

the radiographic examination process.

For field weld F0701~on line

RH-158, the weld filler metal certification records were.also inspected.

No items of noncompliance Were identified.

b.

Pipe Run

The inspector walked the Residual Heat' Removal 6" pipe line in containment

from the class 1, gear assisted manual operated gate valve (1-RH-V-59)

to the 8" class 2 pipe on the outer side of the spec. break, swing check

,

valve (1-RH-V-15). Pipe run components, bends, welds and branch connections-

.-

-

-

-

-

-

- -

-

-

- -

- -

-

-

-

7

_

--

-

-

13

were all examined for conformance to the details specified in'the following

drawings:

-- UE&C drawings F800155 (Revision 11) and F805000

-- Dravo sketches E2936-164,~165, and'166

The Westinghouse record packages for RH valves V-15 and V-59 were also

spot-checked for documented. valve material and process traceability.

No items of noncompliance were identified,

c.

Pipe Supports

The inspector checked the in-place condition, either final _ accepted or

still in process, of the following pipe supports and compared them with

their Pullman detail drawings:

-- 155-RG-28

-- 833-RG-10

Pullman Hanger. Field Weld Process Sheets were examined for documentation.

of the correct weld joint status, to include hold point inspections.

The inspector checked hanger material and weld dimensions,. identification,

and configuration. Concrete embed plates, interfacing with hanger items,

were spot-checked for proper size, thickness, and location.

On hanger 833-RG-10, the welding for which had been inspected and accepted

by QC personnel, the inspector found that an uncommon, double-arrowed

weld symbol had been misinterpreted resulting in two completed field

welds each lacking 2" of required fillet weld. 1 Pullman NCR 1591

was immediately written and the following corrective action initiated.

(1) A review of hanger drawings for weld symbols similar to the

one that caused the error is in progress.

(2) A review of the particular inspector's work is planned.

(3) The weld symbol in question will be incorporated and demonstrated

in future training sessions.

(4) The craft personnes involved will be provided additional

indoctrination and training.

Based upon the preliminary results of the ongoing reviews, it appears

that this weld length error is an isolated case. The inspector has no

.

further questions on the continuing licensee corrective action or other.

!

l

aspects of this issue.

I

No items of noncompliance were identified.

d.

Pipe Material

,

The inspector randomly selected a number of vendor supplied pipe spools,

some of which are already installed, for a check of component and material

L

_

.

.

14

type and identification. Comparison of the Dravo sketch documentation of

the ASTM processes used for fabricating the material with the governing

requirements of the applicable " Piping Schedule and Material Data Sheets"

of UE&C Specification 248-1 (Revision 4) revealed several cases of

conflicting data. While some of these were easily recognizable as

transcript errors, at least two cases required the issuance of an ECA

(08/1381A) to document the material acceptability of portions of the

supplied pipe spools. Other identified discrepancies are currently being

researched; however, it appears that substitutions of ASTM specified

standard material were generally made for several spool pieces as compared

to the 248-1 data requirements.

The inspector requested that the licensee produce evidence that these

substitutions were approved in advance and that proper controls exist

for material type changes, particularly where, for example, the sub-

stitution of welded for seamless pipe may alter future in-service examination

requirements. The licensee is currently investigating whether the apparent

discrepancies may have been caused by specification revisions or the

issuance of broad authorizations of certain. material type substitutions

prior to spool fabrication.

In either case, documented evidence of the

approval of such substitution, beyond the Dravo Sketch data, must exist

in some fonn to not only complete the quality records, but also assure

that proper material, compatible with all specification requirements,

has been supplied.

Pending clarification of the material discrepancies on a programmatic

basis by the licensee in conjunction with the A/E and supplier, this

item is unresolved (443/81-12-03).

12. Cross-Over Pipe Support Welding (Unit 1)

The inspectors observed welding on the Cross-over supports at several different

times during the inspection period.

Particular attention was given to the

contractor controls implemented to preclude the potential lamellar tearing

problems discussed in previous NRC inspection reports (443/81-07 and 81-08).

Pre-weld buttering, MT inspection, preheat controls, and the engineered

sequencing of the support welds were all verified, as was the presence of

a UE8C home office welding engineer during the commencement period of these

welding activities.

An inspector visually examined several butter welds and specifically inspected

final welding on joints 9207, 9208, 9209, and 9216, to include a repair weld

on 9207 as documented in the disposition to Pullman NCR 1454 and the applicable

Field Process Sheet. QC inspection, the control over sequence criteria and

hold points, and the traceability and certification of E7018 electrode

(Heat No. ZZZ028)were all spot-checked.

,

The inspectors discussed continued contractor awareness of the lamellar

tearing potential with QA personnel and evaluated all inspection items with

regard to the governing requirements of AWS Standard D1.1, UE&C Specification

WS-3, Pullman Field Instruction FI-92, and WPS AWS-I-2.

No items of noncompliance were identified.

r

e

s

15

13. Fire Protect'on

The inspector reviewed documented audit findings-and discussed QA program

requirements with licensee and contractor personnel regarding the arrival

on site of shipments of material for the plant fire protection system. While

this material is not itself safety-related, the reduced ten-point QA requirements .

of USNRC Branch Technical Position ApCSB 9.5-1 as' discussed in the Seabrook

Station " Evaluation and Comparison" to Appendix A of that document have been

applied as stated in the Seabrook Station FSAR. The inspector verified

continued licensee _and construction manager supervision and direction

over the contractor to assure the supply and erection of a quality system.

No items of noncompliance were identified.

14. Unresolved Items

Unresolved items are matters about which more information is required in

order to ascertain whether they are acceptable items, items of noncompliance,

or deviations. Unresolved items disclosed during the inspection are discussed

in Paragraphs 9b and lid.

15. Management Meetings

At periodic intervals during the course of this inspection, meetings were

'

held with senior plant management to discuss the scope and findings of this

inspection.

,

.

.m

. -

.

.

.

- . .

.

.

.

. -

..ma

--