r, Th2 mas J. Martin Public Service Electric and Gas Company 80 Park Plaza Newark, N.J. 07101 201/4304316 Vice President Engineering and Construction December 2, 1981
,qn
.,s
[fQ)g
$6)
Mr. Ronald C.
Haynes, Director
[
U.S. Nuclear Regulatory Commission
(;99z DEC1019815-;T2 Office of Inspection and Enforcement Reglon 1
'd u C),
.s, nnsu sauten A**" P" 631 Park Avenue King of Prussia, Pennsylvania 19406 x()x
^f
\\$ /
_{
s, dy l
Dear Mr. Haynes:
s SIGNIFICANT CONSTRUCTION DEFICIENCY DAMAGED BELLOWS ASSEMBLY NO. 2 UNIT, 50-355 HOPE CREEK GENERATING STATION On November 4, 1981, a telephone report was made to Region I representative, Mr.
E. Greenman, advising him of damage to a bellows in the Unit #2 primary containment.
The following interim report is submitted in accordance with 10CFR50.55e.
Description of the Deficiency The Hope Creek containment is a " Mark I" drywell and torus with eight (8) vent lines connecting the drywell to the torus.
Each vent line contains two expansion bellows as-semblies.
During testing of the bellows by the installation contractor, Pittsburgh-Des Moines Steel Company (PDM), a hole was detected through both plies of the outer bellows in ventline 8A.
Safety Implications The perforation of both plies of a ventline bellows, if left uncorrected, would result in a breach of containment during accident conditions.
Corrective Action Our Architect Engineer, Bechtel Power Corporation, has in-structed PDM to perform the following:
1.
Inspect all other Unit #2 ventline bellows assemblies for similar damage.
r I
8112140054 811202 I h)\\0 PDR ADOCK 05000355 S
\\
=
s 1
Mr. Ronald C. Haynes 12/2/81 Corrective Action (Cont.)
2.
Repair or replace the damaged bellows.
3.
Determine the cause of the perforation and actions nec-essary to prevent recurrence.
We anticipate completion of the inspection and investigation (Items 1 and 3 above) in early January, 1982.
We will re-port the results to you at that time.
Very truly yours,
/ '&
/