ML20037D356
| ML20037D356 | |
| Person / Time | |
|---|---|
| Site: | Peach Bottom |
| Issue date: | 06/22/1981 |
| From: | Snyder G NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I) |
| To: | |
| Shared Package | |
| ML20037D354 | List: |
| References | |
| 50-277-81-02, 50-277-81-2, 50-278-81-02, 50-278-81-2, NUDOCS 8107100109 | |
| Download: ML20037D356 (2) | |
Text
_ _.
I a
1 APPENDIX A NOTICE OF VIOLATION Philadelphia Electric Company Peach Bottom Atomic Power Station License Nos. DPR-44 Docket Nos. 50-277 DPR-56 50-278 l
Based on the results of an NRC inspection conducted on January 12-14 and 19-20, 1980 and in accordance with the Interim Enforcement policy, 45 FR 66754 (October 7, 1980), the following violations were identified:
A.
Section 3.2.1 of the PBAPS Environmental Technical Specifications specifies, in part, that the chlorine analyzer shall be calibrated monthly.
1.
Contrary to the above, during the October 1980 calibration of the analyzer, the chlorine analyzer was found out of calibration according to the acceptance criteria of Procedure ST 7.3.2.b and no action was taken for subsequent adjustment of the analyzer, such that that analyzer was not effectively calibrated for that month.
2.
Contrary to the above, from July through October,1979 and June and September, 1980, the grab samples used to calierate the analyzer had "less than 0.1" or 0 mg/l of chlorine, levels too low to elicit a quantifiable response from the analyzer.
This, tnerefore, did not constitute calibration of the system.
This is a Severity Level VI Violation (Supplement I).
~
B.'
Section 3.2.1 of the PBAPS Environmental Technical 3pecifications specifies i
that in the event that the continuous chlorine analyzer is inoperable, manual measurements of the free residual chlorine level in the condenser discharge water shall be made at the start, midpoint, and end of chlori-nation.
4
- Contrary to this requirement, during the intervals June 1 through 3 and 23 through 30, and July 1 through 8,1979, grab samples were collected only at the end of the chlorination period and not at the start or mid-i-
l point.
This is a Severity Level VI Violation (Supplement I).
Pursuant to the provisions of 10 CFR 2.201, Philadelphia Electric Company is hereby required to submit to this office within twenty-five days of the date of this Notice, a written statement or explanation in reply, including:
(1) the corrective steps which have been taken and the results achieved; (2) corrective steps which will be taken to avoid further violations; and (3) the
' 8107100109 810622 PDR ADOCK 05000277 j
g PDR i
Appendix A 2
date when full compliance will be achieved. Under the authority of Section 182 of the Atomic Energy Act of 1954, as amended, this respoase shall be submitted under oath of affirmation.
~
[ Gary L yder,/ Chief _.ergency Dated Prepar ness and Pro m Support Branch Division of.,ergency Preparedness and Operational Support 4