Forwards IE Insp Repts 50-277/81-02 & 50-278/81-02 on 810112-14 & 19-20 & Notice of Violation
ML20037D353
Person / Time
Site: Peach Bottom  
Issue date: 06/22/1981
From: Snyder G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Daltroff S
PECO ENERGY CO., (FORMERLY PHILADELPHIA ELECTRIC
Shared Package
ML20037D354 List:
References
NUDOCS 8107100104
Download: ML20037D353 (2)


See also: IR 05000277/1981002

Text

e

O

.

,

8

%

L[NITED STATES

[

NUCLEAR REGULATORY COMMISSION

,

3

s

REGION I

631 PARK r*3NUE

KING OF PRUSSIA, PENNSYLVANIA 19406

4 * * * * * ,o

Docket Nos. 50-277

50-;78

2 2 JUN 1981

Philadelphia Electric Ccmpany

h

"

g

b

ATTN: Mr. S. L. Daltroff

bid I[f,) b

Ib

N

Vice President

I

Electric Production

f

2301 Market Street

g 0 9 sat u

Philadelphia, Pennsylvania 19101

yC *** W,@^*

Gentlemen:

\\ -\\

4. ,

Subject: Combined Inspection 50-277/81-0$ipd50,-27'8/81-02

j

This refers to the routine safety inspection conducted by Mr. T. Jackson of this

l

office on January 12-14/and 19-20,1981 at Peach Bottom Atomic Power Station and

Philadelphia Electric Company Corporate Office of activities authorized by NRC

License Nos. OPR-44 and DPR-56 and to the discussions of our findings held by

Mr. Jackson with Messrs. W. T. Ullrich and R. H. Logue of your staff at the

conclusion of the inspection, and to subsequent telephone discussions between

Mr. Jackson and Mr. W. B. Willsey anc H. Watson of your staff.

Areas examined during this inspection are described in the Office of Inspection

and Enforcement Inspection Report which is enclosed with this letter.

Within

these areas, the inspection consisted of selective examinations of procedures

)

and representative records, interviews with personnel, and observations by the

f

inspector.

Based on the results of this inspectior., it appears that certain of your activi-

ties were not conducted in full compliance with NRC requirements, as set forth

in the Notice of Violation, enclosed herewith as Appendix A.

These items of

noncompliance have been categorized into the levels described in the Federal

Register Notice (45 FR 66754) dated October 7, 1980.

In accordance with 10 CFR 2.790 of the Commission's regulations, a copy of

this letter and the enclosed inspection report will placed in the NRC's Public

Document Room.

If this report contains any 'rformation that you (or your

contractors) believe to be exempt from discloare under 10 CFR 9.5(a)(4), it

is necessary that you (a) notify this office tj telephone within ten (10) days

from the date of this letter of your intention to file a request for wit 1 holding;

snd (b) submit within 25 days from the date of this letter a written ap.olication

ta this office to withhold such information.

Consistent with section 2.790(b)(1),

any such application must be accompanied by an affidavit executed by the owner

%QL

Sf

in

8107100104 810622

PDR ADOCK 05000277

0

PDR

_ _ _ _ - _ _ _ _ _ _ _ - _ _ _ _

-

_

_ _ _ _ _ _ _ _

%

.

Philadelphia Electric Company

2

2 2 JUN 1981

of the information which identifies the document or part sought to be withheld,

and which contains a f ;l statement of the reasons on the basis which it is

claimed that the information should be withheld from public disclosure.

This

section further requires the stateoent to address with specificity the consider-

ations listed in 10 CFR 2.790(b)(4).

The information sought to be withheld

shall be incorporated as far as possible into a separate part of the affidavit.

If we do not hear from you in this regard within the speci#ied periods noted

above, the report will be placed in '.he Public Document Room.

The telephone

notification of your intent to request witaholding, t any request for an

extension of the 10 day period which you celieve necessary, should be made to

the Supercisor, Files, Mail and Records, USNRC Region I, at (215) 337-5223.

Should you have any questions concern'ng this inspection, we will be pleased to

discuss them with you.

Sinc rely,

N

Gary

Snyde , Chi

, Emergency

Prep edness and Pr gram Support

Bran h, Division of Emergency

Preparedness and Operational Support

Enclosures:

1.

Appendix A, Notice of Violation

!

2.

Combined Office of Inspection and Enforcement Inspection

Report Number 50-277/81-02; 50-278/81-02

cc w/encis:

W. T. Ullrich, Station Superintendent

Troy B. Conner, Jr. , Esquire (Without Report)

Eugene J. Bradley, Esquire (Without Report)

Raymond L. Hovis, Esquire (Without Report)

Michael J. Scibinico, II, Assistant Attorney General (Without Report)

. . . . . . . . . . .

.

-

.

..

__