Amends 103 & 92 to Licenses NPF-10 to NPF-15,respectively, Removing Parts of License Condition Already Complied W/& Replacing Four PASS Requirements W/New Requirements to Provide Needed Info by Different Methods
ML20035D293
Person / Time
Site: San Onofre  Southern California Edison icon.png
Issue date: 04/06/1993
From: Quay T
Office of Nuclear Reactor Regulation
To:
Shared Package
ML20035D295 List:
References
NUDOCS 9304130045
Download: ML20035D293 (4)


Text

_

f t

UNITED STATES

[

. j NUCLEAR REGULATORY COMMISSION

, f WASHINGTON. D.C. 20566 0001

/

....+

SOUTHERN CAllFORNIA EDISON COMPANY SAN DIEGO GAS AND ELECTRIC COMPANY THE CITY OF RIVERSIDE. CALIFORNIA THE CITY OF ANAHEIM. CALIFORNIA DOCKET NO 50-361

~

SAN ONOFRE NUCLEAR GENERATING STATION. UNIT NO. 2 AMENDMENT TO FACIllTY OPERATING LICENSE Amendment No.103 License No. NPF-10 1.

The Nuclear Regulatory Commission (the Commission) has found that:

A.

The application for amendment by Southern California Edison Company, et al. (SCE or the licensee) dated October 2, 1992, complies with the standards and requirements of the Atomic Energy l

Act of 1954, as amended (the Act), and the Commission's regulations set forth in 10 CFR Chapter I; B.

The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C.

There is reasonable assurance (1) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; l

D.

The i uance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E.

The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.

9304130045 930406 PDR ADOCK 03000361 p

PDR l'

f i

2.

Accordingly, paragraphs 2.C.(2) and 2.C.(19)i of Facility Operating i

License No. NPF-10 is hereby amended to read as follows:

2.C.(2)

Technical Specifications The Technical Specifications contained in Appendix A and the Environmental Protection Plan contained in Appendix B, as revised through Amendment No.103, are hereby incorporated in the license. Southern California Edison Company shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan.

2.C.(19)i Post-Accident Samolino System (NUREG-0737 Item II.B.3)

The PASS shall be operable and the post-accident sampling program shall be implemented as described in the SCE letter of April 14, 1983, and revised by SCE letter of October 2, 1992.

3.

This license amendment is effective as of the date of its issuance and must be fully implemented no later than 30 days from the date of issuance.

FOR THE NUCLEAR REGULATORY COMMISSION 0P Theodore R. Quay, Director Project Directorate V Division of Reactor Projects III/IV/V Office of Nuclear Reactor Regulation Date of Issuance:

April 6, 1993 i

mua

}+.

UNITED STATES

[..'*. )

NUCLEAR REGULATORY COMMISSION "a (

f WASHINGTON. D.C. 20SSFc0001

%.... /

SOUTHERN CALIFORNIA EDISON COMPANY SAN DIEGO GAS AND ELECTRIC COMPANY THE CITY OF RIVERSIDE. CALIFORNIA THE CITY OF ANAHEIM. CALIFORNIA DOCKET NO. 50-362 SAN ON0FRE NUCLEAR GENERATING STATION. UNIT NO. 1 AMENDMENT TO FACILITY OPERATING LICENSE Amendment No. 92 License No. NPF-15 1.

The Nuclear Regulatory Commission (the Commission) has found that:

A.

The application for amendment by Southern California Edison Company, et al. (SCE or the licensee) dated October 2, 1992, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commission's regulations set forth in 10 CFR Chapter I; B.

The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C.

There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; D.

The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E.

The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.

i

. 2.

Accordingly, paragraphs 2.C.(2) and 2.C.(17)d of Facility Operating License No. NPF-15 is hereby amended to read as follows:

2.C.(2)

Technical Specifications The Technical Specifications contained in Appendix A and the Environmental Protection Plan contained in Appendix B, as revised through Amendment No. 92, are hereby incorporated in the license. Southern California Edison Company shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan.

2.C.(17)d Post-Accident Samplina System (NUREG-0737 Item II.B.3)

The PASS shall be operable and the post-accident sampling program shall be implemented as described in the SCE letter of april 14, 1983, and revised by SCE letter of October 2, 1992.

3.

This license amendment is effective as of the date of its issuance and must be fully implemented no later than 30 days.* rom the date of issuance.

FOR THE NUCLEAR REGULATORY COMMISSION Y$<

Theodore R. Quay, Director Project Directorate V Division of Reactor Projects III/IV/V Office of Nuclear Reactor Regulatio; Date of Issuance: April 6, 1993