ML20034C228

From kanterella
Jump to navigation Jump to search
Safety Insp Rept 50-155/90-07 on 900102-0416.No Violations Noted.Major Areas Inspected:Licensee Response to Unresolved Issues Re Containment Integrated Leak Rate Test Results,Per Insp Rept 50-155/89-15
ML20034C228
Person / Time
Site: Big Rock Point File:Consumers Energy icon.png
Issue date: 04/23/1990
From: Lougheed V, Maura F, Phillips M
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML20034C226 List:
References
50-155-90-07, 50-155-90-7, NUDOCS 9005020192
Download: ML20034C228 (4)


See also: IR 05000155/1990007

Text

,.~-

-

.

.

Y..

-

U.S. NUCLEAR REGULATORY COMMISSION

Rt.GION ll'1

Report No. 50-155/90007

Docket No. 50-155

License No. DPR-6

Licensee: Consumers Power Company

1945 West Parnali Road

Jackson, MI 49201

Facility Name:

Big Rock Point Plant

Inspection Conducted: January 2, 1990 through~ April 16, 1990

Inspectors:

I

V. P

Date

fl.Loughe6d-w&

We

F. A. Maura 7

Date

Approved By:

2 3dp

"

M. P. Phillips

& te

Inspection Summary

Inspection on January 2, 1990 through April 17,1990(ReportNo. 50,55/90007(DRS))

Areas Ins

TTeensee'pected:

Special . inspection by regional based inspectors of the

s response to the unresolved issues relating to the containment

integrated leak rate test (CILRT) results, as described in inspection

report 50-155/89015. The NRC modules used during this inspection was 92701.

Results: The licensee provided additional information'in their letter of

~

November 1, 1989, which quantified the mass increase during the Type A

u-

test as being due to diurnal effects. The inspectors applied the-same

quantification to the verification test. When this quantification was first

applied, it appeared that the verification test was outside the acceptance

criteria band. This was discussed with the licensee during a' meeting on

-

March 13, 1990. Following submittal of further information by the licensee,

the calculations were rerun, and it was determined that the acceptance

criteria were met. The CILRT was declared a valid test.

However, the values

used for the diurnal effect were calculated using the assumption that changes

to the sphere were uniform.

In order to provide better quantification of the

actual behavior of the steel sphere, the licensee committed to more accurately

measure the changes in containment volume due to atmospheric conditions.

9003020192 900424

PDR

ADOCK 0500

5

0

..

_ _ _ _ . . _ . . . . . . _ . .

. . . . . . . .

-

.:

.

~

.

  • e

=.

DETAILS

1.

Persons Contacted

Consumers Power

R. Alexander, Licensing Engineer

W. Beckman, Plant Manager

T. Marshall, Technical Engineer

D. Mogenburg, Technical Supervisor

J. Toskey, Sr. Technical Engineer

G. Winthrow, Technical Superintendant

U. S. NRC

E. Plettner, Senior Resident inspector

The above attended the exit interviel held, via telephone, on April 16,

1990.

2.

Licensee Action on Previous Inspection Findings

a.

(Closed)-Unresolved Item (155/89015-01(DRS)) : The licensee was

requested to justify why they had not obtained an exemption from the

requirement of 10 CFR Part 50, Appendix J, regarding the performance

.

i

of reduced pressure Type A tests at Big Rock without establishing a

correlation between the full and reduced pressures. The licensee

stated that the requirement to perform correlating tests was=

.

discussed only as a preoperational requirement, and since the site

.

!

!

had been operational when Appendix J was issued no exemption'was

required. The inspectors. reviewed the Systematic Evaluation. Program

'

for the site in relation to compliance with-Appendix J, and.found

that the subject of correlating tests had not been addressed. The

licensee has a May 2000 expiration date for their operating license.

Therefore, the licensee will only have'two.or three more CILRTs to

1

perform at most.

Performance of correlation. tests Ft this' time in

i

plant life would not be worthwhile. Therefore, this item is.

j

considered closed.

!

b.

(Closed) Unresolved item (155/89015-02(DRS)): The licensee was

requested to provide better quantification of the diurnal effects on

=j

the sphere, and justification of the increase in mass for the first.

'

seven hours of the Type A test. The licensee.provided sufficient

i

information to show that diurnal effects was the most likely cause

of the increase in mass. The inspectors additionally applied the

i

!

!

2

1

_.

. . . .-

< 13

.-

+

g4

w

same correction factors to,the verification test,-in order--to ensure-

that the same criteria were used.:to judge both tests._.The initial-

calculations'for the verification test showed'that the test was

-outside the acceptance; criteria.

This was discussed with_the

licensee in a meeting on March 13, 1990. 'The licensee provided

additional-information as to why the test shouldlnot be declared

invalid. Upon fu'rther examination.of.this'information by.the

inspectors, it was found that application _of diurnal effects to the-

verification' test results did not cause;the test to fail. The

inspectors concluded that the July 1989 CILRT,-including verification

test, met the requirements of'10 CFR Part 50, Appendix-J,-and was-

acceptable. However,'the licensee was-requested to continue' efforts

to provide more accurate quantification of.thel diurna 1' effects:on--

the sphere volume, in. order to' ensure that future tests could-

account for such changesLrather than a qualitative explanation of-

" diurnal effects." This was discussed with.'the' licensee during the

exit, and the licensee concurred with the conclusions.1

c.

(Closed)'OpenItem(155/89015-03(DRS)): This-open-item requested

the. licensee calculate the effects of-changestin water level inside

R

containment. and the changes of pressure in'the' control: rod drive

-

and nitrogen accumulators during:the CILRT. ~The: licensee presented;

these calculations in; their~ November 1,1989, , response. 'The' inspectors

have reviewed the calculations and:found them to:be correct. The

effect on the CILRT results wa's negligible.

.

2.

Clarification of Appendix ~J Requirements

The-licensee commented on some'of the' clarifications: submitted in=

.

inspection report 89015._ The inspectors and the licensee discussed the

clarifications and commentsc and concluded that there was no disagreement'

in regard to the clarifications.

Additionally, the effect of air sources _ inside.coritainment (such as the

l

CRD accumulators).on the CILRT_, and the effects of readability and=

sensitivity of instrumentation, as discussed with the licensee during

the test, have been formalized into clarifications. These clarifications

,

are presented below.

I

a.

All air sources left inside containment.duringLa CILRT should be

vented to atmosphere during the test.. If they are not vented,-they:

need to be monitored. The CILRT penalty taken must take into account

-

the readability and- sensitivity ofl the~ monitoring instrumentation.

~

If the air sources are neither vented or; monitored, the penalty added

to the CILRT results must assume that the air _ source went from its

design pressure to the test pressure during the: course of'the. test.

l

a

-

3

1

1

nr

,

,

,.

-

. ! .

_

,

.

..

.

'

a

t,

b.

When determining the results of-the Type B and C tests, the licensee

needs to account for the minimum readability, accuracy, and sensitivity

of the instrumentation used. No leakage rates should be reported as

zero, but should be reported as the minimum discernable value.

I

3.

Exit Meeting

Following review of all the data submitted by the~ licensee, an exit

interview was conducted by telephone on April- 16, 1990.- The inspectors

summarized the scope and conclusions.of the inspection. _The licensee

- acknowledged these conclusions, as discussed above. The inspectors also

discussed the likely informational content of the inspection report with

regards to documents or processes reviewed by the inspectors during the

inspection. The licensee did not identify any- such documents. or. processes -

as proprietary.

!

i

!

'!

!

!

I

~i

i

i

!

i

!

!

1

I

.. f

-

4

t