ML20032D657

From kanterella
Jump to navigation Jump to search
IE Insp Rept 50-373/81-28 During Aug,Sept & Oct 1981. Noncompliance Noted:Failure to Conduct Proper Evaluations & Reviews of Test Results
ML20032D657
Person / Time
Site: LaSalle Constellation icon.png
Issue date: 11/06/1981
From: Hopkins J, Jackiw I, Lanksbury R, Maura F, Peschel J, Ring M, Robinson D, Williams C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML20032D653 List:
References
50-373-81-28, NUDOCS 8111170361
Download: ML20032D657 (16)


See also: IR 05000373/1981028

Text

f

.

.

U.S. NUCLEAR REGULATORY COMMISSION

OFFICE OF INSPECTION AND ENFORCEMENT

REGION III

Report No. 50-373/81-28

Docket No. 50-373

License No. CPPR-99

Liceraee: Commonwealth Edison Company

P. O. Box 767

Chicago, IL 60690

Facility Name: La Salle County Station, Unit 1

Inspection At: La Salle Site, Marseilles, IL

Inspection Conducted: August 11, 12, 17-21, 25-28, September 1-4, 8-11,

15-18, and October 8, 1981

/1 zk unL

Inspectors:

F. M ura (August 17-20. 25-28,

//'6'f/

September 8-11, 17, 18, and October 8)

.

]L 'f

~ t 20, 21, 27 and

,f . g . g;

f

.-

opkins Augas

J.6

~~

/

September 11)

'

'

~I.}aciwIg

.

August. 26, 27, September 3,

// ~ 4 ~ / /

4, 17, 18 and October 8)

-

p_

.'j, an sb

~

  1. - 6 - 5' /

y

9h

1

M. Ring (August 20, 21, September 2-4,

d[6/f/

10, 11 a,nd 18)

d ober 8)

8-5 V>

/'

96

~

y

,

J., eEcN1 (October 8)

///f./F/

c,

,,

,D.'

gust 18-21, 25-27

8-41/

f ',Iob ' n

and September 17-18)

sA

f

.n

Approved By:

I. N; Jackiw Acting Chief

/- 4 -d'/

Tes(Progr[,Section

8111170361 811106

gDRADOCK 05000373

PDR

.

,

.

,

Inspection Summary

Inspection on August 11, 12, 17-21, 25-28, September 1-4, 8-11, 15-18,

and October 8, 1981 (Report No. 50-373/81-28)

Areas Inspected: Routine, unannounced inspection to review preoperational

test procedures and results, startup program test procedures review, pre-

vious open items and material traceability of piping in selected systems.

The inspection involved 464 inspector-hours on site by eight NRC inspectors

including 30 inspector-hours onsite during offshifts.

In addition, the

inspection involved 490 inspector-hours of inspection effort at the regional

of fice by five NRC inspectors.

Results: Of the five areas inspected no items of noncoapliance were iden-

tified in two areas. Within the three remaining areas five apparent items

of noncompliance were identified (failure to conduct proper evaluations

and reviews of test results - Paragraphs 3.a., 3.b., 3.d.; failure to

ensure pipe meets FSAR design requirement - Paragraph 8.a.; failure to

maintain material traceability records - Paragraph 8.b.; failure to control

work done on drywell liner - Paragraph 7. ; failure to control a design

document - Paragraph 3.e.).

!

l

t

I

i

-2-

L

-

.

DETAILS

1.

Persons Contacted

      • B. Stephenson, Project Manager
  • R. Holyoak, Station Superintendent
  • L. De1 George, Licensing Administrator
    • H. Morris, Engineer, Project Engineering
  • T. Watts, SNED Project Engineer
  • R. Bishop, Assistant Superintendent

J. Coonan, Assistant Superintendent, Maintenance

  • W. Huntington, Assistant Technical Staff Supervisor

E. Pfister, Lead Nuclear Engineer

    • R. Rose, Lead Structural Engineer, Construction

J. Harchut, Engineer, Construction

    • D. Skoza, Engineer, Construction
    • D. Shamblin, Engineer, Project Management
    • T. Quaka, Construction QA Superintendent
    • R. Braun, Construction QA Supervisor
  • R. Kyrouac, Operations QA Supervisor

4

M. Wherry, QA Supervisor, Morrison Co.

R. Turkowski, GE Lead STD & A Engineer

Sargent and Lundy Engineers, Inc.

    • A. Walser
    • V.

Reklaitis

    • R.

Cheboub

The inspectors also interviewed other licensee employees including

members of the construction, quality assurance, technical and operat-

ing staff and employees of Morrison Co., Foley Co. and Zack Co.

  • Denotes those attending the exit interview of September 18, 1981.
    • Denotes those attending the exit interview of October 8, 1981.

l

      • Denotes those attending the exit interview of September 18 and the

meeting of October 8, 1981.

2.

Licensee Action on Previous Inspection Findings

(Closed) Noncompliance (373/80-36-02) and Unresolved Item (373/80-

15-09) Failure to centrol motor operated valve torque switch settings.

The inspector verified that the licensee issued a revised motor

operated valve torqee switch setting list and that the Station Nuclear

Engineering Department (SNED) by letter dated November 25, 1980

defined how the list was to be used. Additional instructions were

issued by SNED on June 16, 1981.

(Closed) Open Item (373/80-15-08) Foreign material in reactor vessel

and internals. The inspector reviewed NCR li415, closed on March 11,

1981, and determined that the licensee completed the cleaning of the

steam separator assembly.

-3-

i

,

._

.

(Closed) Open Item (373/80-25-06) Missing cable termination card.

The inspector verified that Foley Electrical Co. generated a "to"

termination card for cable number 158 on August 5,1981. According

to Foley's QA Supervisor the field terminations were verified in

November, 1978.

(Closed) Open Item (373/80-25-12) High pressure bypass leakage

preoperational test. Amendment No. 54 to the FSAR reclarified the

high pressure bypass leakage test as a construction test.

(Closed) Open Item (373/78-33-02)

ILRT performance with liner channel

plugs installed. The inspector informed the licensee that NRC's

position was that the ILRT had to be performed with the liner channel

plugs remcVed or an exemption obtained from NRR. On September 1 and

October 1,1981, the licensee submitted their justification for not

venting the liner channels to NRR.

(Closed) Open Item (373/80-49-01) Air leak rate testing of certain

ECCS penetrations. The inspector verified that the licensee has

revised PT-PC-101 to air test all the penetrations which could

lose their water teal during a postulated LOCA with loss of offsite

power and the fa2 Wre of their ESF division diesel generator.

(Closed) Otem Item (373/80-49-03) PT-PC-101 summary sheets did not

include several ECCS penetrations being air tested. The inspector

verified that Rev.

23 to PT-PC-101 revised Data Sheets 12.11 and

12.13 to include all ECCS penetrations being air tested.

(Closed) Open Item (373/81-20-07) Margin load test for diesel

generator 2A. The inspector reviewed the Unit 2 loads required for

Unit I operation and determined that a margin load test is not re-

quired at this time. For Unit 1 operation the total load is approxi-

mately 15% of rated and the largest single load is approximately 10%

of rated.

(Closed) Open Items (373/79-37-01 and 02)

Incorporation of additional

acceptance criteria on STP-5, CRD System to correspond with prototype

testing results of the new thin blades. The licensee and the General

Electric Company have taken the position that additional criteria is

not necessary, that they were added to the Zimmer program to demon-

strate the adequacy of the original test program. The inspector

stated that he will review the test results against the criteria

developed for Zimmer which is based on prototype test results.

(Closed) Open Item (373/80-36-03) The item involved test procedure

SD-WE-101E (Sump Monitoring) not specifying acceptance criteria con-

sistent with the proposed technical specification limits. The

inspector determined that consistent acceptance criteria are now

specified in the test procedure.

(0 pen) Open Item (373/81-07-03) This item dealt with how test pro-

cedure PT-IN-101 (Primary Containment Instrument Air) satisfied

-4-

L

.

-

Section C.4 of Regulatory Guide 1.80 relating to flow and temperature

of the product ain. The licensee stated that no further actions

had yet been taken on this item. The item remains open pending

further discussions with the licensee.

(Closed) Open Item (373/79-06-03) This item dealt with ensuring

that true specific gravity readings are monitored during battery

surveillance by correcting for electrolyte level changes. The

inspector reviewed surveillance procedure LOS-DC-Q2 Revision 0,

Charging Requirements and Battery Readings for Safety Related

250 V DC and 125 V DC Batteries, dated July 21, 1981 and determined

that electrolyte level readings are recorded and subsequent specific

gravity corrections are provided.

(Closed) Unresolved item (373/78-23-01) This item dealt with PT-AP-102

failing to demonstrate that the battery chargers can recharge their

respective Division 1 or 2 batteries within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> while supplying

normal plant D.C. loads. 1.dditionilly, the Division three hattery

charger (HPCS) was not demonstrated to recharge from minimum to fully

charged while carrying maximum steady state loads within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

The licensee has since demonstrated and defined fully charged and

normal loads. The time frame of 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> has been deleted from the

FSAR paragraph 8.3.2.1.1 which now reads "a time commensurate with

the recommendations of the battery vendor." The SER (Safety Evalua-

tion Report), however, still expected the recharge to occur within

the 12 hour1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> time frame. The Division three battery charger has been

moved to another procedure which has been revised to incorporate the

above requirements. Discussion with NRR (J. Knox) indicates the 12

hour time frame in the SER is no longer applicable.

(Closed) Noncompliance (373/81-22-19): Failure to use an approved

procedure while performing maintenance. The inspector found that

the Work Request in question has received a review, and a procedure

containing applicable portions of the vendor's manual was written

and approved in accordance with Figure 9 of the Station Quality

Assurance Manual. Maintenance personnel have been instructed to

submit procedures containing the applicable portions of the vendor's

manual for on site review.

(Closed) Noncompliance (373/81-22-20): Failure to write a Deficiency

Report. The inspector found that Deficiency Reports were written for

the identified condition. Engineers involved in testing have been

instructed by the Project Manager of the need to document deficient

conditions with a Deficiency Report.

(Closed) Unresolved Item (373/81-22-21): Failure to implement a

Preventive Maintenance Program. The licencee has issued LAP-300-8,

Rev.

O,9/81. Preventive Maintenance Program. The inspector found

the references contained in LAP-300-8 were available and the program

was being implemented.

-5-

t

-

.

(0 pen) Unresolved Item (373/81-22-22): Failure to implement a

Housekeeping and Fluid System Cleanliness Program. The inspector

found that LAP-300-16, Rev.

O, 9/81, Cleanliness Control, has been

issued and appears to meet industry standards, however, LAP-900-15,

Rev. 4, September 1981, Housekeeping Practices, does not meet industry

standards for maintenance activities occurring during the operational

phase which are comparable i nature and extent to related activities

occurring during construction. The licensee stated that LAP-900-15,

Rev. 5 was in the review pt- -ss and it would meet the industry standards.

(0 pen) Unresolved Item (373/. -22-23): Failure to establish a "Q list".

The inspector found that the t'censee had not established a list covering

all activities addressed by tl' QA program, nor has he defined how the

program will be applied to the non-safety-related/ASME Section III

Activities. The licensee stated that a procedure or guideline would

be developed defining how to determine what is on the Q list and de-

fining to what extent the QA program will be applied to the non-

safety-related/ASME Section III Activities listed in Quality Require-

ment 2.

(0 pen) Unresolved Item (373/81-20-10): Failure to verify diode

integrity. The inspector found that LES-DG-101 has been changed to

require a yearly verification of blocking diode integrity, but there

is no procedure referenced to describe the verification process. The

licensee stated that a repair manual will be written to provide a

procedure for diode verification.

(0 pen) Unresolved Item (373/81-20-11): Failure to refurbish the diesel

generator crankcase pressure switch on a periodic basis. The inspector

found that the licensee has not revised the surveillance procedure to

include the crankcase pressure switch.

(0 pen) Unresolved Item (373/81-20-15): Failure to provide for re-

furbishing diesel generator air start motors no later than every 50

starts. The inspector found that a surveillance procedure that will

monitor diesel starts and call for start motor refurbishment has been

drafted, however, it has not been incorporated as part of the surveil-

lance program.

3.

Review of Preoperational Test Procedures and Test Results

The inspectors reviewed the following test procedures and test

results against the FSAR, the SER, Regulatory Guide 1.68, and the

,

QA Manual and found them satisfactory unless otherwise noted.

Deficiences which remain unresolved cust be reviewed by QA prior to

system release for operation.

At that time, all items which must be

corrected prior to fuel loading will be identified. Open items

covering the inspector review of the corrective actions taken by the

licensee appear with each preop test listed below.

a.

PT-SC-101, Standby Liquid Control System and SD-PS-101, Process

Sampling System.

-6-

.

(1) FSAR Table 14.2-54 Test Procedure Item No. 5 states that

upon completion of all previously stated tests, the standby

liquid control tank is filled with the required boron solu-

tion, mixed and sampled and that this will be accomplished

just prior to fuel loading. A:ceptance criteria-#7 states

that " liquid mixing results in a uniform solution and

samples are rep *2sentative of storage tank liquid." The

test procedure did not require testing to ensure that the

air sparging sub-system could promote adequate mixing to

satisfy this cammitment.

A review of the test results in the completed procedure

indicated that the station and the station nuclear engineer-

ing department (SNED) initial review of the procedure had

failed to note that this commitment had not been met and

4

thus a deficiency had not been generated as required by

LSU 200-2, to allow tracking of the commitment to ensure

its performance prior to fuel load. A later review by

SNED did note that this commitment had not been performed,

,

however, SNED failed to adequately ensure that the station

was tracking this commitment.

The inspector reviewed an unofficial draft of a master

pre-fuel load checklist that was being used by the station

to track the above commitment and concluded that the item

identified on the checklist by the station does not meet

the acceptance criteria of the FSAR but instead only

ensures that the technical specification requirements are

met.

(2) FSAR Table 14.2-71 Test Procedure Item No. 4 states that

a verification will be made that all sensors in the pro-

cess sampling system are properly located in accordance

with design. The test procedure did not specifically

require this verification be made to ensure that data

taken by the licensee to evaluate actual chemistry con-

ditions to technical specification limits was valid and

to satisfy this commitment.

The licensee contended that this commitment was met by the

test engineer walking down the system, as required by stat -

lon procedure LSU 100-2; however, a review of this procedure

by the inspector revealed that it has no specific require-

ment to. verify system components are correctly located.

'

In addition, the preoperational test procedure did not

reference this procedure, so no documentation existed in

the test package that the FSAR commitment had been met.

The above two items are considered to be violations of

10 CFR 50, Appendix B, Criterion V and XI, and are an

example of an item of noncompliance (373/81-28-01A).

(3) Open Item (373/81-28-02) Unresolved deficiencies, PT-SC-101.

-7-

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _

_

. _ _ _ _

_ _ _ - __ _________

.

Open Item (373/81-28-03) Unresolved deficiencies, SD-PS-101.

b.

PT-NB-101, Nuclear Boiler System

(1) A review of the test results in the completed procedu.4

and the test evaluation indicated that the station and

the station nuclear engineering department (SNED) had not

noted, nor evaluated during their reviews the following

dir4repancies:

(a) the test data showed that the level

3 (12.5" above instrument zero) scran trip switches and

ADS permissive switches reset at a lower value than the

what they tripped at, (b) some of the level 8 (55.5" above

instrument zero) RCIC turbine and HPCS injection valve

closure trip switches reset at a higher value than the value

they tripped at, (c) that one of the level 2 (-50" below

instrument zero) HPCS initiation and Division 3 diesel

generator start switches reset at a lower value than the

value it tripped at.

This is one of the ten procedures

that was re-reviewed by SNED in response to a previous

item of noncompliance (Report No. 373/81-20).

Based on subsequent investigation by the licensee and the

inspector, including discussion with the switch vendor and

General Electric and review of the most recent calibration

sheets, it was concluded that the problem appears to not

be with the switches but may be caused by the testing method.

The licensee was requested by the inspector to make a com-

plete evaluation of the problem and determine if any further

testing is required.

The above item is considered to be a violation of 10 CFR 50,

i

Appendix B, Criterion XI, and is an example of an item of

noncompliance (373/81-28-01B).

'

(2) Open Item (373/81-28-04) Unresolved deficiences, PT-NB-101.

c.

SD-SA-101, Service and Instrumene Air System

(1) FSAR Section 9.3.1.2.1 states that the design of each air

compressor is such that its capacity is 1750 SCFM at 115

psig discharge pressure. The test procedure required the

measuring of the time it took the air compressor to pump air

into its air resovoir from a discharge pressure of 90 psiF

to 110 psig and then using this determination to figure the

capacity of the compressor.

The test evaluation failed to show that the calculated

capacity, (which is greater than 1750 SCFM, as measured

at a discharge pressure of between 90 and 110 psig) is

equal to or greater than the design capacity specified

in the FSAR. The inspector has requested that the licensee

evaluate the data and determine that the air compressors'

-8-

.

-

.

.

-

.

capacity at a discharge pressure of 115 psig is in accord-

ance with the FSAR requiren.ents. This is considered an

Unresolved Item (373/81-28-05) pending receipt of the above

requested data.

(2) Open Item (373/81-28-06) Unresolved deficiencies SD-SA-101.

d.

PT-VP-104, Primary Containment Chilled Water, and

'

PT-VP-101, Primary Containment Vent and Purge

(1) The licensee has issued a tabulation of Motor Operated

Valve switch settings entitled " Motor Operator Data" and

via letter, T.E. Watts to R. H. Holyoak dated November 25,

1980, stated that "all safety-related motor operated valve

torque switch settings must be within the range indicated

in the " Motor Operator Data" list dated October 29, 1980.

The test engineer's evaluation of PT-VP-101 on page 32

attempted to update the switch settings to match the list.

However, four valves IVQ034, IVQ041, IVQ042 and IVQ043

were done incorrectly resulting in incorrect switch sett-

ings on the valves. Failure to correctly specify the

torque switch settings is considered to be a violation

of 10 CFR 50 Appendix B, Criterion V and is considered to

be an item of noncompliance (373/81-28-01C).

(2) The inspector questioned the torque wrench method of

verifying proper opening set points for the vacuum breaker

valves in PT-VP-101. Review of the torque values specified

and their method of application was not complete as of

this inspection. This item is an unresolved item (373/81-

28-07) pending completion of the review.

(3) Open item (373/81-28-08) Unresolved deficiencies PT-VP-101.

(4) Open Item (373/81-28-09) Unresolved deficiencies PT-VP-104.

'

e.

PT-VP-202, Post LOCA H Control

2

(1) During the performance of PT-VP-202, Post LOCA H Control,

2

the test engineer identified 3 valves; 2HG-MV-10, 2HG-FV-1

and 2HG-FV-2 whose torque switch settings were not listed

in the Motor Operator Data book and kept. in Central File.

Follcwing identification of the problem, the resolution was

to set the valves to the same settings as the identical Unit

I valves. The torque switch settings for these valves were

also not in the Motor Operator Data book, however, their

settings had been previously taken from name plate data.

The original deficiency had been identified and cleared,

test procedure PT-VP-202 had been performed and its results

had been reviewed in May 1981. The inspector reviewed the

procedure and the. Motor Operator Dat.a book on September 11,

1981 and noted that the Motor Operator Data book had not

-9-

_j

L

-

.

been updated to reflect the missing valves. No open de-

ficiency existed at the site to indicate that the book was

incomplete. Additionally, three valves, 2HG018, 2HG002-A,

and 2HG002B, were noted, by the test engineer to have con-

flicting settings between the Motor Operator Data book and

the name plate data. The SNED response to the deficiency

stated that the valves should be set to the name plate data

and that the Motor Operator Data book should be changed.

As of the inspector's review on September 11, 1981, the

Motor Operator Data book had not 1.een changed and no docu-

mented deficiency existed at the site indicating the book

was incorrect. The above examples show a failure to provide

adequate controls for a document which prescribes activities

affecting quality. This is considered to be a violation of

10 CFR 50, Appendix B, Criterion VI and is considered to be

an item of noncompliance (373/81-28-10).

(2) Cpen Item (373/81-28-11) Unresolved deficiencies PT-VP-202.

f.

PT-RD-101B Rod Sequence Control. Unresolved deficienies, Open

Item (373/81-28-12).

g.

PT-RD-101A, Rod Drive Control and Rod Position Indication.

Unresolved deficiencies, Open Item (373/81-28-13).

h.

PT-VD-101, Diesel Ventilation, Unit 1.

Unresolved deficiencies,

Open Item (373/81-28-14).

i.

PT-VD-201. Piene'; Ventilation, Unit 2, Unresolved deficiencies,

Open Item (373/81-28-15).

J.

PT-VY-201, CSCS Equipment Cooling, Unit 2.

Unresolved deficiencies,

Open Item (373/81-28-16).

h.

SD-FC-101, Fuel Pool Cleanup. Unresolved deficiencies,

Open Item (373/81-28-17).

1.

SD-HD-101A, Heater Drain. Unresolved deficiencies,

Open Item (373/81-28-18).

n.

SD-HD-101B, Moisture Separators and Reheaters. Unresolved

deficiencies, Open Item (373/81-28-19).

o.

SD-CX-102, Rod Worth Minimizer. Unresolved deficiencies,

Open Item (373/81-28-20).

4.

Preoperational Test Results Review

The inspector reviewed the results of completed test procedures

PT-AP-102 and PT-AP-202 D.C. Distribution for Units 1 and 2 re-

spectively. For PT-AP-202, only the portion required to support

the Unit I fuel load was reviewed. The following problems were

noted:

- 10 -

.

. .

..- _

.

-

,

.

-

4

.

'

a.

Paragraph- 10.3.B.2.c of PT-AP-102 250 V Battery No I requires

that the individual cell voltage, specific gravity and temperature

.of each cell and the bus voltage be recorded on Data Sheet 12.1d.

Instead, the licensee recorded every 6th cell temperature. No

procedure change was made and the discrepancy was not noted in

the evaluation.

.

b.

During the 24 V Battery acceptance tests for all four batteries,

paragraph 10.3.G.2.g (and similar paragraphs for the remaining

,

'

batteries) required that cell voltage reading be taken hourly

for the first three hours of the discharge and then every 15

minutes until the end of the discharge. The' inspector noted that'

data sheets 12.4e, f, g, and h, were issued with a one half hour

gap between 3 and 3.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br />.

i

These items are considered to be violations of 10 CFR 50,

Appendix B, Criterio XI and V and are examples of noncompliance

1

(373/81-28-01D).

The inspectors also noted that page 8-16 of the SER states the

following:

"Each Division 1 and 2 battery charger as well as

each high pressure core spray (Division 3) battery charger has

sufficient capacity to restore its battery to full charge under

the maximum steady-state load." Page B 1-39 of the FSAR describ-

'

ing the licensee's commitment to Regulatory Guide 1.32 was revised

by Amendment 55 dated March 1981 to state the same cords as

quoted above from the SER. The licensee's procedure demonstrates

the capability to recharge the battery under normal loads but

not under "rcaximum steady state loads." The licensee contenas

that, the statement on page B 1-39 only describes the battery

.

chargers capability and not what oney would be required to do

{

by test.

NRR (J. Knox) concurs with the licensee's position.

i

5.

Preoperational Test Procedure Verification

The inspectors verified that the following preoperational test

!

procedures appear to meet the requirements of Section 14 of the FSAR,

and were reviewed, and approved by licensee management in accordance

with the requirements of Regulatory Guide 1.68 and the licensee's QA

Manual, unless noted otherwise:

l

a.

PT-MS-101B, Mainsteam Isolation Valves and Instruments.

-

b.

PT-MS-101A, MSIV Leakage Control System.

c.

PT-VP-104, Primary Containment Chilled Water

l

d.

PT+VD-101, Diesel Ventilation

e.

PT-VE-101, Auxiliary Electrical Equipment Room HVAC.

f.

PT-VJ-101, Machine Shop HVAC.

g.

PT-VL-101, Laboratory HVAC.

,

h.

FT-V0-101, Off-Gas Building HVAC.

i.

PT-VP-103, Primary Containment HVAC.

4

- 11 -

,

,

-

--

, ,,

--v.<..,-,

-,

---,r

. . ,

.

- - - - - - - .

--m..

e

yev.+

+-

-

- - - ,

-

--,t

-- y

e+

s

.

-

e

J.

PT-VP-102, Post LOCA Hydrogen Control.

k.

PT-VC>101, Control Room HVAC.

,

The procedure did not verify air flow through all personnel

access points is out leakage rather than in leakage as required

by table 14.2-17 of the FSAR. This utficiency had been pre-

viously identified by the licensee and is still open as a pro-

cedure deficiency. This deficiency is an open item (373/81-28-21)

pending the addition of the verification to the procedure.

1.

PT-ST-102, " Vibration Monitoring Preoperational Tests"

FSAR Table 14.2-16, Test Procedure Item No. 2, states in part

that the inspection for visually perceivable vibration includes

branch piping from the main flow paths greater than two inches

in diameter. The test procedure requires looking at branch

piping greater than two inches in diameter, up to the first

support, for visually perceivable vibration.

If vibration is

noted then the remainder of the branch piping will be inspected.

The inspector has questioned whether the licensee's test pro-

cedure meets the FSAR commitment since the FSAR implies that all

branch piping will be inspected and not just the branch piping

up to the first support. This is considered an Open Item

(373/81-28-22) pending further review by Region III technical

inspectors.

m.

PT-CM-101, Containment Monitoring Preoperational Test.

FSAR Table 14.2-7, Test Objective item No. 1.f. states that one

of the parameters to be tested is suppression pool bulk water

temperature. The test procedure does not currently contain

any provision for testing this parameter. The licensee is

currently pursuing a technical specification change and upon

approval of this change plans to submit a FSAR change to

delete the requirement for testing the suppression pool bulk

water temperature. This is considered an Open Item (373/81-

28-23) pending resolution by the licensee and review by the

inspector.

n.

PT-HC-101, Reactor Building Crane

o.

PT-VX-101, Switchgear lleat Removal System

p.

PT-RA-101, Reactor Protection System

q.

PT-RP-102, Remote Shutdown System

r.

PT-VW-101, Radwaste Area HVAC System

s.

PT-PC-103, Primary Containment Isolation System

t.

SD-CQ-101, Communications System

u.

SD-EH-101A, Turbine Electrohydraulic Control System

6.

Review of Startup Program Test Procedures

The following startup program test procedures were reviewed and

found to meet the requirements of the FSAR, 3ER, Regulatory Guide 1.68, and the licensees QA Manual:

- 12 -

'

.

a.

STP-3, Fuel Loading

b.

STP-4, Full Core Shutdown Margin

c.

STP-11, LPRM Calibration

d.

STP-12, APRM Calibration

e.

STE-13, Process Computer

f.

STP-18, Core Power Distribution

g.

STP-19, Core Performance

h.

STP-1, Chemical and Radiological (review consisted of the

water chemistry portion only)

i.

STP-14, RCIC. The licensee had not incorporated the vendor's

comments at the time of the inspection. This item remains open

(373/81-28-24) pending the incorporation of GE's comments.

j.

STP-16, Process Temperature

k.

SIP-70, Reactor Water Cleanup

1.

STP-71, RER

7.

Containment Liner

A major portion of the containment drywell liner was inspected in the

company of licensee representatives.

Items of concern were identified

and their location recorded. They included liner plate bulges, weld

burn marks, undercuts, and " temporary brackets. Neither the licensee

nor its subcontractors could produce documentation to demonstrate

that the " temporary" work done against the liner had been controlled.

All four subcontractors denied responsibility for any of the brackets

welded on the liner. Failure to control the welding of " temporary"

brackets to the containment liner through the use of drawings

and/or procedures to identify their location, purpose, etc. , and

their correct disposition is considered to be a violation of

10 CFR 50, Appendix B, Criterions V and IX and the QA Manual,

Quality Requirements 5.0 and 9.0 and is an example of an item of

noncompliance (373/81-28-

T.

Among the items identifie

ce nine areas where the liner had

bulged inwards.

In most

.s the bulges appear to have been plate

distortions generated dur

, the initial construction of the liner.

The peak radial deflectior is in the range of 1/2" to 1".

While no

attempt was made to determine their volume the surface area of the

bulges is estimated to range between 150 to 400 square inches. All

bulged areas sounded as though they were not backed by concrete when

l

struck with a hammer. They sounded hollow. The adjacent areas of

the liner sounded like they were backed by concrete. The extent of

the apparent " voids" associated with the apparently buldged area of

r

the liner could not be determined. The licensee was asked to deter-

mine if:

a.

the existance of the buldged and apparently unbonded to concrete

area are acceptable during a LOCA,

b.

there are any detrimental long term effects caused by periodic

CILRT,

- 13 -

,

.

-

.

c.

if the buldged and unbonded area are associated with any possible

concrete imperfections

d.

the noted buidges traverse areas of the liner defined by the

location of the liner plate concrete L anchors, which could

indicate separation of an L anchor from the liner plate. The

inspectors noted that one buldged area involved the apparent

location of a liner concrete L anchor.

Meetings on this subject were held un October 1 and 8, 1981, becween

Region III personnel and members of the licensee's staff. During

the meeting on October 8, 1981, the licensee stated that based on

an engineering evaluaticu of the containment liner deformations

(conducted by CECO and SJL engineers), it was concluded that the

liner met all the design criteria and was structurally sound. The

licensee and their engineering contractor also stated that the

deformations were results of welding of the embedments and that the

,

structural integrity test did not cause any outward deformations,

therefore no voids of any significant magnitude can exist.

At the conclusion of the October 8, 1981 meeting the licensee was

'

requested to document their conclusion and send a report of their

engineering evaluation to Region III.

It was requested that the

report include:

a.

Identification and categorization of the deformations on the

liner and specifically those deform, tions that span over two

anchors,

b.

Any surveillance program the licensee plans to initiate to mor.itor

the condition of the deformations, and,

c.

All empirical data to support the cenclusion that with the

deformatior_, the integrity of the containment liner has not

been compromised and also that the concrete behind these

deformations is free of imperfection.

This is an open item (373/81-28-26) pending review of the licensee's

actions.

8.

Containment Leak Rate Tests

The licensee plans to perform the containment integrated leak tests

after fuel loading, but prior to operation requiring containment

integritr, using the surveillance procedure developed for periodic

ILRTs'. The licenst.e stated that Pa is being recalculated and the

results will not bc v.ailable until October at the earliest. The

inspector stated that:

a.

If the new calculated Pa exceeds the pcessure at which the

November 1980 test was conducted, the origina. preoperational

test will be considered invalid.

- 14 -

t

.

b.

Region III has no objection to the test being performed after

fuel loading and prior to containment intergrity requirement

provided the licensee keeps NRR informed and obtains a waiver

from any FSAR requirements. Additionally, the preop must be

performed prior to fuel loading, if the original test becomes

invalid.

9.

Component Traceability

The inspectors conducted an audit of piping in the 1 B diesel

generator air start system, the standby liquid control system,

control rod drive system and drywell pneumatic system. The

findings were as follows:

a.

Lines 1 HP 77 AB 2 and 1 HP 77 AA 2 which connect air receiver

tanks A, B, C, and D to the 1 B diesel air start motors were

inspected. No identification numbers, other than at fittings,

could be located.

In most cases the line had been painted,

however a few sections of new pipe remained unpainted. The

.

licensee was asked why the unpainted sections of pipe had no

merkings and to what code it had been built.

In response to

the inspectors inquiry the licensee reviewed the auxiliary

systems for the two General Electric supplied diesel generators

and determined that while piping supplied by the manufacturer

as an integral part of the diesel package did not have to meet

ASME Section III-1074 requirements, all changes made by CECO

had to meet those requirements. As a result, NCR No. 538 was

written to replace 20 sections of pipe within the starting air,

cooling water, and fuel systems of diesel generators 1 B and 2 B

in order to comply with the requirements of Table 3.2-1 of the

FSAR.

Failure to podify sections of the two HPCS diesel generators

system in accordance with FSAR Table 3.2-1 is considered to be

a violation of 10 CFR 50, Appendix B, Criterion III and the

Q. A. Manual, Quality Requirement 3.0 and is an example of

an item of noncompliance (373/81-23-27).

b.

Approximately ont third of lines 1 SC 02 AA 1 1/2 and

1 SC 08 AA 3/4, frca the SLCS pump 1 A to the explosive valve,

was inspected. A section of pipe between welds WSC-45 and 46

was found to be marked with heat number B 2155 while LLe as

built drawings indicated the heat number to be 70362. The

inspector determined that both heat numbers were acceptable;

however, the licensee was requested to determine why correct

traceability had not been maintained. The licensee performed

an audit of approximately 70 components (pipes and fittings)

within the same two lines and determined that a total nf five

code cr heat numbers were incorrect. They included two sections

of pipe, one elbow, ore. flange and hex nuts. According to the

licensee the problem appears to be a cocumentation transfer

error, which occurred when the informe: tion was transferred from

- 15 -

.~

_

_

,

1

.

,

e

the " cut sheet" (generated at the time the material is selected)

to the isometric drawing Bill of Materials list. The errors

were corrected in revision M to isometric Dwg. F-SC-1201.

At

the inspector's request the licensee performed an audit of

additional piping in the SLCS above elevation 820' which in-

volved over 150 components in eleven isometric drawings. No

additional errors sere found.

c.

A section of pipe in the drywell pneumatic system isometric

drawing No. IN-215 was found by the inspector to contain two

heat numbers, 745333 (engraved) and 783234 (stenciled). A

review of the material certification records showed both heat

numbers to be acceptable. The licensee corrected the error

by removing the engraved number (745333) and engraving the

correct number 783234.

Failure to maintain adequate traceability of the five items

in the standby liquid control and the one item in the drywell

pneumatic systems is considered a violation of 10 CFR 50,

Appendix B, Criterion VIII and the QA Manual, Quality Re-

quirement 3.0 and is an example of an item of noncompliance

(373/81-28-28).

10.

Unresolved Items

Unresolved Items are matters about which more information is required

in order to ascertaic whether they are acceptable Items, items of

Noncompliance, or Deviations. Unresolved Items disclosed during the

inspection are discussed in Paragraph 3.c and 3.d.

11.

Exit Interview

_

The inspectors met with licensee representatives (denoted in Paragraph

1) on September 18, 1981. The inspectars summarized the scope and

findings of the inspection.

The licensee acknowledged the statements by the inspectors with respect

to the items of noncompliance (Paragrapha 3.a

3.b, 3.d, 3.e, 7, 8.a,

and 8.b.).

A meeting was held at the licensee's request on October 8, 1981 to

discuss the containment liner findings (Paragraph 7).

- 16 -

--

-

- .