Third Interim Deficiency Rept Re Seismic Qualification of B&W Equipment in Instrument Panels,Originally Reported on 801124.Util & Vendor Continuing Evaluation of Deficiency. Next Rept by 820218
ML20032B368
Person / Time
Site: Bellefonte  
Issue date: 10/28/1981
From: Mills L
TENNESSEE VALLEY AUTHORITY
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
10CFR-050.55E, 10CFR-50.55E, NUDOCS 8111050476
Download: ML20032B368 (2)


Text

_.

.c.$

0

~.

TENNESSEE VALLEY At2T80FilWOh'

.,>NTA.GEC CH ATTANOOG A, TENNESSEE' 37401 400 Chestnut Street Tower II l\\ $. 4 Octobehl28,N9h1 U.0 Ihlt y.

,6 Mr. James P. O'Reilly, Director 7

,\\

,s k

h

,J Office of Inspection and Enforcement-U.S. Nuclear Regulatory Commission kp,,yf g0( 7pgIAA Region II - Suite 3100

  • 72

[', -

101 Marietta Street

'n 1 Atlanta, Georgia 30303 4

[,'3

Dear Mr. O'Reilly:

. p BELLEFONTE NUCLEAR PLANT UNITS 1 AND 2 - SEISMIC QUALIFICATION OF B&W EQUIPMENT IN TVA PANELS - NCR BLN BLP 8011 - THIRD INTERIM hEPORT The subject deficiency was initially reported to NRC-0IE Inspector R. W. Wright on November 24, 1980 in accordance with 10 CFR 50.55(e).

This was followed.by our interim reports dated December 23, 1980 and

' April 23, 1981. Enclosed is our third interim. report. We expect to submit our next report by February 18, 1982.

If you have any questions concerning this matter, please get in touch with R. H. Shell at FTS 857-2581.

Very truly yours, TENNESSEE VALLEY AUTHORITY L. M. Mills, Manager Nuclear Regulation and Safety Enclosure cc:

Mr. Victor Stello, Jr., Director (Enclosure)

Office of Inspection and Enforcement U.S. Nuclear Regulatory Commis.sion h ahington, DC 20555 Mr. James McFarland (Enclosure)

Senior Project Manager Babcock & Wilcox Company

['

P.O. Box 1260 l

Lynchburg, Virginia 24505 37 g$ j l

s/I-I I'

l 8111050476'811028 gDRADOCK 05000438 PDR i

An Equal Opportunity Emptover

ENCLOSURE BELLEFONTE NUCLEAR PLANT UNITS 1 AND 2 SEISMIC QUALIFICATION OF B&W EQUIPMENT IN TVA PANELS NCR BLN BLP 8011 10 CFR 50.55(e)

THIRD INTERIM REPORT -

Description of Deficiency A number of B&W supplied instruments are intended 'for installstion in TVA's free standing, open, local instrument panels. Because of imprecise specifications in a TVA procurement document, the instrumentation supplied by B&W has nov been seismically qualified to a response spectra which is (3

compatible with the response spectra for TVA local instrument pane,ls.

The responsibility for this deficiency is TVA's.

A list of the instruments in question follows:

Iype of Device Manufacturer Mfr ID No.

Diff. Pressure Transmitter Bailey Meter Co.

Type N1BQ8 N3BQ7 N3BQ8 N2BQ7 a

N2BQ8 Press Transmitter N3RS N2KS N1KS Rosemount 1152GP Dresser 1079 1188 Press Switch B400 Series Diff. Press Indicator ITT Barton Model 227 Diff. Press Switch ITT Barton Model 288A Electro / Pneumatic Converter Fisher Model 546 Interim Progress TVA is continuing to evaluate the subject deficiency and is working with B&W toward a resolution.

c.

-