Text
p.3S %
Thomas J. Martin Public Service Electric and Gas Company 80 Park Plaza Newark, N.J. 07101 201/4304316 Vice Presdent Engineering and Construction October 1, 1981 l
~
,/Q r b#
'e~'
,a
,i ss) v - >[r/j/
~
N L Mr. Ronald C. Haynes, Director w,
b 007 f p, 4 U.S. Nuclear Regulatory Commission s
O Cp Office of Inspection and Enforcement 4 gh*e,gJggI4.')
Region 1
~
~
- N %r 631 Park Avenue L
s King of Prussia, Pennsylvania 19406 8
i O
p Dear Mr.
- 1es:
01 POTENTIAL SiGNIFICANT CONSTRUCTION DEFICIENCY SUPPRESSION CHAMBER SEISMIC ANALYSIS NO. 1 AND 2 UNITS (50-354/355)
HOPE CREEK GENERATING STATION On September 4, 1981, a verbal report was made to Region 1, Office of Inspection and Enforcement representative, Mr.
E.
Greenman, advising of a potential significant con-struction deficiency.
The reported potential deficiency concerns seismic design analysis review for the suppression chamber.
Specifically, the action of the water mass in the chamber if a seismic event occurs in a post accident condition with.the chamber completely filled with water.
The following supplemental information is submitted in ac-cordance with the requirements of 10CFR50.55(e).
PSE&G is currently reviewing this concern to deterrine I
reportability per the requirements of 10CFR50.55(e).
This I
assessment is scheduled for completion November 6, 1981, at which time a report will be made to the NRC.
Very truly yours, f'71&
110200506 8i1O01
~
(SDRADDCr,OSOOOggg.
CC:
Office of Inspection and Enforcement Division of Reactor Construction Inspection 1/
Washington, D.C.
c1% D NRC Resident Inspector - Hope Creek P.O.
Box 241
.Hancocks Bridge, N.J.