Monthly Operating Repts for Mar 1994 for McGuire Nuclear Station Units 1 & 2
ML20029C620
Person / Time
Site: McGuire, Mcguire  Duke Energy icon.png
Issue date: 03/31/1994
From: Robert Williams
DUKE POWER CO.
To:
Shared Package
ML20029C621 List:
References
NUDOCS 9404190260
Download: ML20029C620 (10)


Text

. .. _ _ _ __ -

!. . 1 1

l I

OPERAlik6 DATA REPORT DOCKET NO 50;369 DATE Anil 15,1994 i OPERATINS STATUS COMPLETED BY P.A. Williaes TELEPHONE 704-383-R46___ i

1. Unit Nase: McGuire 1
2. Reporting Period: March 1, 1994-March 31, 1994 ,
3. Licensed Thereal Power (MWt): 3411  !
4. Naseplate Pating (Bross MWe): 1305* Notes #Naseplate Fatirig 1 5.DesignElectricalRating(NetMWe): 1100 (Gross MWe) calculated as 1
6. Maxinus Dependable Capacity (Gross NWe): 1171 1450.000 NVA x .90 power
7. Maxisus Dependable Capacity (Net MWe): 1129 factor per Page lii, B. If Changes Occur in Capacity Ratings (!tess Husber 3 Through 7) Since Last NUREG-0020.

Report. Give Reasons: ,

i

9. Power Level To Which Restricted, if Any (Net MWeh i
10. Reason For Restrictions, If any: l This Month Vr.-to-Date Cumulative l
11. Hours in Reporting Period 744.0 2160.0 108096.0 1
12. Number Of Hours Reactor Was Critical '144.0 1373.8 75394.3 l
13. Reactor Geserve Shutdewn Hours --0-- --0-- --0-- 'I
14. Hours Generator On-Line 744.0 1370.8 74590.3 l
15. Unit Reserve Shutdown Hours --0-- --0-- --0--
16. Gross Thereal Energy Generated (MWH) 24263B3 4520073 231245709
17. Gross Electrical Energy Generated (MWH) 835430 1561432 79523587
18. Net Electrical Energy Generated (MWH) 002209 1487450 75921600
19. Unit Service Factor 100.0 63.5 69.0
20. Unit Availability Factor 100.0 63.5 69.0
21. Unit Capacity Factor (Using MDC Net) 95.6 61.0 61.1
22. Unit Capacity Factor (Using DER Net) 91.4 59.4 59.5 l
23. Unit Forced Cutage Rate 0.0 36.5 14.9

{

24. Shutdown Scheduled Over Next 6 Months (Type, Date, and Caration of Each): 1 Refueline - August 19. 1994 - 65 davs l
25. If Shut Down At End Of Report Period. Estinated Date of Startup l
26. Units In Test Status (Prior to Cossercial Operation): Forecast Achieved  !

INITIAL CRITICAllTY INITIAL ELECTRICITY COMMERCIAL OPERAT10M 9404190260 940331 PDR ADOCK 05000369 R PDR e-

,nr- -

w w w..dm v'%,m- mw wa,.

?i OPERAllNG DATA REPORT DOCKET NG 50-369 ilNil McGuire i DATE 62fjll5.1994 COMPLETED BY R. A. Wi.JJ.itas -

TELEPHONE 704-382-5346 MONTH March 1994

~ CJ1 AVERAGE DAILY POWER LEVEL  !!! AVEhABE DAILY F0WER LEVEL (MWe-Nett (MWe-Net!  ;

i 1135 17 '1133 2 1133 18 1136 3 1135 19 1132 4 1112 20 1130 5 270 21 1130 6 392 22  !!28 7  !!24 23 1132 8  !!36 24 1132~

9 1133 25 1127 10  !!31 26 1125 11 1132 27 1131 12  !!34 2B 1131 13 1137 29 1127 14 1134 30  !!23 15 1135 31  !!23 16 1133

UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO. 50-369 -

U N I T N A M E 7 t y u i x t. 1 DATE ve/15/94 REPORT MONTH March 1994 COMPLETED BY x. a. Williams TELEPHONE (/us) 362-dde6 (1) (2) (3) (4) (5)

R MET-E HOD T' A OF LICENSE N Y S SHUT EVENT SYS- CAUSE AND CORRECTIVE O P DURATION O DOWN REPORT TEM COMPONENT ACTION TO

. DATE E HOURS N R/X NO. CODE CODE PREVENT RECURRENCE 2-P 94 4 F --

A --

HH VALVEX HOLD AT 33% POWER DUE TO STEAM GENERATOR "A" MAIN FEEDWATER VALVE FLOW (1) (2) (3) (4)

F Forced Reason- Method: Exhibit G - Instructions S Scheduled A-Equipment Failure (Explain) 1-Manual for Preparation of, Data B-Maintenance or test 2-Manual Scram Ent U Sheets For Licensee Event Report (LER)

C-Refueling 3-Automatic Scram D-Regulatory Restriction , ,

4-Other (Explain) File (hMG- 0161)

E-Operator Training & License Examination F-Administrative (5)

G-Operator Error Exhibit I - Same Source H-Other (Explain) (Explain)

i 1

OPERATING DATA REPORT l

l

( DOCKET N0 50-370 l DATE April 15. 1994 OPERATING STATUS COMPLETED BY . R.A. Willlaes TELEPHONE 704-382-5346

1. Unit Name: McGuire 2
2. Reporting Period: March 1, 1994-March 31, 1994 l 3. Licensed Thersal Power (MWt): 3411 l 6. Naseplate Rating (Gross MWe): 13051 Notes #Naceplate Rad ng
5. Design Electrical Fating (Net NWr):  !!B0 (6ross MWe) calculated as
6. Maxieus Dependable Capacity (6ross MWe):  !!71 1450.000 MVA x 90 power
7. Maxinus Dependable Capacity (Net MWe):  !!29 factor per Page iii, B. If Changes Occur in Capacity Ratings (Itees Nusber 3 Through 7) Since Last NUREG-0020.

Report. 6tye Reasons:

9. Power Level To Which Restricted, If Any (Net MWe):
10. Reason for Restrictions, if any:

This Month Yr.-to-Date Cuaulative

11. Hours in Reporting Period 744.0 2160.0 88392.0
12. Nusber Of Hours Reactor Was Critical 744.0 2017.4 67859.4
13. Reactor Reserve Shutdoun Hours --0-- --0-- --0--
14. Hours Generator On-Line 744.0 2015.1 66891.3
15. Unit Reserve Shutdown Hours --0-- - --0--
16. Gross Thereal Energy Generated (MWH) 2533507 6836200 218708187
17. Gross Electrical Energy Generated (MWH1 891993 2400176 76449111
18. Net Electrical Energy Generated (MWH) B60791 2312114 73278234
19. Unit Service Factor 100.0 93.3 75.7
20. Unit Availability Factor 100.0 93.3 75.7
21. Unit Capacity Factor (Using MDC Net) 102.5 94.8 72.6
22. Unit Capacity Factor (Using DER Net) 98.1 90.7 70.3
23. Unit Forced Outage Rate 0.0 6.7 7.2
24. Shutdown Scheduled Over Next 6 Months (Type, Date, and Duration of Each):

None

25. If Shut Down At End Of Report Period. Estimated Date of Startup:
26. Units In Test Status (Prior to Cessercial Operation): Forecast Achieved INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION

l OPERATING DATA REPORT -j I

DOCLET NO 50-370 l UNii McGuire 2 )

DATE AJril 15._1994 j i

COMPLETED BY R.A.Willians TELEPHONE 704-382-53 %  !

l RONTH March.'1994 QSy. AVERABE DAILY POWER LEVEL I,H - AVERABE DAILY POWER LEVEL (MWe-Net) '(MWe-Net)-

1 1156 17 1157 2 1156 18 1158 3 1156 19 1158 l

4  !!57 20 115B t 5 1157 21 1i58 l

! 6 1157 22 1156 7 1157 23 1158 8  !!58 24 1159 9 1156 25 1157 10  !!56 26  !!56 11 1157 27 1157 s

12 1157 29 1157 13 1158 29 1157 14 1158 30 1154 t 15 1152 31 1155 l.

16 1157 l 0

. - - - . - . _ _ _ . - _ - . _ . - . ~ . . . _ . _ . _ . . . _ _ - _ . - . _ _ _ - _ . _ - . _ - . _ _ . . - _ . . _ . . . _ . . _

UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO. 50-370 -

UNIT NAME Mwuix4 2 .

DATE us/id/v4 March 1994 COMPLETED BY x. A _. Williams REPORT MONTH tive; 302-d346 TELEPHONE (1) (2) (3) (4) (5)

R MET- ,

E HOD T A OF LICENSE N Y S SHUT EVENT SYS- CAUSE AND CORRECTIVE O P DURATION O DOWN REPORT TEM COMPONENT ACTION TO DATE E HOURS N R/X NO. CODE CODE PREVENT RECURRENCE NO SHUTDOWNS OR REDUCTION S (1) (2) (3) (4)

F Forced Reason- Method: Exhibit G - Instructions S Scheduled A-Equipment Failure (Explain) 1-Manual for Preparation of Data B-Maintenance or test 2-Manual Scram Ent y Sheets For Licensee C-Refueling 3-Automatic Scram Event Report (LER)

D-Regulato n Restriction 4-Other (Explain) File ( M EG-0161)

E-Operator Training & License Examination (5)

F-Administrative Exhibit I - Same Source G-Operator Error (Explain)

H-Other (Explain)

I

. l.

_. _ _ - _ - _ _ _ _ _ - _ _ - _ _ _ _ - _ - _ _ _ _ _ = - _ _ _ _ _ - _ _ - . _ - _ - _ _

l i

l I

i l

DOCKET: 50-370 UNIT: McGuire 2 Date: 04/15/94 NARRATIVE SLM GRY MJNIH: March 1994 McGuire Unit 2 began the month of March operating at 100% full power. The unit operated at or near 100% full power for the entire nunth.

l l-l i

l l Prepared by: R. A. Williams l Telephone: (704)-382-5346 l

1 1

MONTHLY REFUELING INFORMATION REOUEST

1. Facility name: McGuire, Unit 2
2. Scheduled next refueling shutdown: November 1994 l
3. Scheduled restart following refueling: January 1995 ]

THE PROJECT MANAGER HAS BEEN ADVISED BY SEPARATE COMMUNICATION OF ANY T.S. CHANGE OR LICENSE AMENDMENT. THEREFORE, QUESTIONS 4 THROUGH 6 WILL NO LONGER BE MAINTAINED IN THIS REPORT.

4. Will refueling or resumption of operation thereafter require a technical specification change or other licence amendment?

If yes, what will these be?

l If no, has reload design and core configuration been reviewed by Safety Review Committee regarding unreviewed safety questions?

5. Scheduled date (s) for submitting proposed licensing action and supporting information.
6. Important licensing considerations (new or different design or supplier, unreviewed design or performance analysis methods, significant changes in design or new operating procedures).
7. Number of Fuel assemblies (a) in the core: 193 (b) in the spent fuel pool: 817
8. Present licensed fuel pool capacity: 1463 Size of requested or planned increase: ---
9. Projected date of last refueling which can be accommodated by present licensed capacity: December 2003 DUKE POWER COMPANY DATE: April 15, 1994 l

l Name of

Contact:

R. A. Williams Phone: (704)-382-5346 i

i l

l l l

.