ML20028C323

From kanterella
Jump to navigation Jump to search
Provides Sixth Quarterly Update of Projected Const Completion Date.Unit Approx 91% Complete as of 821121.Fuel Load Scheduled for Oct 1984
ML20028C323
Person / Time
Site: Catawba Duke Energy icon.png
Issue date: 12/30/1982
From: Tucker H
DUKE POWER CO.
To: Adensam E, Harold Denton
Office of Nuclear Reactor Regulation
References
NUDOCS 8301070336
Download: ML20028C323 (2)


Text

s-v DUKE POWER GOMPANY 1*.o. nox 33180 CliAHI.oTTE, N.o. 28242 II AL 15. TUCKEl{

TE LEPHONE vuee.urpr v (704) 373-4531 December 30, 1982

.mu...o

="

Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Washington, D. C. 20555 Attention:

Ms. E. G. Adensam, Chief Licensing Branch No. 4 Re: Catawba Nuclear Station Docket Nos. 50-413 and 50-414

Dear Sir:

Your June 9, 1981 letter to W. S. Lee requested quarterly updates of the projected construction completion date for Catawba Unit 1.

The following provides information for our 6th quarterly update. Erection status of various commodities for the September, October and November accounting periods are included.

Catawba Unit 1 is estimated to be 91 percent complete as of November 21, 1982.

This completion figure is based on the installation of key commodities such j

as piping, support / restraints, cables, concrete, and instrumentation. The estimate of remaining work includes an end of job projection based on projected scope growth of these commodities.

The Chemical and Volume Control System (NV), the Nuclear Service Water System (RN),

the Ice Condenser Ref rigeration System (NF), and the Component Cooling System (KC) have been turned over to our Nuclear Production Department for further testing.

Our total Construction workforce increased from 3564 on September 19, 1982 to 3635 on December 19, 1982. Second shift work and overtime is used where necessary to complete work on critical systems.

The following quantities of listed Unit 1 commodities were erected during the September, October, and November accounting periods (12 weeks). The " Quantity Remaining to Be Erected" column indicates recently revised end of job estimates.

Quantity Erected Quantity Remaining Commodities During Period to Be Erected Structural Concrete (cy) 1173 21,109 Piping (weighted value) 1243 18,132 Cable Pulls (each) 321 3,517 Cable Terminations (each) 2235 9,891 Instruments (equivalent loops) 357 2,159 Piping Support / Restraints (each) unavailable unavailable (Inspected)

Sob I 8301070336 821230 PDR ADOCK 05000413 R

PDR

t i

Mr. Harold R. Denton, Director December 30, 1982 Page 2 The Catawba Unit 1 Fuel Load Date is scheduled for October, 1984. Current progress indicates that work ie progressing on schedule.

Very truly yours, BV& gf Hal B. Tucker ROS/php cc:

Mr. James P. O'Reilly, Regional Administrator U. S. Nuclear Regulatory Commission Region II 101 Marietta Street, Suite 3100 Atlaata, Georgia 30303 M.r. W. H. Lovelace Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Washington, D. C. 20555 Mr. P. K. Van Doorn NRC Resident Inspector Catawba Nuclear Station Mr. Robert Guild, Esq.

Attorney-at-Law P. O. Box 12097 Charleston, South Carolina 29412 Palmetto Alliance 2135 Devine Street Columbia, South Carolina 29205 Mr. Henry A. Presler, Chairman Charlotte-Mecklenburg Environmental Coalition 943 Henley Place Charlotte, North Carolina 28207 Mr. Jesse L. Riley Carolina Environmental Study Group 854 Henley Place Charlotte, North Carolina 28207